GLAST Calorimeter



CAL Status
LAT F2F Meeting
17 Mar 2005
Crystal Detector Element (CDE) Manufacturing - Complete
PreElectronic Modules (PEMs) - Complete
Analog Front End Electronics (AFEE) - Complete
 All flight boards complete, burned in and conformal coated.
 4 spares and 4 more for T&DF support are finishing burn in.

CAL Modules
 15 modules have been completely assembled.
– 101 - 107 have been delivered
– 108 – 110 are in TVAC chamber, pump down on Friday.
 PEMs 116 & 117 are in AFEE card installation

All required EM2 TEM/TPS for 18 CAL modules are at NRL
W Neil Johnson
2
Naval Research Lab
Washington DC
109
110
111
112
113
114
115
116
117
118
W Neil Johnson

]
]
]
]
]
]
]



]
]
]
]
]
]
]
]
]
]
]
]
]
]
]
]
]
]
]
]
]
Post Ship
Test
]
]
]
]
]
]
]
Ship
Data
Review
]
]
]
]
]
]
]
]
]
]
]
]
]
Final CPT
Calibration
]
]
]
]
]
]
]
]
]
]
]
]
Mass
Properties
]
]
]
]
]
]
]
]
]
]
]
]
]
]
TVAC
]
]
]
]
]
]
]
]
]
]
]
]
]
]
]
TEM/TPS
]
]
]
]
]
]
]
]
]
]
]
]
]
]
]
Vibration
108
]
]
]
]
]
]
]
]
]
]
]
]
]
]
]
EMI/EMC
107
Conformal
Coat
106
]
]
]
]
]
]
]
]
]
]
]
]
]
]
]
TEM/TPS
Installation
105
]
]
]
]
]
]
]
]
]
]
]
]
]
]
]
]
]
]
Safe-to-Mate
104
AFEE
Installation
103
PEM
Assembly
Module S/N
102
Initial CPT
Assembly and Test
GLAST Calorimeter
101
LAT F2F Meeting
17 Mar 2005
Completion

] ]
]
] ]
]
]
]
]
Started
This month
Previously

3
Naval Research Lab
Washington DC
GLAST Calorimeter

Issues
LAT F2F Meeting
17 Mar 2005
Use of QUAL flight TEM/TPS for FM116 or FM117 environmental
testing at NRL.
 Need next week for safe to mate for FM116 or week later for FM117

Restarting TVAC at NRL on 3/21 but without checkout of “Big
Blue” Thermal Control System
 Not needed for CAL testing – individual cold plates for each CAL and
TEM/TPS.
 “Big Blue” TCS will be checked out between CAL tests.
 Next CAL TVAC will be FM111 – FM114

Need to re-install (rent) humidity control system (dehumidification)
for work in May and June
 Approx $25K cost expected to be covered within existing budget.
W Neil Johnson
4
Naval Research Lab
Washington DC
GLAST Calorimeter
W Neil Johnson
LAT F2F Meeting
17 Mar 2005
CAL Module Deliveries
December ’04
FM 101
January ’05
FM 102 – 105
February ’05
FM 106 – 107
March ’05
---
April ’05
FM 108 – 110
May ’05
FM 111 – 114
June ’05
FM 115 – 118
5



Naval Research Lab
Washington DC