GLAST LAT Project
I&T Integration Kickoff Meeting 03/09/04
GLAST Large Area Telescope:
Gamma-ray Large
Area Space
Telescope
I&T Integration Kickoff Meeting
Overview
March 9th, 2004
Pat Hascall
SLAC
System Engineering Manager
[email protected]
650-926-4266
LAT System Engineering
1
GLAST LAT Project
I&T Integration Kickoff Meeting 03/09/04
Topics
•
•
•
•
Test plan flow
Strategy for completion
Documentation
Schedules
LAT System Engineering
2
GLAST LAT Project
I&T Integration Kickoff Meeting 03/09/04
Test Planning Flow
Test Plan Flow
Test Flow
Pat Hascall
Feb 9, 2004
Test Flow
Mechanical
Subsystem Test
Plan
LAT-TD-00493
LAT Instrument
Performance
Verification Plan
LAT-MD-00408
LAT Flight
Software Test
Plan
LAT-TD-00786
SVAC Plan
LAT-MD-00446
LAT Environmental Test Sequence
LAT-MD-02717
LAT Assembly Sequence
LAT-MD-00676
Thermal System
Test Plan
LAT-TD-tbd
Work Orders
Work Orders
Electronics Test
Plan
LAT-TD-00296
Tracker Tower
Test Plan
LAT-TD-00155
Test definitions
Calorimeter Test
Plan
LAT-TD-00262
High Level
Test Plans
ACD Test Plan
ACD-PLAN000050
LAT Performance
and Operations
Test Plan
LAT-MD-02730
Test Toolbox
-Comprehensive
Test Proc
-Functional Test Proc
-Mechanical
Procedures
-Lower level generic
procedures
LAT Integration
and Test Plan
LAT-MD-01376
Test
Proc
Integration
Test
Proc
Comp.
Test
Proc
Commisioning
LAT Instrument
Survey Plan
LAT-MD-00895
Survey
Proc
Mass/
CG
Proc
Comp.
Test
Proc
EMI/
EMC
Proc
Dynamics
Proc
Comp.
Test
Proc
Thermal
Vac
Proc
Comp.
Test
Proc
Mass/
CG
Proc
Envir. Test
LAT Weight and
CG Measurement
Plan
LAT-MD-01598
LAT EMI/EMC
Plan
LAT-MD-0xxxx
LAT Dynamics
Plan
LAT-MD-01196
LAT Thermal Test
Plan
LAT-MD-01600
Required Tests Per Phase
MAR
Generic Test Requirements
Test Flow
Other notes/issues
1-Van De Graf test, how and where does it fit
2-The science cal plan calls for EM tests, not covered under this flow
3-How does Steve Ritz data flow verification fit into this plan?
4-Where are algorithms for EGSE software (and SAS software) specified? They
need to be consistent
Required Tests Per Phase
Generic Processes and Requirements
Other plans/procedures that are valuable resources:
LAT Integration and Test Subsystem Electrical Performance Test Plan (Wai-LAT-MD-01055)
GLAST LAT I&T Testing Requirements Document - (Claus - LAT -TD-02834)
LAT SVAC Test Requirements Plan (Eduardo, LAT-MD-01587)
Sequencing
Test Specific Rqmts
LAT System Engineering
3
GLAST LAT Project
I&T Integration Kickoff Meeting 03/09/04
Strategy for Completion
• Phased approach to provide planning necessary for first 6
months of integration
• Focus is on Calorimeter and Tracker first, followed by DAQ
boxes, then ACD
LAT System Engineering
4
GLAST LAT Project
I&T Integration Kickoff Meeting 03/09/04
Near Term Test Planning Flow
Test Flow
Mechanical
Subsystem Test
Plan
LAT-TD-00493
LAT Instrument
Performance
Verification Plan
LAT-MD-00408
LAT Assembly Sequence
LAT-MD-00676
Thermal System
Test Plan
LAT-TD-tbd
LAT Flight
Software Test
Plan
LAT-TD-00786
SVAC Plan
LAT-MD-00446
Work Orders
Electronics Test
Plan
LAT-TD-00296
Tracker Tower
Test Plan
LAT-TD-00155
Test definitions
Calorimeter Test
Plan
LAT-TD-00262
High Level
Test Plans
ACD Test Plan
ACD-PLAN000050
LAT Performance
and Operations
Test Plan
LAT-MD-02730
Test Toolbox
-Comprehensive
Test Proc
-Functional Test Proc
-Mechanical
Procedures
-Lower level generic
procedures
Test
Proc
Test
Proc
Integration
LAT Integration
and Test Plan
LAT-MD-01376
LAT System Engineering
5
GLAST LAT Project
I&T Integration Kickoff Meeting 03/09/04
LAT Assembly Sequence
• LAT Assembly Sequence LAT-MD-00676
– Contents
• Defines in detail the sequence of operations necessary
to integrate the LAT
• Focuses on mechanical operations, and calls out
electrical tests to be run from separate procedures
– Status
• Draft completed, some refinement needed
– Schedule
• Personnel reprioritized, ETC TBD
• Mitigation
– Sufficient detail available to proceed, remaining work is
primarily clean up
LAT System Engineering
6
GLAST LAT Project
I&T Integration Kickoff Meeting 03/09/04
LAT Performance and Operations Test Plan
•
LAT Performance and Operations Test Plan LAT-MD-02730
– Contents
• Defines at a high level each of the individual tests (e.g. TE103,
Tracker Bias Current)
• Define when the test will be run (Functional Test,
Comprehensive Test, Integration test …)
– Status
• Draft initiated (samples on next viewgraphs)
• Details worked in weekly meetings with I&T and subsystems
• Will include definition of 2 tower test derived from End-to-End
Committee results
– Schedule
• First cut out by end of month as part of an incremental release
series
• Mitigation
– Information generated by a team effort (including members of
End-to-End Committee), so test development can proceed in
parallel
LAT System Engineering
7
GLAST LAT Project
I&T Integration Kickoff Meeting 03/09/04
Test Definition Sample
• Tracker GTRC configuration register and readback
– The GTRC chips are sequentially addressed and their
configuration registers loaded with a bit pattern. Each time
the register is read back and checked for errors. The test is
repeated with the complement of the bit pattern. The test
then is repeated with a broadcast address for writing the
register, followed by sequential readback. (Based on
Tracker Test TE201)
• FSW Tracker Configuration Test
– This test shall verify the ability of the SIU to configure the
TKR subsystem as desired and read back the necessary
configuration information to completely determine the TKR
subsystem configuration (Based on FSW test 7b)
LAT System Engineering
8
GLAST LAT Project
I&T Integration Kickoff Meeting 03/09/04
Test Instance Format Sample
ID
Two
Tower
…
Test
Incoming
Tower
Comp.
Power Consumption
X
X
X
Temperature
X
X
X
Leakage Current
X
X
X
GTRC configuration
X
X
X
GFTE left/right configuration
X
X
X
GFTE split configuration
X
X
X
Reset
X
X
Threshold Scan
X
X
X
X
Charge Injection Scan
X
Gain and Noise
X
X
X
X
Layer Timing
X
X
X
X
Occupancy
X
X
X
X
Occupancy w/readout
X
X
X
X
Muon Scan
X
X
High Rate/ Deadtime
X
X
X
X
X
X
…
Combined Charge Injection Scan
…
FSW Tracker Configuration Test
LAT System Engineering
X
9
GLAST LAT Project
I&T Integration Kickoff Meeting 03/09/04
Integration Drawings
• Integration Drawings
– Contents
• Defines how the pieces delivered to I&T relate and
provides some assembly information
• In some cases, provide a model with internal details
removed to facilitate model usage (outline drawings)
– Status
• Drawing tree defined
• Model and drawing completion on hold
– Schedule
• Will take approximately 2 months after effort is restarted
to complete model integration and drawings
• Mitigation
– Many of the models can be used now to get views
necessary for integration procedures
LAT System Engineering
10
GLAST LAT Project
I&T Integration Kickoff Meeting 03/09/04
Drawing Tree
LAT Level Drawing Tree
LAT-DS-01624
LAT Assembly
Drawing
Rev 5
Jan 15, 2004
LAT-DS-01628
-Y Radiator
Outline Drawing
LAT-DS-TBD01
MLI
Pat Hascall
LAT-DS-01629
+Y Radiator
Outline Drawing
LAT-DS-02563
LAT Instrument
Assembly
LAT-DS-TBDxx
X-LAT Plate
Assembly Outline
Drawing
LAT-DS-02443
Heat Pipe EMI
Cover
LAT-DS-01626
Anticoincidence
Detector
Assembly
LAT-DS-02111
Cable Assy, DAQACD External
LAT-DS-01247
X-LAT Plate
Assembly
LAT-DS-2812
ACD to
Temperature
Sensor Bracket
LAT-DS-02110
ACD to RF Shield
(telemetry)
LAT-TBD41
Bracket Assy,
Temperature
Sensor
LAT-DS-02137
Assembly,Heater
Control Interface
Box
LAT-DS-02109
Heater Control
Interface, Box to
RF Shield
LAT-DS-TBD15
MLI
2054500
Anticoincidence
Detector
LAT-DS-02561
LAT Tower and
Electronics
Assembly
LAT-DS-02562
LAT Internal
Cable Assy
LAT-DS-01494
GASU Spider
LAT-DS-01696
Power Distribution
Unit
LAT-DS-01264
EMI Skirt
Connector Panel1 LH +X
LAT-DS-01862
SIU Assembly
LAT-DS-02533
EPU Assembly
LAT-DS-01611
GASU Box
Assembly
LAT-DS-01988
EMI Skirt
Connector Panel2 RH +X
LAT-DS-01989
EMI Skirt
Connector Panel3 LH -Y
LAT-DS-01990
EMI Skirt
Connector Panel4 LH -Y
LAT-DS-01734
Support, Cable
Way
LAT-DS-01487
Flange Screw
LAT-DS-01741
Upper Tray,
Narrow, Cable
Way
LAT-DS-02560
LAT Tower
Assembly
Drawing
LAT-DS-02211
Cable Guide, +Y
Side, Thermal
Shunt
LAT-DS-02559
CAL-TEM-PS
Module Assembly
LAT-DS-01643
Assembly, Tower
Electronics
Module/Power
Supply
LAT-DS-01735
Two Way
Transition, Cable
Way
LAT-DS-01742
Standoff
Modification,
Cable Way
LAT-DS-02212
Cable Guide, -Y
Side, Thermal
Shunt
LAT-DS-01580
Grid Box Base
Assembly
LAT-DS-01554
Calorimeter -TEM
Standoff
LAT-DS-01625
Calorimeter
Module Outline
Drawing
LAT-DS-01736
Three Way
Transition, Cable
Way
LAT-DS-02192
Lower Tray End,
Cable Way
LAT-DS-02213
Bottom Top Cable
Block
LAT-DS-1627
Tracker Module
Outline Drawing
LAT-DS-01392
LH Down Spout
Heat Pipe SCD
LAT-DS-02004
LH Heat Pipe
Patch Panel
LAT-DS-02005
RH Heat Pipe
Patch Panel
LAT-DS-02003
X Center EMI
Shield
LAT-DS-02007
RH X EMI Shield
LAT-DS-02006
LH X Emi Shield
LAT-DS-02002
Center EMI Shield
LAT-DS-02179
Empty Box
LAT-DS-01991
EMI Skirt
Connector Panel6 LH -X
LAT-DS-01737
Four Way
Transition, Cable
Way
LAT-DS-01992
EMI Skirt
Connector Panel6 RH -X
LAT-DS-01738
Lower Tray,
Short, Cable Way
LAT-DS-02194
Upper TrayNarrow End,
Cable Way
LAT-DS-02193
Upper Tray-Wide
End, Cable Way
LAT-DS-02214
Middle Cable
Block
LAT-DS-01391
RH Down Spout
Heat Pipe SCD
LAT-DS-02215
Cover Plate +Y
Side Thermal
Shunt
LAT-DS-02576
LH Corner Shear
Plate
LAT-DS-01993
EMI Skirt
Connector Panel7 LH +Y
LAT-DS-01739
Lower Tray, Long,
Cable Way
LAT-DS-02195
Baseplate, Cable
Way
LAT-DS-01994
EMI Skirt
Connector Panel8 LH +Y
LAT-DS-02092
Cable Assy, DAQACD Internal
LAT-DS-02099
Cable Assy, DAQ/
SIU-Spacecraft
Power
LAT-DS-01740
Upper Tray, Wide,
Cable Way
LAT-DS-02196
Baseplate
Standoff
Modification,
Cable Way
LAT-DS-02093
Cable Assy, DAQSpacecraft 1PPS
LAT-DS-02100
Cable Assy, DAQ/
PDU-VHCP Temp
Monitor
LAT-DS-02094
Cable Assy, DAQSpacecraft 1553
LAT-DS-02101
Cable Assy, DAQ/
PDU-Radiator
Temp Monitor
LAT-DS-02102
Cable Assy, DAQ/
PDU-ACD Bea
Temp Monitor
LAT-DS-02106
Cable Assy, DAQ/
TEM-GASU
Command
LAT-DS-02333
Support Post,
Cable Way
LAT-DS-02096
Cable Assy, DAQ/
PDU-Spacecraft
Power
LAT-DS-02095
Cable Assy, TEM
PDU Power
LAT-DS-02103
Cable Assy, DAQ/
PDU-GASU
Command and
Power
LAT-DS-02107
Cable Assy, Grid
Temp Base Plate
LAT-DS-02097
Cable Assy, DAQ/
SIU-Spacecraft
Discrete
LAT-DS-02104
Cable Assy, DAQ/
SIU-GASU
Communications
LAT-DS-02098
Cable Assy, DAQ/
SIU-Radiator
Heater Control
LAT-DS-02105
Cable Assy, DAQ/
SIU-PDU
Command
LAT-DS-02108
Cable Assy, DAQ/
EPU-PDU Power
LAT-DS-02216
Cover Plate -Y
Side Thermal
Shunt
LAT-DS-02577
RH Corner Shear
Plate
LAT-DS-02578
Quarter Point
Shear Plate
LAT-DS-02579
Center Shear
Plate
LAT-DS-02581
CAL Plate
Washer
LAT-DS-02651
Dowel Pin, 0.25
OD by .875 L
LAT-DS-02653
Dowel Pin, 0.375
OD by .875 L
LAT-DS-02493
Corner Pin
Retainer
LAT-DS-02494
Quarter Point Pin
Retainer
LAT-DS-02495
Center Pin
Retainer
LAT-DS-00722
Tracker Module
Assembly
Xxx
Calorimeter
LAT-DS-01481
Tower Electronics
Module
LAT-DS-01482
Tower Power
Supply
LAT System Engineering
11