Undulator System Overview Fabrication Schedule (Includes BLM)

Download Report

Transcript Undulator System Overview Fabrication Schedule (Includes BLM)

LCLS Undulator System
Overview and Fabrication
Geoff Pile
12 November 2008
FAC Review - Undulator System
Geoff Pile
[email protected]
Safety Minute
FY09 - SLAC steps up it’s Work Planning and Control
even further
My personal views and experiences:
Work Planning and Control is an Integral part of good Integrated Safety Management
In most facilities, implementation of ES&H requirements and work control processes at
the activity level has not been effective for non-experimental work activities.
By complying with DOE Work Planning & Control: ALL work in “Research & Development,
Operations, Maintenance & Construction/Destruction should be reviewed”.
APS holds effective weekly pre-project and pre-task briefings associated with
Operations and Shut downs - work planning and control is discussed and approved in
principle.
“Operations Group” requires formal approved work requests prior to work starting
Feedback and lessons learned during task close out. Usual attendance of 25-30 reps and
interested parties
12 November 2008
FAC Review - Undulator System
Geoff Pile
[email protected]
Second Safety Minute
Make time for WP&C - Group Leaders should schedule seperate mandatory 1 to 2
hours weekly WPC meetings. Plan least two weeks work for workers every week. Work
Planner describes plan to workers involved
Documentation: Written assignments with work, safety check lists, referenced
procedures, work request and/or permit numbers and feed back discussions.
Schedule 1 hour weekly mandatory cross training – 1 staff to up to 10 trainees
Practical – perform approved group procedures and make sure they work
Theory - explanations of relevant components, systems and how system
works with LCLS
10 years of weekly cross training helps both staff and trainees
Share the load, plan the work and don’t carry the can yourself!
12 November 2008
FAC Review - Undulator System
Geoff Pile
[email protected]
Overview of Undulator Component Fabrication
Topics
What has and hasn’t been delivered to SLAC as of
November 12th 2008?
What has been… or appear problem areas now?
What is ANL doing in FY09
12 November 2008
FAC Review - Undulator System
Geoff Pile
[email protected]
Controls
12 November 2008
FAC Review - Undulator System
Geoff Pile
[email protected]
Controls Status and Schedule
ALL Controls delivered I month ahead of schedule (23rd June 2008)
September work deferred due to funding issues. ANL Under estimated
contingency effort required to support and complete installation.
PROBLEMS: EPICS Programming
Support and Motion positioning system not functioning properly. SLAC
doesn’t get same results as ANL’s SUT, LTT or LAB View results –
Suspect software
Stein and Shaof working on LTT with APS metrology group – checking
software programming and version #’s, IOC versions - cam calibration etc.
LTT still looks good - Exploring basics first, expect resolution this week.
Voogd has been helping out at SLAC during installation and turn on
Stein will be at SLAC after thanksgiving to help with controls integration
12 November 2008
FAC Review - Undulator System
Geoff Pile
[email protected]
Magnets and Supports
12 November 2008
FAC Review - Undulator System
Geoff Pile
[email protected]
Problem: (discussed at last FAC)
Obtaining X Translation Limits & Stops
for - 5.5 mm over travel - required
redesign
Solution:
69 production units
delivered to SLAC on
6 /20/08
12 November 2008
FAC Review - Undulator System
Geoff Pile
[email protected]
Vacuum
12 November 2008
FAC Review - Undulator System
Geoff Pile
[email protected]
Diagnostics
12 November 2008
FAC Review - Undulator System
Geoff Pile
[email protected]
Diagnostics Status and Schedule 1.4.5
BPM Mechanical – Deliveries complete
Problems – brazing BPM window went well until the last
7 units.
33 brazed production Units
7 units were Indium/tin soldered.
BPM Electrical –
36 Production Units complete
4 spare units very late due to parts shortage at Miteq
ALL parts at Vendors – delivery rescheduled to ANL Nov 21
ANL complete by Nov 28th - Ship to SLAC following week
12 November 2008
FAC Review - Undulator System
Geoff Pile
[email protected]
Diagnostics (Contd)
12 November 2008
FAC Review - Undulator System
Geoff Pile
[email protected]
Beam Loss Monitor
Initially five BLMs will be used to protect the undulators by inhibiting
beam bunches following an “above-threshold” radiation event.
30 production BLMs may be built in FY09 if R&D is successful
Scheduled delivery to SLAC – Berg to install
5 units - 18th of November 2008
Aggressive schedule – Vendor dates slip - may need few extra days to
assemble/checkout – plastic radiator backup solution available for 18th.
Electronics are done
First Article detector fitted well – vendor approved to proceed
Still some components at vendors
Anodizing completed this week
Quartz Promised to ANL Friday 14th
12 November 2008
FAC Review - Undulator System
Geoff Pile
[email protected]
Undulator Inserted Position
12 November 2008
FAC Review - Undulator System
Geoff Pile
[email protected]
BLM Detector and Electronic Interface
Z Integration of Detector Head
12 November 2008
FAC Review - Undulator System
Geoff Pile
[email protected]
Long Term Test
Does LTT match SUT?
 LTT testing was put on hold at the
end of August
 ANL approved to finish more
comprehensive and comparative
results
Requires matrixed staff for:
 Alignment, mechanical and
electrical assembly, Controls and
data acquisition etc. Task
management, work planning and
control.
 The effort is not insignificant ($30
- $40K) but was in MW’s original
budget and it is essential
12 November 2008
FAC Review - Undulator System
Geoff Pile
[email protected]
Status and Schedule
Undulator System Management and Integration
CPR & Costs to go –
Generally in good shape. Some unplanned effort has been
required in the last two months to solve problems and meet
installation schedules.
ANL Controls CPR for October with positive $200K variance
Some of it will solve integration problems ( a month or two of
Voogd, Shoaf and Steins’ effort)
Most spares costs were moved to OPC in September.
SLAC has funded essential ANL work in FY09 MOU
12 November 2008
FAC Review - Undulator System
Geoff Pile
[email protected]
Summary
Almost all work related to installation will be completed by
late November/ early December 2008 –
Production BLMs? TBD (2009)
Argonne Construction team started rolling off the project in
July – mainly documentation and LTT effort is required to
wrap things up.
September was a tough month – a few essential people
now catching up with outstanding work
FY09 – the original small budget included for installation
and commissioning support has been increased to allow
better integration and problem resolution
12 November 2008
FAC Review - Undulator System
Geoff Pile
[email protected]