APWA DIV 5 – FINAL – Oct 2014 – Spec. Updates

Download Report

Transcript APWA DIV 5 – FINAL – Oct 2014 – Spec. Updates

DIVISION 5 SUBCOMMITTEE
OCT 2014 Update
• The Washington Chapter is one of 67 local chapters in
the US and Canada which make up the American Public
Works Association (APWA).
• Membership in APWA is open to public and private
sector individuals, agencies, and companies interested
and involved in the delivery of public works goods,
projects and services.
• The American Public Works Association exists to
develop and support the people, agencies, and
organizations that plan, build, maintain, and improve
our communities
Members of the Division 5 Subcommittee include:
• Public works personnel
• Municipal consultants
• Paving contractors
• Material testing representatives
• WSDOT H&LP
The Division 5 Subcommittee has two co-chairs.
• Cody R. Hart P.E.
• CRH Engineering
• Sedro-Woolley, WA
• Eric Jenkin
• Spokane County
• Spokane, WA
DIVISION 5 SUBCOMMITTEE
2014 APWA DIV-5 GSP’s
FHWA Approved GSP’s for local agency use can be found @
www.wsdot.wa.gov/partners/apwa/Division_5_Page.htm
5-04.3(3)A
5-04.3(7)A2
5-04.3(8)A1
5-04.3(8)A4
5-04.3(8)A5
5-04.3(8)A6
5-04.5(1)B
Material Transfer Device / Vehicle
Statistical or Non-statistical Evaluation
General
Definition of Sampling Lot and Sublot
Test Results
Test Methods
Price Adjustments for Quality of HMA
Compaction
2014 APWA DIV-5 GSP’s
Highlights of Benefits
• Ability to reduce or eliminated use of MTD/V as deemed
appropriated to reduce project costs.
• Provides concise acceptance criteria
• Mandates Anti-strip determination prior to bid opening
• Eliminates Requirement for WSDOT verified Mix!!!!
• Eliminates Requirement for Hamburg test
• Clarifies reduced acceptance criteria for small quantities of HMA
• Allows for optional Testing of HMA for compliance of Va
•
Establishes a maximum CPF of 1.0
2014 APWA DIV-5 GSP’s
Example
5-04.3(8)A4
Definition of Sampling Lot and Sublot
(January 16, 2014 APWA GSP)
Section 5-04.3(8)A4 is supplemented with the following:
For HMA in a structural application, sampling and testing for total project quantities
less than 400 tons is at the discretion of the engineer. For HMA used in a structural
application and with a total project quantity less than 800 tons but more than 400
tons, a minimum of one acceptance test shall be performed:
If test results are found to be within specification requirements, additional testing
will be at the engineers discretion.
If test results are found not to be within specification requirements, additional
testing as needed to determine a CPF shall be performed.
Going Forward
• Continue to gather Feedback about current APWA Div. 5 GSP’s
- Only minor desired revisions have been received.
• Make old WSDOT ATB specification available for use by GSP
• Research possibility of approval of Non-nuclear testing methods
AASHTO T343-12 - “Density of In-Place Hot Mix Asphalt (HMA) Pavement
by Electronic Surface Contact Devices.”
ASTM D7713-05 - “Standard Test Method for Density of Bituminous Paving Mixtures
in Place by the Electromagnetic Surface Contact Methods”
• Review Pervious HMA Pavements Specifications for possible inclusion as new
GSP
QUESTIONS?