Transcript Bundi
Visitor Praveen Gupta DPM- NRHM
23 rd to 27 th Oct 13
Objective of Visit
To see overall progress of the project To see proper utilization of fund To see status of building & identify scope of work To see Staff status/Rational use of Human Resource To see status of ASHA programme To see utilization status MMU-MMV, 10 8 Amb, J express
Facilities Visited
Block CMO – Kapren,Talera CHC – K Patan, Kapren,Talera,Hindoli (all DPs) PHC - Arnetha, Raithal,Khatkad (DP) Matunda Sub-center - Balkasa,Kuranti,Anthada,Dholada, MMU/MMV -Bundi Ambulance 108 -Taleda Upper primary / Secondary School - Keshorai patan,Taleda ASHA Training Site- 4 Batches ASHA Six Monthly Review Meeting on RI -125 ASHAs and ANMs MDR workshop with CMHO ,RCHO,Dy CMHOs All BCMOs ,All CHC in-charges Meeting with all BPMs ,Block PHC CHC accountants and ASHA Supervisors
Basic Information
District Hospital No. of CHCs : 1 : 11 No. of PHCs No of Sub-Centers No. of MMU/MMV : 1 (MMU), 2 (MMV) Janani Express : 7 No of Ambulance 108 : 31 : 214 : 9
Major Finding’s
At CHCs
Due to bad condition of building immediate action required for new land(K.Patan)
BSU Facility and Pead. available LSAS and Gyne. Not available (K Patan)
MTP Services Not given even after Gyne . and trained Doctor available(Kapren) C-Section not Conducted even after Gyne.and LSAS Doctor available (Kapren) At all the Delivery Point CHCs Branding yet not done Process of Utilization of Cleanliness funds yet not done CTF Connectivity available with only one CHC Taleda Payment of Incentives to ASHA for institutional delivery and HBNC pending
Major Finding’s
At PHCs At all the Delivery Point PHCs Branding yet not done Process of Utilization of Cleanliness funds yet not done Payment of Incentives to ASHA for institutional delivery and HBNC pending Partograph not in Use Licence for disposal of Biomedical waste is under process
Major Finding’s
At Sub Center
SBA trained staff available at all Sub Centers
No of Deliveries at sub centers is very low
Payment of Incentives to ASHA for institutional delivery and HBNC pending Partograph not in Use Utilization of Untied Fund is very low All essential eqipments and furniture available
108 Ambulance
Total Allotted – 9
Functional - 8
Stickering – under process Payment of maintenance 108 Ambulance
Janani Express
Total Allotted - 7
Functional - 7
Total Drivers – 14
24 Hours Facility available
Stickering – complete
MMU-MMV
Total Allotted MMU – 2 (Available – 1)
Functional - 0 (Due to Black listing of NGO)
Total Allotted MMV – 2 (Available – 2)
Functional - 2 (Through DHS) Manpower available through Placement Agency
Stickering - under process