SAME_28_Apr 2011 - The Society of American Military

Download Report

Transcript SAME_28_Apr 2011 - The Society of American Military

Society of American Military Engineers (SAME)

28 April 2011

Lance K. Toyofuku Director of Public Works U.S. Army Garrison, Fort Irwin, CA

Our mission is to provide standardized, effective & efficient services, facilities and infrastructure to Soldiers, Families and Civilians for an Army and Nation engaged in persistent conflict.

We are the Army’s Home

Lance Toyofuku(760) 380-3433, [email protected]

28 Apr 11

US Army Garrison Fort Irwin, CA Agenda

• Fort Irwin Universe • Fort Irwin Energy Campaign – Challenges – Achievements • Environmental Campaign Plan • Pubic Works Resources – Sustainment, Restoration & Modernization (SRM) – Military Construction (MCA) • Contracting • Way Ahead

Lance Toyofuku (760) 380- 3543 [email protected]

UNCLASSIFIED 2 OF 15 28 Apr 11

US Army Garrison Fort Irwin, CA Fort Irwin Universe

Land Acreage: 636,398 Acres (994 sq mi)

Cantonment – 5,474 Acres Land Expansion: 127,290 Acres

Roads (Paved & Unpaved): 525.3 Miles

Paved – 257.6 Miles MSR Trails – 171 Miles Unpaved – 47 Miles Tank Trails – 49.7 Miles

Serving & Supporting Paved Area (Excluding Roads) 47 Tenant Units

Parking = 1,073,358 yd 2

4,910 Rotational Soldiers

Sidewalks = 362,000 yd 2

Utilities: 140 Miles 4,709 Assigned Military (living on installation – 3,380)

Water (Domestic) – 66 Miles Water (RO) – 42 Miles Water (Sewer) – 32 Miles

Environmental Clean-up

Restoration (IRP) – 4 Active Munitions (MMRP) – 8 Active Compliance Clean-up (CC) – 5 Active

7,461 Family Members (living on installation – 5,147) 5,646 Civilian Workforce ------------------------------------- Daily Population – 22,726* School System (SVUSD)

Pre-School - 235, Lewis Elementary (K-2) 609 Tiefort View Intermediate (3-5) 453 Fort Irwin Middle School (6-9) 342 Off Post SVHS (10-12) 251

Lance Toyofuku (760) 380- 3543 [email protected]

UNCLASSIFIED 3 OF 15

Buildings: 1600 = 4,523,929.7 SF

Permanent – 1318 Bldgs Semi-Permanent – 107 Bldgs Temporary – 175 Bldgs Barstow Outreach Center – 1 Bldg Daggett Heliport – 2 Bldgs

Family Housing Units, 2,383

Built since 2004 - 556 Under Construction - 54

Barracks Inventory (spaces): 1,430

Barracks – 1,203 BOQ – 121 (100 series and Old Tiefort) Town Center Terrace – 106

Airfields

Bicycle Lake Southern CA Logistics Airbase (SCLA) (Leased) Daggett Heliport (Leased)

Railroads

MCLB – YERMO Railhead * Based on May 2008 ASIP Lock 28 Apr 11

US Army Garrison Fort Irwin, CA

Fort Irwin Energy Campaign Plan

Lance Toyofuku (760) 380- 3543 [email protected]

UNCLASSIFIED 4 OF 15 28 Apr 11

US Army Garrison Fort Irwin, CA Irwin Energy Profile

• • • • •

Fort Irwin is not meeting mandated energy reduction goals Fort Irwin currently has 106 high energy use trailer buildings for admin space (400,000+ sq ft) Fort Irwin lacks metering capability to audit energy consumption (currently 95% of the facilities & buildings are NOT metered) for effective energy management Fort Irwin’s on-site landfill operations costs $1.48 million; in FY12 will require $4.5 million to expand Audit and EMCS Demand 2003 Baseline: 100 WH/yr 2007 Usage: 115 MWH/yr Peak demand: 25 MW Avg demand: 15 M 2010 : 140 MWH/yr Peak demand: 28 MW Avg demand: 18 MW Lance Toyofuku (760) 380- 3543 [email protected]

UNCLASSIFIED 5 OF 15 28 Apr 11

US Army Garrison Fort Irwin, CA

• • • • • • • • • •

What we have done

ENERGY CONSERVATION:

Net Zero Energy Ammunition Building ($720 K) Replacing Solar Exterior Lighting – installing 132 exterior solar lights for streets, ASP perimeter lights, jogging path lights and parking areas CID, OPS GRP HQ, DFAC BLDGS: 39kW solar roof panels installed SCE participating load pilot study for $325,500 credit Participated in SCE Demand Bidding Program which in 2009 led to a billing credit of $52,000 & avoided electricity cost of $1.7 million Current intra-post use of electric vehicles (GEM) w/PV powered charging stations in FY12 Lutron lighting in 7 buildings w/30% energy savings in each

Construction Engineering Research Laboratory (CERL, COE):

100 kW solid oxide fuel cell at DOL

Gas (LPG) engine driven air conditioning (GEDAC) Combined geothermal, wind & solar energy in dome COB, net-zero facility in remote site ($300/month savings by being off the grid)

Replaced 668 street lights w/LED lights ($15,000/yr savings)

• •

WATER CONSERVATION:

Wastewater Treatment Plant: New tertiary plant will recycle wastewater (9 million gallons+ in Aug 2010) for irrigation throughout the cantonment area; Phase I of III operational FY10 3 rd qtr, project complete FY13 Grass Reduction: 5,000 sq ft in 2010

RECYCLING:

Since the inception of the FI Recycling Program in FY05, we have saved over $5.4 M in landfill costs and provided $1.9 M back to the community in MWR programs Current recycling rate is 25%

• •

916 th Support Brigade Converted shading areas & tents into foam-coated structures in RUBA area for cost avoidance of $8,470,868 annually. By reducing generators for AC, there was positive impact on air quality Foam-coated tents DOWN RANGE for a cost-avoidance of $12,236,225 Lance Toyofuku (760) 380- 3543 [email protected]

UNCLASSIFIED 6 OF 15 28 Apr 11

US Army Garrison Fort Irwin, CA

Iluminates dark corner near youth facilities Lance Toyofuku (760) 380- 3543 [email protected]

UNCLASSIFIED 7 OF 15 28 Apr 11

US Army Garrison Fort Irwin, CA

Keeps joggers safe during night runs Lance Toyofuku (760) 380- 3543 [email protected]

UNCLASSIFIED 8 OF 15 28 Apr 11

US Army Garrison Fort Irwin, CA Environmental Campaign Plan

Pollution Prevention Plan

– Reduce solid waste from 2500 tons/yr to 200 tons/yr – Increase recycling to 10,000 tons/yr by expanding baling facility – Use best available technology to convert trash/waste to energy

HAZARDOUS WASTE (HW)

• Background: FY08 – Regulated toxic and non toxic wastes: 2.0M lbs – Turn-in volume accepted: 1.8M lbs (80% P2 rate) • Long Term Goals: Increase P2 Rate to 90% by Dec 09

Reduce water use

― Remove or replace non-mission essential green space – Extend T2 water irrigation pipes to all major green areas (200M gal/yr) – Construct construction fill stands using T2 water – Investigate engineering solutions, i.e. cisterns, and alternate sources of water, i.e. springs, gray water, etc. (included in Landscape Master Plan.

Lance Toyofuku (760) 380- 3543 [email protected]

Air Quality

Background: FY07 – Nitric oxide (NOx) emissions limited to 25 tons/yr, currently 22 tons/yr – – PM10 (dust), 146 tons/yr Carbon Dioxide: 5.2M lbs/rotation Compliance Goals to Improve air quality – Replace 70% generators with solar power systems in the box reducing NOx by 70% – Install emission controls on boilers – Increase dust suppressants on tank trails; reduce PM10 by 80% – FOB Standardization program will reduce CO2 emissions by 3.5M lbs/ rotation (60% reduction) – Eliminate NOx emissions – UNCLASSIFIED Eliminate CO2 emissions 9 OF 15 28 Apr 11

US Army Garrison Fort Irwin, CA

Repair of Building 264 Augmentee Barracks at Fort Irwin

Public Works Program

Building 98 Lance Toyofuku (760) 380- 3543 [email protected]

UNCLASSIFIED 10 OF 15

Repair Infant Playground Area

28 Apr 11

US Army Garrison Fort Irwin, CA SRM Program

2010 2010 2011 2011 2011 2011 2011 2011 2011 One-Stop In & Out Processing Center USAG Headquarters Renovation Construction Aerobic Center G3 Aviation Operations Facility Construct Community Pavilion Construct Playground Areas NTC Head Quarters HVAC Renovation NEC Headquarters HVAC Building 985 Renovate Building 254 Construction Construction In Design In Design In Design In Design In Design In Design In Design Lance Toyofuku (760) 380- 3543 [email protected]

UNCLASSIFIED 11 OF 15 28 Apr 11

US Army Garrison Fort Irwin, CA Military Construction Army (MCA) Program

2010 MOUT, Phase IV 2011 No Projects 2012 Qualification Training Range Infantry Squad Battle Course Under Construction Under Design Under Design 2013 Fitness Facility/Pool Addition Replacement Hospital Water Treatment Plant 2014 No Projects 2015 Urban Assault Course 2016 Hand Grenade Familiarization Range Soldier & Family Support Center Campus PH-I 2017 NTC Headquarters Company Operations Facility Soldier & Family Support Center Campus PH-II Designed Under Design Design Charette Concept Phase Concept Phase Concept Phase Concept Phase Concept Phase Concept Phase Lance Toyofuku (760) 380- 3543 [email protected]

UNCLASSIFIED 12 OF 15 28 Apr 11

US Army Garrison Fort Irwin, CA Contracting

• Contracting Vehicles: DPW does not award contracts rather use following agencies to award and execute project – Army Contracting Agency, Fort Irwin Contracting Office – US Army Corps of Engineers – South West Navy – General Services Administration; Require Offloading approval from Fort Irwin Contracting Office.

• DPW Function: – Prepare project scope, design , Estimate and Contract Award Package – Service Contracts require Service Contract Approval from HQ (IMCOM) – Monitor QA/QC, Schedule, Liaison with Fort Irwin Customer • Words of Wisdom for A-E Firms and Contractors: – Register with the above agencies to get business at Fort Irwin – If you are 8-A or small business, work with these agencies and SBA

Lance Toyofuku (760) 380- 3543 [email protected]

UNCLASSIFIED 13 OF 15 28 Apr 11

US Army Garrison Fort Irwin, CA Way Ahead

• Hire/obtain additional personnel: – Designers (contractors) – Quality Assurance (contractors/DA civilians) – Environmentalists (DA civilians) – Engineer Technicians (DA civilians) – Project Engineers (DA civilians) • Increase funding • Finalize master planning update • Seek private venture support to finance projects through various means: Energy Savings Performance Contracts, Utilities Energy Service Contract, Enhanced Use Lease, Power Purchase Agreements, etc.

Lance Toyofuku (760) 380- 3543 [email protected]

UNCLASSIFIED 14 OF 15 28 Apr 11

US Army Garrison Fort Irwin, CA

INSTALLATION MANAGEMENT COMMAND

“Sustain, Support and Defend

” UNCLASSIFIED 15 OF 15

Lance Toyofuku (760) 380- 3543 [email protected]

28 Apr 11