Implementation of River Information System on the Bulgarian Part of

Download Report

Transcript Implementation of River Information System on the Bulgarian Part of

OPERATIONAL PROGRAMME ON TRANSPORT 2007-2013

Implementation of BulRIS Project

BULGARIAN PORTS INFRASTRUCTURE CO.

RIS Workshop Danube Commission

April 11, 2011 Budapest

Kuzman Genov

ICT Director and BulRIS Project manager, BPI Co. – HQ Sofia

Agenda:

     

Project Overview System Components

    

Tracking & Tracing Voice VHF Communication System ERI Data Gateway Notices to Skippers Communication Infrastructure AIS and VHF Network Layout & Design Construction Works What next ? - Phase II and III

Implementation of River Information System on the Bulgarian Part of Danube - BulRIS

Project overview - General

Project duration 18 Months

Start: May 2010

End: November 2011

Contracting Authority: Bulgarian Ports Infrastructure Co.

Budget 5.6 Mil €

Project is co-funded by EFRD - Operational Program on Transport 2007 – 2013

Implementation of River Information System on the Bulgarian Part of Danube - BulRIS

Project Overview - Project Goals

To establish the required base infrastructure for RIS operation on the Bulgarian part of Danube

    

Communication infrastructure Tracking and tracing (AIS) infrastructure Voice VHF Communication System ERI Data Gateway

Notices to Skippers

To apply DIRECTIVE 2005/44/EC of the European Parliament and of the Council

Implementation of River Information System on the Bulgarian Part of Danube - BulRIS

Project Overview – Implementation Schedule

Task 1: Inception report and planing (completed) Task 2: System design (completed) Task 3: Construction (in progress) Task 3: Software development (completed) Task 4: System installation (in progress) Task 5: System integration (Q2-Q3’2011) Task 6: Testing and training (Q3-Q4’2011) Task 7: Migration to real life operation (Q4’2011)

Implementation of River Information System on the Bulgarian Part of Danube - BulRIS

System Components - Tracking and Tracing

AIS based system

8 sites

Exchange of actual, safety related information between ships and shore

Client – Server architecture

Web interface

Functions:

Provision of a TTI/STI

Provision of traffic management or fairway information services

Web access for logistic users

Implementation of River Information System on the Bulgarian Part of Danube - BulRIS

System Components - Tracking and Tracing

Implementation of River Information System on the Bulgarian Part of Danube - BulRIS Tracking and Tracing - Additional AIS functions dGPS trough AIS network

Improves the accuracy of the vessel positioning

Functions:

Correction of GPS positioning

Compliant with international recommendations

Implementation of River Information System on the Bulgarian Part of Danube - BulRIS System components - Voice VHF Communication Network

8 sites along Bulgarian Danube

Cohabitation with AIS base stations

Independant system

Integration and data exchange with AIS

Graphic presentation of the vessels position

Implementation of River Information System on the Bulgarian Part of Danube - BulRIS

System Components - ERI

   

Allows simplification of cross border procedures Functions:

  

Data exchange between vessel and competent authorities Available via web application Access according to the user rights Users:

 

Vessel parties Competent authorities Compliant with European and international standards

Implementation of River Information System on the Bulgarian Part of Danube - BulRIS

System Components - ERI

Implementation of River Information System on the Bulgarian Part of Danube - BulRIS

System Components – Data Gateway

   

National and international exchange of RIS data Functions:

  

Provision of relevant RIS data Interface to T&T, ERI and Hull system Web based users interface Users:

Governmental users

Commercial users Different data access rights have to be defined

Implementation of River Information System on the Bulgarian Part of Danube - BulRIS

System Components – Data Gateway

Implementation of River Information System on the Bulgarian Part of Danube - BulRIS

System Components – Notices to Skippers

Used for fairway information, traffic information and management as well as voyage planning

Functions:

Users:

Available via web service

Automatic translation on 23 languages

Input information for voyage planning

Traffic/Fairway authorities

Harbour Master’s Offices/Port authority

Police

Shippers

Skippers/Captains

Inspection and customs authorities

Compliant with European standards

Implementation of River Information System on the Bulgarian Part of Danube - BulRIS

System Components – Notices to Skippers

Implementation of River Information System on the Bulgarian Part of Danube - BulRIS

System Components – Communication Network

Total of 16 sites

14 radio reley links

1 dedicated optical link

1 MAN link

Interlinked togeather to form a closed network

Network is invisble to outside world

Hack proof

Used for AIS and VHF communication

Real time data replication between Ruse and Varna backup centre

Implementation of River Information System on the Bulgarian Part of Danube - BulRIS

System Components – Communication Network

Implementation of River Information System on the Bulgarian Part of Danube - BulRIS

AIS and VHF Network - Locations

Implementation of River Information System on the Bulgarian Part of Danube - BulRIS

AIS and VHF Network – Radio Coverage

(c) Kongsberg Seatex AS

Implementation of River Information System on the Bulgarian Part of Danube - BulRIS GUI of the Client Application 1/2

(c) Periskal

Implementation of River Information System on the Bulgarian Part of Danube - BulRIS GUI of the Client Application 2/2

Implementation of River Information System on the Bulgarian Part of Danube - BulRIS GUI AIS WEB Application 1/2

(c) Periskal

Implementation of River Information System on the Bulgarian Part of Danube - BulRIS GUI AIS WEB Application 2/2

(c) Periskal

Implementation of River Information System on the Bulgarian Part of Danube - BulRIS

Construction Works

Scope of works

  

Design Evaluation of radiation influence Obtainig building permits

 

Site construction Exploatation permits

4 new sites

Other sites are existing sites owned by Bulgarian telecom

Implementation of River Information System on the Bulgarian Part of Danube - BulRIS

What next? – Phase II and III

Construction of the RIS Center building

 

Conceptual design finalized Technical project – start in May 2011

  

Construction works – start in fall 2011 In operation – end of 2012 Upgrade and development of the services (pre-project study)

 

Automatic water level measurement/modeling RIS portal

  

WLAN access to RIS services Calamity abatement services ………………………………………

THANK YOU FOR YOUR KIND ATTENTION Kuzman Genov [email protected]