By Ed Landauer, C.Q.E., P.E.
November 13, 2012
Short Run SPC
What it is
What it isn’t
SPC is not intended to be a substitute for
inspection and testing
Programs such as JIT make Short Run SPC
more common
What Constitutes a Short Run?
A run of 25 parts?
A run of 100 parts?
A run of 1000 parts?
A run of 50,000 parts?
A single part?
General Categories of Short Runs
Not enough parts in a single production run to
develop or maintain control limits on the
process
Process cycles are so short that production runs
are over before sufficient data can be gathered
Many different parts are made for many
different customers
Examples
Example: CNC Machine
Extremely complex machine
Has dozens of different tools
That produce hundreds of different parts
With thousands of characteristics
Example: CNC Machine- Generic
Operations
Select a tool
Position a tool
Rotate a tool
Move the part
Remove the metal
Example: CNC Machine
Nearly all problems encountered after the
initial set-up involve the ability of the
machine to position the tool precisely
For example, the location of a single hole
provides information on the location of the
tool in both the x and y directions
Sample Set of Data
Twelve subgroups- 3 observations per subgroup
5.0037 5.0009 4.9973 5.9974 6.0021 5.9981
5.0015 5.0023 5.0029 5.9990 5.9983 6.0018
4.9989 4.9981 4.9985 6.0015 5.9977 6.0023
7.0014 6.9991 7.0003 6.0031 5.9987 5.9987
7.0009 6.9979 6.9975 5.9985 6.0011 6.0021
6.9979 6.9995 7.0021 6.0017 6.0021 6.0001
Method 1: Target Average and
Range Charts
Subtract nominal (or target) value from
the actual measurements
x* = x - nominal
Can plot several parts from a given process
on a single chart
Can plot several features from a single part
on a single chart
Method 1: Restrictions
Nominal (or target) values must be close to
each other with the same tolerance
Or the most restrictive tolerance must be
used for all
Method 1: Control Limits
• Calculate averages and ranges of the
deviations from target
• Control limit formulas are the same as for
traditional control charts
Method 2: Standardized Variables
Control Charts
Good for recurring families of parts
They are independent of the unit of
measure
They are scaled so that different
characteristics can be plotted on the same
chart
They are “true” process control charts
Method 2: Calculations
Use the normalizing transformations
Need to use historical averages from
previous data in the calculations
Method 2: Control Limits
X-bar Chart
R chart
-A2 and A2
D3 and D4
Short Run Attribute Chart- c-chart
Job shop welding process
Produces small quantities of single order
only parts
Operation always involves joining parts of
similar material and size
Can plot chart of weld imperfections per 100
inches of weld
Short Run Attribute Chart- p-chart
Job shop welding process
Similar operation to previous slide
Plot chart of the number of weld
imperfections per total welds per 100 inches
of weld
Summary
Only minor change in mechanics to move
from traditional SPC to Short Run SPC
The biggest difference in the perception of
Statistical Process Control rather than
Statistical Product Control
Questions?
Thank You!
[email protected]