Transcript ppt
GLAST LAT Project 3 May 2005 LAT Requirements Verification in TVAC LAT Mission Thermal Requirements are provided in four documents: 1. 433-MAR-0001, “Mission Assurance Requirements”, Sections 4.6, 10.4 2. LAT-SS-00778, “LAT Environmental Specification”, Section 11.1,2,3 3. LAT-MD-00408, “LAT Program Instrument Performance Verification Plan”, Sections 5, 7.1.1.8 4. LAT-SS-00010-02, “LAT Performance Specification – Level II (B)”, Section 5.3.11.1,2 Requirements verification by individual test is summarized in Test Segment Chart and detailed in the LAT TVAC Test Plan. TIM 1 GLAST LAT Project 3 May 2005 LAT Requirements Verification LAT Thermal Environmental TIM Source Parameter Surv. ColdCase Nom HotCase Units Earth IR on any exposed surface 208 208 265 265 W/m2 Earth Albedo on any exposed surfaces 0.25 0.25 0.4 0.4 Solar Flux on surfaces exposed to +X direction 1286 1286 1419 1419 W/m2 IRD 3.2.3.5, Table 3-3 Solar flux due to 1 deg glancing view of the sun on +/- Y surfaces 0 0 0 6 W/m2 SPS 3.4.5.1 Orbit-average absorbed solar flux on one Radiator due to re-pointing 0 0 27 0 W SPS 3.4.5.1 IRD 3.2.3.5, Table 3-3 IRD 3.2.3.5, Table 3-3 2 GLAST LAT Project 3 May 2005 LAT Requirements Verification LAT Environmental Test Loads and Durations Test Test Levels/Durations Qual Protoqual Acceptance Thermal Vacuum Cycling Temperature5 Normal Operation Survival Rate6 Vacuum Number of Cycles Max/Min Predict ±10° C Max/Min Predict ±10° C Max/Min Predict ±5° C Max/Min Predict ±10° C Max/Min Predict ±10° C Max/Min Predict ±5° C <20°C/Hour <20°C/Hour <20°C/Hour -5 -5 <1X10 Torr <1X10 Torr <1X10-5 Torr 12 4 4 5- Normal operating temperature for the LAT is 0° C to 30° C. Survival temperature is -2° C to 40° C. 6-T he CAL module must not exceed a 10° C per hour rate TIM 3 GLAST LAT Project 3 May 2005 LAT Thermal Vacuum Testing Timeline 50 LAT Thermal-Vacuum Test Timeline 45 LAT LAT Init, Hot-PF LAT LAT Init, Surv Aliveness CPT Surv Aliveness Hot-TB LPT, SVAC Open-Door CPT, SVAC 40 Disable 35 Warm -Up LPT Cool-Dow n LPT Enable Cool-Dow n LPT Warm -Up LPT Cool-Dow n LPT Thermal-Vacuum Cycle Testing Cold TCS Testing Cold Operational Thermal-Balance Cold PFQ Performance Testing Hot PFQ Perf Cold Survival Thermal-Balance 10 Warm -Up LPT Cool-Dow n LPT Hot TCS Testing Bakeout 15 Hot Operational Thermal-Balance 25 20 LAT Init, Aliveness Enable Turn Off Hot Plateau CPT Hot Plateau LPT Vent Disable Open Door Prep Pumpdown Temperature (deg. C) 30 Hot Plateau LPT Open Door Close- Open-Door CPT, SVAC Warm -Up LPT 5 LAT LAT Init, Cold-PF Surv Aliveness CPT 0 -5 Cold-TB LPT, SVAC LAT Init, Aliveness RIT Temp TCS Turn On, Aliveness Extreme LAT Temp Cold Plateau LPT Cold Plateau LPT 1 May 2005 Update Cold Plateau CPT -10 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Time (days) TIM 4 17 18 19 20 21 22 23 24 GLAST LAT Project 3 May 2005 Thermal Vacuum Test Segments Individual Test Segments are Conducted in the Following Order According to LAT Document [TBD] “LAT TVAC Test Procedures” • • • • • • • • • • • • Chamber Pump Down Bakeout Hot Operational Thermal Balance Hot Operational Thermal Control System Hot Operational Peak Power Hot Performance Cold Survival Thermal Balance Cold Performance Cold Operational Thermal Balance Cold Operational Thermal Control System Thermal Cycling Chamber Recovery During and between certain above tests, LAT electrical performance tests will be conducted according to the LAT “Electrical Performance Test Procedure" TIM 5 GLAST LAT Project 3 May 2005 Chamber Pump Down • Electrical Performance Tests, chamber door open. • Pump down according to NRL procedures to <1.E-05 Torr • Activate LAT power buses, but LAT is powered OFF. • Chamber shroud cool down according to NRL procedures. – Adjust simulated environmental temperature hardware to maintain LAT assembly between 20 and 40 degC. TIM 6 GLAST LAT Project 3 May 2005 Bakeout • Adjust simulated environmental temperature hardware to maintain LAT assembly at 45 degC • Monitor out-gassing with Thermal Quartz Crystal Microbalance (TQCM) according to the LAT Contamination Control Plan • Duration of bakeout according to TQCM criteria in LAT Contamination Control Plan TIM 7 GLAST LAT Project 3 May 2005 Hot Operational Thermal Balance • Simulated environmental temperature hardware adjusted to provide hot case end-of-life (EOL) environmental heat loads. • Thermal balance is attained when there is less than a 5% energy imbalance in the LAT instrument. The RIT is expected to stabilize below +15 degC without TCS control. • Science verification and calibration tests are performed (power dissipation is unaltered). • Thermal data used to correlate the LAT systems level Thermal Math Model, which provides flight temperature predictions. TIM 8 GLAST LAT Project 3 May 2005 Hot Operational Thermal Control System Hot TCS Testing consists of three tests: 1. RIT control using primary reservoir heaters and symmetric orbit average load. – Only primary reservoir heaters enabled (redundant heaters are controlled by B-side SIU, so this is standard). – Primary and redundant radiator survival (antifreeze) heaters are enabled, but are expected to remain off. – RIT initial set point same as that achieved previously in hot operational thermal balance. – Demonstrate RIT control by incrementally increasing RIT set point to +15 degC and then lowering back to original level. 2. Peak power. – Increase LAT power to peak levels (706W) for 10 minutes or until a steady state has been achieved at the discrition of the thermal engineer. – Monitor LAT temperatures to assure they remain within limits 3. RIT control using redundant reservoir heaters at nominal power with transient environmental loading – Configure LAT with only redundant reservoir heaters enabled. – Control radiator simulated environmental temperature hardware to follow hot case temperature profiles. – Demonstrate RIT control by incrementally increasing RIT set point to +15 degC and then lowering back to original set level. – Verify ability of TCS to maintain RIT stable within +/- 7 degC under transient environmental radiator loads. TIM 9 GLAST LAT Project 3 May 2005 Radiator Sink Transient Temperatures – Hot Case Radiator Sink Temperature Hot CaseTransient 20 0 -20 Temperature, deg. C -40 -60 -80 -100 Rad_1 Ave -120 Rad_2 Ave -140 0 10 20 30 40 50 60 70 80 Time, minutes TIM 10 90 100 GLAST LAT Project 3 May 2005 Hot Performance • Simulated environmental temperature hardware adjusted “until as many LAT temperatures as feasible are 10 degC above their predicted operating limits.” This will be the hot proto-qualification temperature limit. • Thermal stability is attained when certain monitored temperatures* are within 3 degC [TBD] of target/goals. • After LAT temperatures are stable, execute a LAT Power-On/Off/On sequence according to LAT Electrical Test Procedure. * Note: “Certain monitored temperatures” are a set of temperature sensors that represent the complete temperature distribution within the LAT. TIM 11 GLAST LAT Project 3 May 2005 Cold Survival Thermal Balance • Simulated environmental temperature hardware adjusted to provide environment for cold survival case. • Transition according to LAT TVAC Test Procedure. LAT is powered off after LPT. – Primary and redundant survival (Grid and radiator) heater circuits are enabled. – Primary and redundant reservoir heater circuits are enabled. • After reaching primary set point temperature, the primary survival heaters will cycle and the redundant heaters will remain off since the redundant temperature set point is set below that of the primary • Redundant reservoir heater is thermostatically controlled and will turn off when temperature increases above +15 degC. Primary heater will maintain reservoir at near +40 degC at 100% duty cycle. • Thermal balance attained when there is less than a 5% energy imbalance in the LAT. RIT is expected to stabilize near - 6 degC. • Following thermal balance, redundant Grid and radiator survival heater circuits are enabled and primary circuits are disabled, and environmental temperatures are decreased slightly until redundant thermostats engage the redundant heaters. EGSE must be designed for this function and also to override reservoir heater circuit enabling. TIM 12 GLAST LAT Project 3 May 2005 Cold Performance • Simulated environmental temperature hardware is adjusted until “as many LAT temperatures as feasible are 10 degC below their predicted operating limits.” This will be the cold proto-qualification temperature limit. – Not practical at cold end, since cold performance and operational limits are below cold survival limit. • Thermal stability is attained when certain monitored temperatures [TBD] are within 3 degC [TBD] of target/goals. • After LAT temperatures are stable, execute a LAT Power-On/Off/On sequence according to LAT Electrical Test Procedure. TIM 13 GLAST LAT Project 3 May 2005 Cold Operational Thermal Balance • Simulated environmental temperature hardware adjusted to provide cold case beginning-of-life (BOL) environmental heat loads. • Thermal balance is attained when there is less than a 5% energy imbalance in the LAT instrument. The RIT is expected to stabilize below -10 degC without TCS control. • Science verification and calibration tests are performed (power dissipation is unaltered) • Thermal data used to correlate the LAT systems level Thermal Math Model, which provides flight temperature predictions. TIM 14 GLAST LAT Project 3 May 2005 Cold Operational Thermal Control System Cold TCS Testing consists of three tests: 1. RIT control using primary reservoir heaters and symmetric orbit average load. – Only primary reservoir heaters enabled (redundant heaters are controlled by B-side SIU, so this is standard). – Primary and redundant radiator survival (antifreeze) heaters are enabled, but are expected to remain off. – RIT initial set point same as that achieved previously in cold operational thermal balance. – Incrementally increase RIT set point to +15 degC and then lower back to original level. 2. RIT control using redundant reservoir heaters at nominal power with transient environmental loading ─ Configure LAT with only redundant reservoir heater enabled. – Control radiator simulated environmental temperature hardware to follow cold case temperature profiles. – Demonstrate RIT control by incrementally increasing RIT set point to +15 degC and then lowering back to original set point. – Verify ability of TCS to maintain RIT stable within +/- 7 degC under transient environmental loads. 3. TCS Parameter Upload. – Enabling antifreeze protection at higher temperatures. – Changing reservoir heater control band. – Disabling an individual VCHP. – Rejection of impossible or conflicting parameters. TIM 15 GLAST LAT Project 3 May 2005 Radiator Sink Transient Temperatures -50 -55 -60 -65 -70 -75 -80 -85 -90 -95 -100 RAD1 AVG RAD2 AVG 57 60 58 8 08 58 8 56 59 8 04 59 8 52 60 8 00 60 8 48 60 8 96 61 8 44 61 8 92 62 8 40 62 8 88 63 8 36 8 Temperature (Degrees C) Sink Temperature Beta 0 Cold Case Time (Seconds) TIM 16 GLAST LAT Project 3 May 2005 Thermal Cycling • A total of four thermal cycles will be performed consisting of – four hot plateau – four cold plateau – eight transitions • At each plateau, electrical performance testing according to timeline and LAT Electrical Test Procedure TIM 17 GLAST LAT Project 3 May 2005 Chamber Recovery • Chamber recovery according to NRL Procedures – Return to ambient temperature • simulated environmental temperature hardware adjusted to maintain LAT assembly between 22 and 30 degC. RIT set point temperature adjusted accordingly. • when ambient temperature achieved, LAT is powered off and power circuits disabled. • all GSE power circuits disabled. – Return to ambient pressure • Check room humidity to be in proper range before opening vacuum chamber door. TIM 18 GLAST LAT Project 3 May 2005 LAT TVAC Test Segments Test Segment Test Segment Description Hot Operational TCS Testing RIT Control Hot Op Hot Op Cold Surv PumpHot Op Hot Perf Bakeout Prim, Red Peak Transient T-Bal, Htr down T-Bal Test (QT) Rsvr Htr's Power (TCS) Func Asymmetric Maintain Symmetric Symmetric Maintain Symmetric transient test article orbit avg orbit avg test article Evacuate orbit avg load. RIT Survival at 50°C load. RIT load. RIT at hot QT chamber load without control by heater test +0C/-3C for control by control, 10 +10C/-0C for RIT control prim/red rsvr TBD hrs prim rsvr htrs min ? TBD hours htrs ColdOperational Operational TCS TCS Testing Testing Cold Cold Op (TCS) RIT Control Cold Op Cold Perf Cold Op Parameter Prim, Red Transient Test (QT) T-Bal Upload Rsvr Htr's (TCS) Asymmetric Symmetric Asymmetric Symmetric transient orbit avg transient load. orbit avg load. RIT load. RIT RIT control by load w/out control by control by prim rsvr htrs RIT control prim/red rsvr prim rsvr htrs htrs Thermal Cycle 4 Thermal cycles LAT Status LAT Power @ RIT, W STE Heat Sinks Radiator Shrouds, °C Reservoir Shrouds, °C 0 0 615 615 708 615 0 0 float, initially > -2 495 --- TBD TBD TBD TBD TBD TBD TBD TBD profile profile TBD TBD TBD TBD Bus Simulator, °C -- 50 50 50 50 50 50 0 0 0 0 5 0 5 0 5 0 5 0 0 0 Primary enabled, OFF enabled, OFF enabled, OFF enabled, OFF enabled, OFF enabled, OFF enabled, OFF Redundant disabled disabled disabled disabled disabled disabled disabled Primary enabled, OFF enabled, OFF enabled, ON enabled, cycling enabled, cycling enabled, cycling Redundant disabled disabled disabled disabled disabled (dis)enabled, cycling (dis)enabled, cycling disabled Primary enabled, OFF enabled, OFF enabled, OFF enabled, OFF Redundant disabled disabled disabled disabled enabled, OFF enabled, OFF 4.6 (4), 10.4 (9) 4.6 (1,4), 4.6.1 (5) Grid Mass, °C SC Heat Leak Sim's Rad Strut per Rad, W Flexure Sim per Flex, W Grid Make-Up Heaters, W -- 44 float, initially float, initially float, initially float, initially < 20 < 20 < 20 < 20 32? float, initially > -4 float, initially float, initially > -2 > -2 float, initially > -2 495 495 495 615 TBD TBD TBD TBD profile profile profile profile TBD TBD -10 -10 10 -10 -10 +50 to -10C 0 0 155 (dis)enabled, cycling (dis)enabled, cycling 0 0 0 0 0 0 0 0 enabled, ON enabled, OFF enabled, OFF enabled, OFF disabled disabled disabled disabled enabled, ON enabled, ON enabled, cycling enabled, ON to 15ºC, disabled disabled enabled, ON enabled, OFF enabled, OFF enabled, OFF disabled disabled disabled disabled Reservoir Heaters, W (dis)enabled, enabled, cycling cycling (dis)enabled, disabled cycling Rad Anti-Freeze Heaters, W enabled, OFF enabled, OFF enabled, OFF disabled (dis)enabled, cycling (dis)enabled, cycling TQCM Temp Requirements Addressed 433-MAR-0001 LAT-SS-00010-02 5.3.11.1, 5.3.11.2 LAT-SS-00778-02 11.1 (1), 11.2 (2,3,4) LAT-MD-00408-03d TIM 7.1.1.8 (8) 7.1.1.8 (4,8) 4.6 (2,3) 4.6 (1,4), 4.6.1 (5) 4.6 (2,3) 5.3.11.1, 5.3.11.2 11.2 (4) 11.2 (4) 4.6 (4), 4.6.2 (6,7,8) 4.6 (1,4), 4.6.1 (5) 5.3.11.1, 5.3.11.2 11.2 (4) 11.3 (5) 11.1 (1), 11.2 (2,3,4), 11.3 (5) 11.3 (5) 11.1 (1), 11.2 (2,3,4) 7.1.1.8 (5,8) 7.1.1.8 (4,5,8) 7.1.1.8 (5,8) 7.1.1.8 (4,8) 19 11.2 (4) 11.2 (4) 5 (1), 7.1.1.8 (2,3,6,7,8) GLAST LAT Project 3 May 2005 TVAC LAT Cool Down Comparison Cool Down Scenarios During LAT TVAC Cycling 80 Grid Time to Reach Cold Extreme Temperature, Hours 70 CAL 60 TKR 50 40 30 20 10 0 1-Ref, Power ON, Sinks @90°C,No HEX 2-Ref, Sinks @ 150°C 3-Ref, with HEX 4-Pwr OFF, 5-Pwr OFF, 6-Pwr OFF, 6a-Pwr 6b-Pwr 6c-Pwr 7-Pwr OFF, Resrv. Heat Resrv. Heat Resrv. Heat OFFOFFOFFResrv. Heat ON ON, with OFF ON@25C, ON@15C, ON@8C, OFF, with HEX Resrv. Heat Resrv. Heat Resrv. Heat HEX OFF, Sinks OFF, Sinks OFF, Sinks @-150°C @-150°C @-150°C Cool Down Scenario TIM 20 GLAST LAT Project 3 May 2005 Simulated Environmental Temperature – Cal Rod Concept “Picture Frame” baffles; polished aluminum with holes for Cal Rod sockets Height of ACD Height of radiator 6” 6” – 8” Support structure, low e with heaters or blanketed; 15” – 20” from radiator Width of radiator TIM 21 GLAST LAT Project 3 May 2005 LAT TVAC Personnel Requirements Category 1 2 3 4 5 6 7 8 9 10 Description Test Conductor (alternate between Cat 2 and Cat 4 or 5) Thermal Engineer Chamber/Facility Engineer LAT Operations/Systems Engineer LAT Electrical/Performance Scientist LAT Software Engineer Subsystem Specialist, ACD Subsystem Specialist, TKR Subsystem Specialist, CAL Subsystem Specialist, E-Box/Cabling 30 day test x 3 shifts/day = 90 shifts Cat 1 – 3: all shifts Cat 4: all shifts initially, part time during cycling Cat 5: all shifts initially, then as necessary, always during electrical performance tests Cat 6: all shifts initially, then as necessary Cat 7 – 10: all shifts initially, then during electrical performance tests Estimated total effort: 400 shifts x 8 hr/shift = 3200 hrs TIM 22