Transcript Management
GLAST LAT Project Gamma-ray Large Area Space Telescope LAT F2F Mgrs Meeting WBS 4.1.1 Instrument Management Tanya Boysen LAT Project Controls Manager [email protected] November 17, 2004 1 GLAST LAT Project LAT F2F Mgrs Meeting Summary of Cost Changes • Overall methodology: Change in instrument delivery date assumed to be from 7/14/05 to 9/28/05, so added 2.5 months schedule at current rate (~$900K) In addition: • HEPL – Incorporates pending changes in June 04 proposal to NASA – Adds two graduate students – Pending review by Peter Michelson • UCSC – Adds students, reflects one-year reduction in budget (change in funding source) November 17, 2004 2 GLAST LAT Project LAT F2F Mgrs Meeting Summary of Cost Changes, Cont’d • SLAC – Reflects funding change for computer support – Extends peak level of PMCS support for four months (rather than 2.5) to keep pace with project schedule; adds incremental budget for rebaseline implementation – Increases budget for Lockheed Martin thermal support to full-time November 17, 2004 3 GLAST LAT Project LAT F2F Mgrs Meeting Change Detail OBS Description Notes Delta K$ GSFC HEPL NRL UCSC November 17, 2004 Extend Sci. Prep./Instr. Sci. $ 48 Total GSFC $ 48 Adjust for Jun04 Proposal Extend PI (chargeable thru 9/30/05 only) Extend Management Extend Sci. Prep. Add 2 Grad. Students Extend Sci. Prep. Extend EEE Parts Extend Sci. Prep. B. Atwood Off-Project FY05 CV thru Oct 04 $ $ $ $ $ (32) 58 25 63 126 Total HEPL $ 240 $ $ 15 75 Total NRL $ 90 $ $ $ 30 (123) 51 Total UCSC $ (42) From Nov 04 thru Oct 05 4 GLAST LAT Project LAT F2F Mgrs Meeting Change Detail, Cont’d SLAC November 17, 2004 Extend Management (2600003) Delete Computer Support Extend Project Controls (2600005) Add'l Support for Rebaseline (AIM) Extend AIM contract thru Jul. 05 Add'l Travel for IDE (2600231) Extend D. Plaza to 7/14/05 Extend M. Foss Extend Management for IDE (2600232) Extend Fab. Engineering (2600233) Add Jeff Wang FT in FY05 Extend Security Charges $ $ $ $ $ $ $ $ $ $ $ $ 108 (62) 99 50 132 7 12 33 77 30 152 11 Total SLAC $ 650 Grand Total $ 986 10/15/04 thru end-of-project Labor & Travel Only Add 4 months @ $33K/month Add 1 man-month Currently Budgeted @ 1/2 time 5