Strategies for Rapid Scale up of Nuclear Capacity

Download Report

Transcript Strategies for Rapid Scale up of Nuclear Capacity

Strategies for
Rapid Scale up of Nuclear
Capacity
U C Muktibodh
Executive Director (Engg.)
NPCIL
5th Nuclear Energy Conclave, New Delhi
06 Sept 2013
Inspiration for Growth
•
•
•
•
Electricity Demand
Clean source of energy
Sustainability
Energy security
Present Status of Nuclear Power
REACTOR TYPE AND CAPACITY
CAPACITY
(MW)
CUMULATIVE
CAPACITY(MW)
 20 reactors (18 PHWRs+2BWR)
at 6 sites in operation at Tarapur,
Rawatbhata, Kalpakkam,
Narora, Kakrapar and Kaiga
4,780
4,780
 2 PWRs under advanced stage of completion
at Kudankulam (2x1000 MW)
2,000
6,780
 PFBR under construction at
Kalpakkam (1 X 500 MW)
500
7,280
 Projects construction Launched (XI Plan)
KAPP-3&4 (2x700 MW PHWR)
RAPS-7&8 (2x700 MW PHWR)
Total by 2017
2,800
10,080 MW
Nuclear Capacity – Under Construction & Planned in XII Plan
22,700 MW (Construction + Planned)
2000 MW
Advanced Stage of
completion
3300 MW
17,400 MW(Planned)
Under construction
•Planned to be launched in XII Plan-
•KAPP-3&4 :
•2x1000 MW LWR, Kudankulam, TN
•KK-1&2 :
( 2x700 MW PHWR)
•2x1650 MW LWR , Jaitapur,
Maharashtra
2x1000 MW LWR
•RAPP-7&8
•2x1500 MW LWR: Kovvada, AP
(2x700 MW PHWR)
•2x1100 MW LWR : Mithi Virdi,Gujarat
•500 MW PFBR
•2x700 MW PHWR : Gorakhpur,Haryana
Units under construction will be completed in XII Plan .
•2x700 MW PHWR :Chutaka,M.P
•2x700 MW PHWR :Mahi-Banswara, Raj
•2x700 MW PHWR : Kaiga,Karnataka
•2X500 MW FBR: Kalpakkam, TN
•1X300 AHWR: Site being identified
NPPs in Operation & under Construction
Gorakhpur, Haryana
NPPs under Planning
PHWR Site
LWR Site
FBR Site
2 X 700 MW
Chutka, MP
2 X 700 MW
Mahi-Banswara,
Rajasthan
2 X 700 MW
Mithi Virdi, Gujarat
Kovvada, AP
2 X 1100 MW
2 X 1500 MW
Jaitapur, Maharashtra
2 X 1650 MW
Kaiga, Karnataka
2 X 700 MW
Kalpakkam, TN
2 X 500 MW
Kudankulam, T.N
.
2 X 1000 MW
Nuclear Power Programme
• Three stage nuclear power programme
• PHWRs in the first stage
Pressurised Heavy Water Reactors
• Evolved through plant sizes of 220, 540 to the present
700 MWe
• Matured indigenous technology with impeccable
safety record
• Standardised plant size of 700 MWe
• Standard plant design
• Exploring single or two standard seismic designs
• Use of Integrated Engineering Environment tools for
engineering
• Project implementation through Mega ePC packages
• Target construction period of 5 years
FOR 2012-13 A.F = 90.43 %
Continuous Run (more than a year)
RAPS 5 - 400 days (continuing)
Year Wise Electricity Generation
35000
30000
Million Units
25000
20000
15000
10000
5000
0
Series1
2008-09
2009-10
2010-11
2011-12
2012-13
14927
18803
26472
32455
32863
Light Water Reactors
• LWRs, as additionalities, being implemented
through international collaboration.
• Business model formulated for optimisation of
cost and for meeting design & safety
requirements.
Strategies
• Public outreach programs
• CSR activities
• Early Site selection and commencement of
Pre-project activities
• Design standardisation
• Supply chain support
• Project implementation
Support from Industry
• Indian industry has developed capability to
supply NPP equipment & components
• The rapid expansion programme will require
industry support for maintaining supply chain
for high quality equipment, meeting project
schedules.
Conclusion
• NPCIL is poised for the rapid expansion
programme
• Synergy between NPCIL and Indian industry is
a key element to meet the programme
• The programme can be realised in a national
mission mode with the support of all
stakeholders