National Highway Construction Cost Index
Download
Report
Transcript National Highway Construction Cost Index
National Highway
Construction Cost Index
Federal Highway Administration
October, 2010
Ralph Erickson
National Highway Construction
Cost Index (NHCCI)
• Replaces the FHWA Bid-Price Index
• Uses Fisher Index to produce a quarterly
index at the National level
• Bid-Tabs data provided by Oman
Systems, Inc.
• Possible extensions
– State level indexes
– Component indexes
Fisher Ideal Index
• “Ideal” refers to the Fisher Index
addressing changing ratios of inputs
– Captures the effects of changes in the relative
importance of different cost items in highway
construction over time
– Minimize substitution biases
Index Data Requirements
• Product requirements for isolating cost
changes
– Specific
– Consistent over time
• Continuity of time series for individual
products (pay-items)
• Sufficiently representative (and large) set
of observations for statistical confidence
Oman Systems, Inc. (OSI) Data
• Captures State web-posted bids awarded
on highway construction contracts
• Partial data back to 1993
• Covers all contiguous States since 2007
• Composed of State-defined pay-items
What State Bid-Items Measure
• Cost of
– Material
– Installation (capital and labor)
– Overhead
– Profit
• Not a measure of pure price changes
– Such as the BLS Producer Price Index
– PPI (for H&S) now discontinued
OSI Data
•
•
With judicious editing, OSI data can meet
the above data requirements for indexes:
Remove pay-item records:
– Non-standard
– Unit of measure (lump sum) issues
– Suspect categories
Non-standard
• Same pay item number but have different
pay item descriptions (or units of measure)
between projects
• Cannot be included due to the differing
types of work from project to project
Unit of measure issues
• There are some pay items where the unit
of measure makes it difficult to track price
changes
– Example:
• Landscaping
• Lump sum =1
• The prices bid on these items are not
related to price trends
Suspect categories
• Categories of work such as start-up costs,
incentives, etc.
– Mobilization
– Alternates/Bonuses/Time
Further Data Edits
•
Eliminate records where pay-items:
–
•
Lack eight quarters of consistent data
Eliminate records where pay-items fail
established variance tests
–
Rationale is to reduce data entry errors
Edit Example
•
Eliminate records for pay-items :
– Maximum observed price is more than 16
times the minimum price
– Coefficient of variation is greater the 42
when evaluating the log of change in price
times 100
– The “16” and “42” above vary by run
Effect of the Edits
• Overall effect of the edits (although large in number) still
leaves a useful dataset for constructing the NHCCI
• Remaining value is representative of all bid tabs
expenditures with almost 40% of the original
observations still available
• The distribution of the expenditure categories which
determine the weights in the NHCCI are largely
unaffected by the edits
Summary
•
•
•
•
•
The new FHWA cost index
Data characteristics
OSI data
Edits to the OSI data
Results
Jun-10
Mar-10
Dec-09
Sep-09
Jun-09
Mar-09
Dec-08
Sep-08
Jun-08
Mar-08
Dec-07
Sep-07
Jun-07
Mar-07
Dec-06
Sep-06
Jun-06
Mar-06
Dec-05
Sep-05
Jun-05
Mar-05
Dec-04
Sep-04
Jun-04
Mar-04
Dec-03
Sep-03
Jun-03
Mar-03
2003 = 1.00
NHCCI Results
1.5
1.4
1.3
1.2
1.1
1
0.9
0.8
0.7
0.6
Resources
• Ralph Erickson
– 202-366-9235
– [email protected]
http://www.fhwa.dot.gov/ohim/nhcci/