Network Manager DMS Projects
Name
Location
Commonwealth Edison
Chicago, IL
CPS Energy
No. of
Customers
Production
Date
3,700,000
2004
San Antonio, TX
650,000
2006
Ergon Energy
Brisbane, Australia
600,000
2006
Jackson EMC
Jackson, GA
190,000
2006
Arizona Public Service (APS)
Phoenix, AZ
1,200,000
2007
DTE Energy
Detroit, MI
2,200,000
2007
New Hampshire Electric Coop.
Plymouth, NH
77,000
2007
Network Manager Projects
© ABB Inc. - 3
-
ComEd Project Highlights

Chicago Live as of 5/10 – Now
Live System-Wide

Large Single Database – 2.2M
Nodes

Use of CADOPS Remote in
Regional Offices

Integration with ABB SCADA

CIM XML Based Interfaces

GIS CIM interface with
SmallWorld GIS
Network Manager Projects
CPS Energy Project Highlights







© ABB Inc. - 4
-

Parallel Implementation of GIS, Data
Conversion, and OMS in Phase 1
Going Live Next Month
ABB Prime for GIS Electric/Land/Gas, Data
Conversion, OMS, GIS Design, and Mobile
GIS
Integration between ABB Network Manager
DMS, MDSI Advantex, and SAP
ICCP Interface to SCADA
netCADOPS Call Entry Screen Embedded
in SAP
Network Analysis Applications for Phase 2
(Balanced Load Flow and Fault Location)
Plans for Notification and WebMap
Modules
Network Manager Projects
© ABB Inc. - 5
-

APS Project Highlights

Phase 1 FAT Starting Next Month

TIBCO Based EAI

ICCP Interface to SCADA

AMI Integration

netCADOPS Call Entry Enhancements

Notification, WebMaps, and Crew Callout

Network Analysis Applications for Phase 2 (RSA, Unbalanced
Load Flow, Fault Location, Simulation Mode, Auto-Schematic,
Line Unloading, Capacitor Control Integration)
Network Manager Projects
© ABB Inc. - 6
-

DTE Project Highlights

FAT near completion

DTE implementing new ESRI GIS in parallel

Not implementing OMS at this point

Integration with ABB SCADA

Integration with Dispatcher Training Simulator

DMS applications (Unbalanced Power Flow, RSA, Line
Unloading, Auto-schematic, Fault Location, Simulation Mode,
Phase Angle Security Check, Dispatcher Training Simulator)
Network Manager Projects


© ABB Inc. - 7
-

Ergon Energy Project Highlights

ABB EMS/DMS Integrated system

DMS Pilot / No OMS at this point

Split Mode

SmallWorld GIS Interface
Jackson EMC Project Highlights

Tagging and Referral Enhancement

Going live in October

ESRI GIS interface
New Hampshire Electric Coop. Project Highlights

Starting October

ESRI GIS Interface

4 Month Project
ABB Project Implementation Approach
Define Scope
Scope of Work
(SOW)
Program
Development
System (PDS)
Initial Project
Team Training
Requirements
Review
Configuration
Guide
System
Architecture
Guide
As-Is/To-Be
Workflows
Test &
Acceptance
Plan
Test
Procedure
(TPR)
Factory
Acceptance
Testing (FAT)
Site
Acceptance
Testing (SAT)
Cutover/
Rollout
Knowledge
Transfer
Detail Requirements
Software Task
Spec. (STS)
Develop System
Code
Development
Deploy System
© ABB Inc. - 8
-
Site System
Integration
Business Process Change Management


© ABB Inc. - 9
-

Change Management Goals

User Acceptance

Realization of Benefits

Process Based Communication/Training/Support
Process Change Management

As-Is/To-Be Workflow

Gap Analysis / Impact Analysis
Communication, Training, & Support

Project Team / Core Team / SME’s

Super Users (Tier 1 Support)

End Users (Roles Based Security)