Innovation in the Thameslink Programme

Download Report

Transcript Innovation in the Thameslink Programme

Suppliers Technical
Forum - Innovation
David Pinkney
Date 13.02.2013
Date 00.00.00
Create your footer by changing copy in the Header and Footer section
1 1
Innovation on Thameslink
• Using new products equipment and tools to reduce costs
and create efficiencies
• Often teamed with headquarters, maintenance, or another
programmes
• Most have a large engineering content and the
development of a new product
• Often involve product acceptance and changes to ways of
working
• Need to flexible, adaptable, thinking out of box
• But still supporting programme delivery
Date 00.00.00
Create your footer by changing copy in the Header and Footer section
2
Example of a successful project - New
CCTV technology for London Bridge
• Use of mega pixel technology to reduce the number
cameras needed for London Bridge station.
• The reduction of cameras produces reductions in brackets,
power, cables
• The like for like saving for the London Bridge installation is
£1m (25%) but the big saving is in maintenance – circa
60%
• Project Manager’s role was to gain acceptance by the HQ
CCTV group and NR Head of Security and have the
standard changed
Date 00.00.00
Create your footer by changing copy in the Header and Footer section
3
Mobile Maintenance Unit
• The MMU is a train with a
workshop, stores, messing,
worker transport
• Self contained train for installation
and maintenance
• Moving green zone – work force
protected
• Realisation is that MMUs will
radically change the way we plan
and manage our site work
Date 00.00.00
Create your footer
Presentation
title toby
gochanging
here
copy in the Header and Footer section
4
Mobile Maintenance Unit
Date 00.00.00
Create your footer by changing copy in the Header and Footer section
5
Mobile Maintenance Unit
Date 00.00.00
Create your footer by changing copy in the Header and Footer section
6
Mobile Maintenance Unit – Status
• Nationally 7 units are needed (4 specifically in the south
east)
• Aligning Thameslink with Kent
• In the tender process – 5 companies bidding
• Planning visits to users
Date 00.00.00
Create your footer by changing copy in the Header and Footer section
7
Mobile Maintenance Unit – Status
Continued
• For Thameslink two extra
variants
• For tunnel working – To reduce costs – TOC
compensation, 7 day railway
– Keeping one track open while
working on the other track
– Still a mobile green zone
– Expanding slides and opening side
doors
Date 00.00.00
Create your footer by changing copy in the Header and Footer section
8
Mobile Maintenance Unit – Status
Continued
• Second variant
– Enables slim-line gantries to
be used
– Efficiencies in installation and
maintenance
• The necessary kit is there
• Difficult bit –
– How are we going to use it?
– Define the processes
– Which variants do we need?
Date 00.00.00
Create your footer by changing copy in the Header and Footer section
9
Cable Management Sleepers
• Replace
– Under and Over Track Crossings
– Orange Pipes and Yellow Split
Ducting
• Savings of the order 95%
• Reduce risk as the track bed is not
disturbed
• Two variants product accepted
• In use across the whole of Network
Rail as well as Thameslink
Date 00.00.00
Create your footer by changing copy in the Header and Footer section
10
Cable Management Sleepers – further
work
• Modified
– Wider rebate
– Clips
– Inserts to mount third rail
insulators
• Production moulds for GV54
sleeper on order
• Thameslink requirements until
2018 defined
Date 00.00.00
Create your footer by changing copy in the Header and Footer section
11
Cable Management Sleepers
Date 00.00.00
Create your footer by changing copy in the Header and Footer section
12
Negative Short Device
• The Negative Short Device will be
used to improve the efficiency and
safety of third rail isolations.
• Replace short circuiting straps and
strap-men (can have up to 25)
• Simplifies the process considerably
• Project timescale 40 weeks
• Proposed fit NSDs to London Bridge
low level
• Manual switched solution – not using
SCADA
• Only 25 NSDs needed
Date 00.00.00
Create your footer by changing copy in the Header and Footer section
13
Increase in Work Time with NSDs
Existing Communication Chain for Isolations
Circuit Breaker Isolation
• Current situation
– Available work time 2h 30m
Value Adding Work
From 01:15 to 03:45
2:30 hours
– Complicated
Sub-section CB1
– Many phone calls
• With NSDs
-
– Available work time 4h 00m
PICOP
Signaller
– Much simpler
Protection
Staff
00:15
PICOP
insructs PS to
place PLB
Signaller
protects
possession
00:20
PLB in place
x4
00:21
Grants
possession
00:35
Confirm SCS
and MB in
place
00:30
Circuit breaker
only - grants
isolation - with
NSD applied
04:47
Confirms
removal of
Marker
Boards
04:50
Request
recharge of
traction
current
04:54
Request
handback of
the
possession
04:56
Confirm
removal of
PLBs
05:00
Hands back
possession
Signaller
takes back
possession
Confirms PLB
in place
04:53
Confirm
traction
current on
PS#1
04:55
Instructs
removal of
PLBs
Requests
Isolation
ECRO
Requests to
set up
worksite and
test traction
circuit
Engineerin
g
Supervisor
– Far fewer phone calls
Communication Chain for Isolations using Negative Short Devices
Circuit Breaker Isolation
00:10
PICOP
requests
possession
Confirm SCS
and MB in
place #1
Authorises
the issue of
CRP
Instructs to
erect MB and
possition SCS
#1
Worksite
Staff
04:46
Remove
marker boards
04:48
Marker boards
removed
Value Adding Work
From 00:40 to 04:45
4 hours
Issues CRP to
COSS x 20?
04:45
Returns CRP
COSS
-
Sub-section CB1
PICOP'
Worksite
Staff'
Engineerin
g Staff'
ECRO'
COSS
Date 00.00.00
Create your footer by changing copy in the Header and Footer section
14
NSD Savings
• Reduction in resource needed over 2 years = £840k
• Reduced communication over 2 years, 208 hours = 52 extra shifts
• Not cancelling the first and last trains over 3 years = £300k
• Reduction in risk
– Reduced requirement for line blockages
– Less staff on the infrastructure
– Reduced involvement from interface stakeholders
– No strapping in the wrong area
– Reduced communications
– Reduced staff on track / less chance of injury
Date 00.00.00
Create your footer by changing copy in the Header and Footer section
15
Snow displacer
• Very simple, inexpensive
length of foam that sits in
the point ends
• Stops snow (anything
else) from entering and
jamming the points
• Saves delay minutes
• Saves energy (30%) by
insulating the point
heaters
Date 00.00.00
Create your footer by changing copy in the Header and Footer section
16
Snow displacer installation
Date 00.00.00
Create your footer by changing copy in the Header and Footer section
17
Snow displacer – status
• Thameslink is part of the national programme
• Trial underway at Hither Green
• Further work –
– Develop a version for the very narrow end of the points
– Arrange for points to be automatically fitted to the points at the
factory
– ‘Productionise’ the existing snow displacer for easier fitting
Date 00.00.00
Create your footer by changing copy in the Header and Footer section
18
Electro-luminescent PPE
• Worked very closely with the
suppler Fhoss to complete final
development
• Thameslink Route Access Team
is testing 10 sets of PPE
• Battery life 12 hours
• A worker can be seen 1 ½ miles
down the track
• Compliant with Rail Standards
• Additional cost is not significant
Date 00.00.00
Create your footer by changing copy in the Header and Footer section
19
Pavegen – electrical energy from foot falls
• Sustainable renewable energy
• Floor tiles form the green area in
the ‘mock up’ photo
• Hopefully drive assets such as
destination boards
• Trial site in the station to be set
up
Date 00.00.00
Create your footer by changing copy in the Header and Footer section
20
CCTV Scanning of Pantographs
• A damaged pantograph or shoe can cause
much damage to the infrastructure and very
many delay minutes
• Even more when we are at 24 trains per hour
• CCTV scanning will allow damaged trains to
be sidelined before they enter the
Thameslink central core
• An installation at Farringdon will check that
the pantograph is down as the train travels
south into the third rail area
• Probably the trial site will be at Farringdon
A camera installation showing the housing
containing the radar, flash and camera
Date 00.00.00
Create your footer by changing copy in the Header and Footer section
21
CCTV Scanning of Pantographs
A drawing of a
typical installation
in the Nederlands
Date 00.00.00
Create your footer by changing copy in the Header and Footer section
22
Balise Bars
• Can be used for Balise Bars from
Siemens, Alstrom and others
• Can be fitted or removed in less than
2 minutes using standard tools
• Use standard rail fittings so no drilling
or digging out the ballast
AWS magnets
• Ordinary ferrite magnets –
– Lose strength due to interference
in third rail areas
– Bulky heavy
– Require frequent maintenance or
rebuilding
• Vortok - Rare Earth Magnets
– With an opposing coil and digital
control electronics
– Smaller and Lighter
– Little or no loss of strength
– Plug coupled so quick to fit
Innovation on Thameslink
• Not just be confined to Network Rail
• Surely our partners have innovations as well
• Example – Invensys use the IBM Rational tool provides platform for integrating and
synchronizing product development processes
• The need - Invensys Rail Dimetronic needed to improve its competitiveness and reduce timeto-market for its solutions. This required automating, streamlining and increasing control over
development processes.
• The solution The company used integrated IBM® Rational® software to automate code
generation and speed developers' response to frequent changes and new traffic signal
requirements.
• The benefit The company reduces time-to-market for products by 40 percent and reduces
cost and risks of development by generating all code in compliance with coding standards.
• This case study has been published by IBM
• Please tell me of your innovations on Thameslink
• Are there opportunities for partnering?
Date 00.00.00
Create your footer by changing copy in the Header and Footer section
25