Transcript PPT
GLAST Monthly Mission Review August 6, 2007 GLAST LAT Instrument Monthly Mission Review Gamma-ray Large Area Space Telescope Project Status Overview August 6, 2007 Ken Fouts SLAC [email protected] K. Fouts, SLAC 1 GLAST LAT Instrument K. Fouts, SLAC LAT Project Status GLAST Monthly Mission Review August 6, 2007 7/14 LAT FSW 1-0-1 installation & regression test complete 7/16 LAT Radiators Removed 7/17 LAT Radiator velcro and ACD blanket cleaning complete 7/23 Completed LAT A-side CPT 7/28 Completed LAT B-side CPT 2 GLAST LAT Instrument LAT Planned Milestones Activity LAT Radiator Flight Install & test LAT MLI Closeout for TVAC K. Fouts, SLAC GLAST Monthly Mission Review August 6, 2007 ECD 8/9? Pre-TVAC 3 I&T/Online Progress GLAST LAT Instrument GLAST Monthly Mission Review August 6, 2007 FSW B1-0-1 fall-out script and configuration issues Configuration files updated for compatibility with FSW B1-0-1 ACD cable 14 issue resolved (red herring) GRB handling scripts updated Various JIRAed bug fixes K. Fouts, SLAC 4 GLAST LAT Instrument Online JIRA issues (as of 7/30) GLAST Monthly Mission Review August 6, 2007 Issues opened since 7/10 Issues closed since 7/10 Total # of issues currently open LICOS 4 5 6 LICOS_Config 11 14 4 LICOS_ETC 3 6 15 LICOS_Scripts 12 13 16 INT 8 5 19 LDF 0 0 1 LSF 0 0 0 E-Logbook 0 0 20 38 43 81 Package Totals K. Fouts, SLAC 5 GLAST LAT Instrument LAT Issues and Concerns GLAST Monthly Mission Review August 6, 2007 Command & Data Dropouts 2 Command dropouts during CPT LAT Watt-rod Cage Rework Cages have been re-assembled Shipping container mods underway Additional shielding to be received 8/15 Return to GD by end of August Timely delivery of configuration definitions prior to TVAC K. Fouts, SLAC 6 GLAST Monthly Mission Review August 6, 2007 GLAST LAT Instrument Gamma-ray Large Area Space Telescope Cost Reports for 4.1 LAT June 2007 Month End K. Fouts, SLAC 7 Cost Status by Organization GLAST Monthly Mission Review August 6, 2007 GLAST LAT Instrument June 07 Month-End By Institution K$ Current Period Cumulative to Date Budgt'd Actual Budgt'd Actual Cost Cost Cost Cost Work Work Cost Work Work Cost Scheduled Performed Variance Scheduled Performed Variance Budgeted at Completion DG *** GSFC 57 33 24 21,254 20,669 586 21,489 DH *** HEPL 110 95 15 11,291 10,779 512 11,797 DL *** SLAC 545 633 -88 107,261 106,449 811 109,489 DN *** NRL 178 207 -29 34,735 34,750 -15 35,456 0 0 0 59 59 0 59 52 38 14 3,734 3,441 292 3,937 0 0 0 15 15 0 15 DU *** UCSC 29 29 1 2,913 2,857 55 3,034 DW *** UW 10 12 -1 491 386 105 538 982 1,047 -65 181,754 179,407 2,347 185,813 DO *** Financial Plan Transfer/Sub Out DS *** SSU DT *** Texas A&M Sub Total Contingency Total K. Fouts, SLAC 2,242 982 1,047 -65 181,754 179,407 2,347 188,055 8 GLAST LAT Instrument Cost by Orgs with Variances ≥$100K June 07 Month-End By Institution & WBS Level 3 K$ DG *** GSFC 4.1.1 INSTRUMENT MANAGEMENT 4.1.6 ANTICOINCIDENCE DETECTOR 4.1.D SCIENCE ANALYSIS SOFTWARE 4.1.E SUBORBITAL FLIGHT TEST OBSTotals: DH *** HEPL 4.1.1 INSTRUMENT MANAGEMENT 4.1.2 SYSTEM ENGINEERING 4.1.4 TRACKER 4.1.7 ELECTRONICS 4.1.A PERFORM & SAFETY ASSURANCE 4.1.B INSTRUMENT SCIENCE OPS CENTER 4.1.D SCIENCE ANALYSIS SOFTWARE 4.1.E SUBORBITAL FLIGHT TEST OBSTotals: DL *** SLAC 4.1.1 INSTRUMENT MANAGEMENT 4.1.2 SYSTEM ENGINEERING 4.1.4 TRACKER 4.1.5 CALORIMETER 4.1.6 ANTICOINCIDENCE DETECTOR 4.1.7 ELECTRONICS 4.1.8 MECHANICAL SYSTEMS 4.1.9 INTEGRATION & TEST 4.1.A PERFORM & SAFETY ASSURANCE 4.1.B INSTRUMENT SCIENCE OPS CENTER 4.1.C EDUCATION & PUBLIC OUTREACH OBSTotals: DS *** SSU 4.1.C EDUCATION & PUBLIC OUTREACH OBSTotals: DW *** UW 4.1.D SCIENCE ANALYSIS SOFTWARE OBSTotals: K. Fouts, SLAC GLAST Monthly Mission Review August 6, 2007 Current Period Cumulative to Date Budgt'd Actual Budgt'd Actual Cost Cost Cost Cost Work Work Cost Work Work Cost Scheduled Performed Variance Scheduled Performed Variance Budgeted at Completion 30 0 27 0 57 18 0 16 0 33 12 0 12 0 24 2,016 17,479 1,381 378 21,254 1,629 17,482 1,180 378 20,669 387 -3 201 0 586 2,139 17,479 1,493 378 21,489 78 0 0 0 0 0 32 0 110 76 0 0 0 0 0 20 0 95 2 0 0 0 0 0 12 0 15 3,670 2,681 1,475 1,021 263 258 1,463 460 11,291 3,476 2,638 1,475 1,019 248 257 1,206 461 10,779 194 43 0 2 16 0 257 0 512 4,051 2,681 1,475 1,021 263 258 1,588 460 11,797 42 144 0 0 0 68 0 250 42 0 0 545 20 326 0 0 0 49 0 236 3 0 0 633 22 -182 0 0 0 19 0 14 39 0 0 -88 14,383 8,906 18,144 721 685 28,324 17,441 13,595 4,998 59 5 107,261 14,325 8,877 18,097 718 683 28,372 17,417 12,853 5,049 59 0 106,449 58 29 47 2 3 -48 25 742 -51 0 5 811 14,495 9,643 18,144 721 685 28,605 17,441 14,566 5,124 59 5 109,489 52 52 38 38 14 14 3,734 3,734 3,441 3,441 292 292 3,937 3,937 10 10 12 12 -1 -1 491 491 386 386 105 105 538 538 9 FTE Report GLAST LAT Instrument GLAST Monthly Mission Review August 6, 2007 LAT PROJECT FTEs 120.0 110.0 ACTUALS PLANNED 100.0 90.0 80.0 70.0 60.0 50.0 40.0 30.0 20.0 K. Fouts, SLAC OCT07 SEP07 AUG07 JUL07 JUN07 MAY07 APR07 MAR07 FEB07 JAN07 DEC06 NOV06 0.0 OCT06 10.0 10