Transcript Document

Civil Works Progress
Improvement of NR33
Development of CBF
(15.83 Km Kg Trach to Preak Chak)
(4.02 Ha Lork-Kampot)
23 April 2012
GMS-SCCP
ADB Loan No. 2373-CAM(SF) / AusAID Grant No.0096-CAM
MPWT/PMU3
Egis International
CS Consultant
Mr. Chhin Kong Hean
Project Coordinator
Mr. Andre Drockur
Project Manager
Mr. Pheng Sovicheano
Project Director
Mr. Khagnh Sitnarit
Highway Engineer/NTL
Mr. Sar Vutha
Project Manger
Lim Sarin & SWEE JV
CW1 Contractor
Mr. Ung Kotaro
Project Manager
CDOH (SP)
Mr. Bun Meng
Communication Specialist
Kuy Leang Ky
CW2 Contractor
Mr. Khoun Chamroeun
Project Manager
Table of Content
1.
2.
3.
4.
5.
6.
7.
Project Location Map
Overall Project Completion Rate
Summary of Civil Work Progress of NR33 (CW1)
Summary of Civil Work Progress of CBF (CW2)
Summary Civil Work Progress of NR3 (CW3)
Summary of Progress Activities of the CSC
Detailed Information of NR33 – CW1
7.1. General Contract Data
7.2. Physical Work Progress up to March 2012
7.3. Payment and disbursement up to March 2012
7.4. Contractor’s Cash Flow Forecast up to March 2012
7.5. Contractor’s Work Program and Progress up to March 2012
7.6. Progress Feature up to March 2012
8. Detailed Information of CBF – CW2
8.1. General Contract Data
8.2. Physical Work Progress up to March 2012
8.3. Payment and disbursement up to March 2012
8.4. Contractor’s Cash Flow Forecast up to March 2012
8.5. Contractor’s Work Program and Progress up to March 2012
1. Project Location Map
2. Overall Project Completion Rate
3. Summary of Civil Work Progress of NR33 (CW1)
- Contract for Civil Works A.1-Improvements of NR33 (Contract No.
SCCP-CW1) with Contractor Lim Sarin Co., Ltd and SWEE
Construction & Transport Co., Ltd, Joint Venture and the MPWT has
been signed on 20 May 2011.The Contractor’s Project Director and
Contractor’s Project Manager have been appointed and approved by
PMU3 and the CSC.
- Physical accomplishment during the reporting month was 6.3 %,
which is behind the Contractor’s schedule which was 6.73 %
(Variance: - 0.43 %), with an overall accumulated accomplishment of
23.26 % against scheduled 40.64 % (Variance: - 17.38 %).
- (i) Re-survey by CSC’s and Contractor’s survey teams completed
100%, (ii) UXO and demining works completed 100%, (iii)
Renovation/refurbishing of Site camp for the Engineer 100%
completed, (iv) Maintenance of existing road completed 40%, (v)
Clearing & grubbing completed 93%, road way excavation completed
90%, embankment completed 77%, sub-grade completed 41% and
overall structures works completed 16%.
4. Summary of Civil Work Progress of CBF (CW2)
- Contract for Civil Works A.2-Development of Cross Border Facilities
(Contract No. SCCP-CW2) with Contractor Kuy Leang Ky Co., Ltd
Construction Trading Group Co., Ltd and the MPWT has been
signed on 25 November 2011.
- Physical accomplishment during the reporting month was 1.46 %,
which is behind the Contractor’s schedule which was 4.01 %
(Variance: - 2.55 %), with an overall accumulated accomplishment of
6.2 % against scheduled 8.79 % (Variance: - 2.59 %).
- (i) Possession of Site and Notice to Commence the Works have
been issued to CBF Contractor on 13 December 2011 and 23
January 2012, (ii) Re-survey by CSC’s and Contractor’s survey
teams completed 100%, (iii) UXO and demining works completed
100%, (iv) Renovation/refurbishing of Site camp for the Engineer
completed 100% and Preliminary works completed 48%, (v)
Perimeter security fence completed 52%, clearing and grubbing
completed 75%, removal of unsuitable materials completed 30% and
RC piles completed 40%.
5. Summary Civil Work Progress of NR3 (CW3)
Contract No.
Contract Name

Type of works, Section and
Length
CSC Consultant
Draft Bidding Documents
submitted to MPWT
ADB comments on the Draft
Bidding Documents
Response to ADB regarding
their comments
ADB approval on the response
Bidding procedure
Invitation for Bids advertised
Deadline for Bids submission
Pre-bid meeting
Bid evaluation to PMU3
Expected Award/sign Contract

SCCP – CW3
Maintenance of NR3, Kampot to Veal Rinh
Quantity and unit-priced maintenance works on road
section Km 12+300 to Km 32+850 (22.55km).
Performance/output based routine maintenance for two
years on two sections: Km 0+000 to Km 12+300
(12.3km) and Km 32+850 to Km 54+300 (21.45km).
Egis International in association with KACE, KCC,
KCEC, SBK and VIDO.
04 November 2011
06 January 2012
17 January 2012
20 January 2012
National Competitive Bidding
25 January 2012
16 March 2012
08 February 2012
20 April 2012
15 June 2012
6. Summary of Progress Activities of the CSC
- Consulting Services C.1- Construction Supervision Consultant (CSC)
commenced on 23 May 2011. CSC’s Project Manager (Andre
Drockur) has been appointed and approved by PMU3.
- (i) Conducted several joint site inspections and coordination
meetings (Monthly Coordination Site Meetings were conducted
regularly for both CBF project and NR33) and (ii) CSC has reactivated
and
continues
updating
the
project
website
http://www.mpwt.gov.kh/externalfund/sccp, and finalized forty four
(44) deliverable reports and up-loaded to the project web site, (iii)
Attended and monitored all activities related to Social Safeguard
Compliance, (iv) Review/Evaluation/Approval of NR33 and CBF
Contractor’s documents, (v) Reviewed Contractor’s claims of NR33
and CBF (prepared V.O. No.2 for NR33), (vi) Continued working on
the budget and cost estimate of proposed SCCP’s additional
projects: 1- Revised cost of all buildings for SCCP-CW2, 2- Revised
cost estimate for Covered Walkway and building N0. 10, 3- Office
Furniture and Equipment for Cross Border Facilities, (vii) CSC just
completed the bid evaluation report for the Maintenance of NR3
Kampot-Veal Rinh, etc.
7. Detailed Information of NR33 – CW1
7.1. General Contract Data
7. Detailed Information of NR33 – CW1
7.2. Physical Work Progress up to March 2012
7. Detailed Information of NR33 – CW1
7.2. Physical Work Progress up to March 2012 (Continue)
7. Detailed Information of NR33 – CW1
7.3. Payment and disbursement up to March 2012
7. Detailed Information of NR33 – CW1
7.4. Contractor’s Cash Flow Forecast up to March 2012
(including proposed Contract Variation Order No. 2)
7. Detailed Information of NR33 – CW1
7.5. Contractor’s Work Program and Progress up to March 2012
7. Detailed Information of NR33 – CW1
7.6. Progress Feature up to March 2012
8. Detailed Information of CBF – CW2
8.1. General Contract Data
8. Detailed Information of CBF – CW2
8.2. Physical Work Progress up to March 2012
8. Detailed Information of CBF – CW2
8.2. Physical Work Progress up to March 2012 (Continue)
8. Detailed Information of CBF – CW2
8.3. Payment and disbursement up to March 2012
8. Detailed Information of CBF – CW2
8.4. Contractor’s Cash Flow Forecast up to March 2012
8. Detailed Information of CBF – CW2
8.5. Contractor’s Work Program and Progress up to March 2012
THANK YOU