Module 3 HMA construction

Download Report

Transcript Module 3 HMA construction

HMA Construction Program
Module 3 - Surface Preparation
Module 3 - Objectives
•
•
•
•
State the objectives of surface preparation
Proper base preparation techniques
Proper techniques for overlay preparation
Proper materials and construction
techniques for patching
• Proper techniques for placing leveling
courses
• Proper milling techniques
Preparation of a
New Base
To Prime...
or
Not to Prime...
FORM 3-1 BASE PREPARATION CHECKLIST
Date:_____________________
Project #: _______________ Project:__________________________________________________________
Location of area:
Station ______ to ______; Offset ____________;
Other __________________________________
Base Type: (Natural Subgrade, Stabilized Subgrade, Sub-Base, Aggregate Base)
Item
Deficiencies
(Location and Type)
Corrective Action
(List Details)
Agency OK
Initials / Date
Contractor OK
Initials / Date
Final Grade
cross-section
____________________________
____________________________
____________________________
____________________________
____________________________
__________________________________________
__________________________________________
__________________________________________
__________________________________________
__________________________________________
___________
___________
___________
___________
___________
_____________
_____________
_____________
_____________
_____________
Density Testing
____________________________
____________________________
____________________________
____________________________
____________________________
____________________________
__________________________________________
__________________________________________
__________________________________________
__________________________________________
__________________________________________
__________________________________________
___________
___________
___________
___________
___________
___________
_____________
_____________
_____________
_____________
_____________
_____________
Proof Roll and
Visual Survey
____________________________
____________________________
____________________________
____________________________
____________________________
__________________________________________
__________________________________________
__________________________________________
__________________________________________
__________________________________________
___________
___________
___________
___________
___________
_____________
_____________
_____________
_____________
_____________
Prime Coat
Type: ________
Rate: ________
____________________________
____________________________
____________________________
____________________________
__________________________________________
__________________________________________
__________________________________________
__________________________________________
___________
___________
___________
___________
_____________
_____________
_____________
_____________
REMARKS: ________________________________________________________________________________________________________________
__________________________________________________________________________________________________________________________
__________________________________________________________________________________________________________________________
Preparation of an
Existing Surface
Pavement Repair
• Matching Techniques
• Materials
• Procedure
FORM 3-2 EXISTING SURFACE PREPARATION CHECKLIST
Date:_____________________
Project #: _______________ Project:__________________________________________________________
Location of area:
Station ______ to ______; Offset ____________;
Other __________________________________
Surface Type: (HMA Base; HMA Binder, HMA Surface [new or old], PCC Surface)
Item
Deficiencies
(Location and Type)
Corrective Action
(List Details)
Agency OK
Initials / Date
Contractor OK
Initials / Date
Visual Survey
____________________________
____________________________
____________________________
____________________________
____________________________
__________________________________________
__________________________________________
__________________________________________
__________________________________________
__________________________________________
___________
___________
___________
___________
___________
_____________
_____________
_____________
_____________
_____________
Pavement Repairs
____________________________
____________________________
____________________________
____________________________
____________________________
____________________________
__________________________________________
__________________________________________
__________________________________________
__________________________________________
__________________________________________
__________________________________________
___________
___________
___________
___________
___________
___________
_____________
_____________
_____________
_____________
_____________
_____________
Final Cleaning
____________________________
____________________________
____________________________
____________________________
____________________________
__________________________________________
__________________________________________
__________________________________________
__________________________________________
__________________________________________
___________
___________
___________
___________
___________
_____________
_____________
_____________
_____________
_____________
Tack Coat
Type: ________
Rate: ________
____________________________
____________________________
____________________________
____________________________
__________________________________________
__________________________________________
__________________________________________
__________________________________________
___________
___________
___________
___________
_____________
_____________
_____________
_____________
REMARKS: ________________________________________________________________________________________________________________
__________________________________________________________________________________________________________________________
__________________________________________________________________________________________________________________________
Preparing a
Milled Surface
Module 3 - Review Objectives
•
•
•
•
State the objectives of surface preparation
Proper base preparation techniques
Proper techniques for overlay preparation
Proper materials and construction
techniques for patching
• Proper techniques for placing leveling
courses
• Proper milling techniques