Undulator Production Schedule
Download
Report
Transcript Undulator Production Schedule
In a project, we live or die by the schedule.
After we’re “baselined” it is our plan for what we
will accomplish and when, and it is the
government’s plan for funding us.
If we’re late, the cost goes up. We pay more for
people to work longer than planned, plus the
value of the money gets escalated.
Being late means maybe having to give up or
postpone some things. DOE probably can’t find
more money. They have a schedule too.
Too late and the project may be cancelled.
M. White – June 28, 2004
LCLS Requirements Meeting
To Succeed: Plan Well. Stick to the Plan.
The requirements must be clearly defined.
The responsibilities and interfaces must be
clearly defined.
Use talented and experienced designers.
Use experienced reviewers.
There’s no glory in reinventing the wheel, so
use what we can from other people and
projects. There are enough challenges as it is
without solving old problems over again.
Do not make cosmetic changes late in the game.
M. White – June 28, 2004
LCLS Requirements Meeting
The Exception
The exception is if we are building something
that we know won’t work.
It’s better to be a little late on something that
works than on time with something that
doesn’t.
M. White – June 28, 2004
LCLS Requirements Meeting
We’re here to make sure we all know
and agree on what we’re doing….
The prototype was constructed and tested, and
many of the drawings are close to final.
At this stage, changes will cost time and money,
proportional to the degree of the modifications.
If the requirements have changed significantly
since we began, or if they were misunderstood
and the present system won’t work, changes
must be made.
If there is a disagreement based on personal
preference and both methods will work, consider
whether it is important enough to potentially
result in loss of something else down the road.
M. White – June 28, 2004
LCLS Requirements Meeting
Else we go in circles
M. White – June 28, 2004
LCLS Requirements Meeting
Acquisition Strategy
The undulators were designed and prototyped
by APS, based on the combined experience of
many people over many years. This decreased
the technical and schedule risk to LCLS.
Our design and assembly procedures will be
furnished to the assembly vendors; any changes
by the vendors will require our approval.
As a direct result of the US funding system, we
will procure some critical long-lead parts early
and furnish them to the assembly vendors.
M. White – June 28, 2004
LCLS Requirements Meeting
Long Lead Procurements
Long lead procurements are those undulator
components that are expected to have long
delivery times.
Orders are to be placed as soon as there is
money next FY in order to maintain the
schedule. We assume that there will be money
by November 1st 2004.
Large and/or complex procurements take
months to prepare, and require significant effort
from procurement and project staff.
High-value procurements need DOE signoff.
M. White – June 28, 2004
LCLS Requirements Meeting
Schedule from 50,000 feet
UN30_28430 Undulator System Requirements Frozen
03/31/04 (not?)
UN30_28420 Strongback Motion Spec
04/01/04 (not?)
UN30_FINIM Finish Undulator Magnet Systems
07/24/07
UN30_28440 All Undulator Magnets Ready for Installation
08/06/07
M. White – June 28, 2004
LCLS Requirements Meeting
Long Lead Procurement Issues
Affecting Titanium Strongbacks:
Magnet Blocks
Change in gap size and which direction the gap faces
Change in # of survey monuments and methodology
Change in support and alignment philosophy
Are PZTs needed?
Relationship between quads, BPM, and undulator
needs to be settled for BBA.
No pending changes are known.
Magnet Poles
Internal review was held – change to wingless pole
design, canted spacers is being implemented.
M. White – June 28, 2004
LCLS Requirements Meeting
Titanium Strongbacks
UN33_00270 Internal Design Review - Undulator Systems 04/29/04 06.19.04
UN33_00280 Incorporate Comments from Internal Des Rev. 04/30/04 05/13/04
UN33_10002 Prepare for Final Design Review 05/14/04 06/11/04
UN33_10010 Prep Bid Package - Ti Strongback 05/14/04 07/14/04
UN33_10004 Final Design Review - Und Sys and Ti Strongback 06/14/04
MSC_UN005 CRIT: Contract - Ti Strongback 06/15/04 – error in P3.
UN33_10006 Incorporate Comments from Final Des Rev. 06/15/04 07/13/04
UN33_10020 Release RFP - Ti Strongback 07/15/04
UN33_10030 Vendor Prep Proposal - Ti Strongback 07/16/04 08/13/04
UN33_10040 RCV: Proposal - Ti Strongback 08/13/04
UN33_10050 Evaluate Proposal - Ti Strongback 08/16/04 08/20/04
UN33_10060 AWARD: Contract - Ti Strongback 11/01/04
M. White – June 28, 2004
LCLS Requirements Meeting
Magnet Blocks
MSC_UN010 CRIT: Start Procurement of Magnet Blocks 07/06/04
UN33_20010 Prep Bid Package - Magnet Blocks 07/06/04 07/26/04
UN33_20020 Release RFP - Magnet Blocks 10/04/04
UN33_20030 Vendor Prep Proposal - Magnet Blocks 10/05/04 11/01/04
UN33_20040 RCV: Proposal - Magnet Blocks 11/01/04
UN33_20050 Evaluate Proposal - Magnet Blocks 11/02/04 11/08/04
UN33_20060 AWARD: Contract - Magnet Blocks 11/09/04
UN33_20070 Vendor Fab/Assy - 1st Half Magnet Blocks 11/10/04 03/03/05
UN33_20080 RCV: From Vendor - 1st Half Magnet Blocks 03/04/05
UN33_20090 Vendor Fab/Assy - 2nd Half Magnet Blocks 03/07/05 06/20/05
UN33_20081 50% magnet blocks delivered 06/21/05
UN33_20100 RCV: From Vendor - 2nd Half Magnet Blocks 13/20 06/21/05
M. White – June 28, 2004
LCLS Requirements Meeting
Magnet Poles
MSC_UN015 CRIT: Start Procurement of Magnet Poles 06/14/04
UN33_30010 Prep Bid Package - Magnet Poles 06/14/04 07/02/04
UN33_30020 Release RFP - Magnet Poles 10/04/04
UN33_30030 Vendor Prep Proposal - Magnet Poles 10/05/04 11/01/04
UN33_30040 RCV: Proposal - Magnet Poles 11/01/04
UN33_30050 Evaluate Proposal - Magnet Poles 11/02/04 11/08/04
UN33_30060 AWARD: Contract - Magnet Poles 11/09/04
UN33_30070 Vendor Fab/Assy - 1st Lot Magnet Poles (1-10) 11/10/04 02/16/05
UN33_30080 RCV: From Vendor - 1st Lot Magnet Poles (1-10) 02/17/05
UN33_30082 Vendor Fab/Assy - 2nd Lot Magnet Poles (11-20) 02/17/05 05/19/05
UN33_30086 RCV: From Vendor - 2nd Lot Magnet Poles (11-20) 05/20/05
UN33_30087 Vendor Fab/Assy - 3rd Lot Magnet Poles (21-30) 05/20/05 08/22/05
UN33_30096 50% magnet poles received 05/20/05
UN33_30088 RCV: From Vendor - 3rd Lot Magnet Poles (21-30) 08/23/05
UN33_30090 Vendor Fab/Assy - 4th Lot Magnet Poles (31-33) 08/23/05 11/22/05
UN33_30100 RCV: From Vendor - 4th Lot Magnet Poles (31-33) 11/23/05
M. White – June 28, 2004
LCLS Requirements Meeting
And then…
After the long lead items are awarded, there is a
lag time, during which the vendors procure their
materials, make the objects, and secondary
vendors are machining parts.
Then it’s time to award the undulator assembly
work. The schedule is very tight on that, and we
really cannot afford to delay without putting the
schedule at risk.
M. White – June 28, 2004
LCLS Requirements Meeting
Decisions
In these 2 days, we need to make decisions
about the critical issues so we can proceed.
We can leave room for options, but it must be
clear to us what options are likely. Flexibility is
expensive.
In a Project, Every Day Counts!
M. White – June 28, 2004
LCLS Requirements Meeting
Magnets are Cool
Magnets are Fun
They Make Good Toys
For Everyone
M. White – June 28, 2004
LCLS Requirements Meeting