1. Introduction Science Overview
Download
Report
Transcript 1. Introduction Science Overview
GLAST LAT Project
Gamma-ray Large
Area Space
Telescope
CDR/CD-3 Review May 12-16, 2003
GLAST Large Area Telescope:
Introduction & Science Overview
Peter F. Michelson
Stanford University
LAT Principal Investigator &
Spokesperson
[email protected]
(650) 723-3004
Document: LAT-PR-01967
Section 1 Introduction & Science Overview
1
GLAST LAT Project
CDR/CD-3 Review May 12-16, 2003
Introduction and Science Overview
Outline
GLAST Mission and Science Overview
Large Area Telescope
instrument overview
transition from design to flight hardware fabrication
status: schedule, cost, international commitments
challenges
Document: LAT-PR-01967
Section 1 Introduction & Science Overview
2
GLAST LAT Project
CDR/CD-3 Review May 12-16, 2003
Through most of history, the cosmos has
been viewed as eternally tranquil
Document: LAT-PR-01967
Section 1 Introduction & Science Overview
3
GLAST LAT Project
CDR/CD-3 Review May 12-16, 2003
`
During the 20th century the quest to broaden our view of
the universe has shown us the vastness of the Universe
and revealed violent cosmic phenomena and mysteries
Document: LAT-PR-01967
Section 1 Introduction & Science Overview
4
GLAST LAT Project
CDR/CD-3 Review May 12-16, 2003
GLAST is an important part of the continuing quest
to broaden our view of the universe.
observe, with unprecedented detail, cosmic
arenas of extreme violence
explore Nature’s highest energy processes
(10 keV – 300 GeV)
- LAT: ~20 MeV - >300 GeV
- GBM: correlative transient
observations ~10 keV – 20 MeV
Document: LAT-PR-01967
Section 1 Introduction & Science Overview
5
GLAST LAT Project
CDR/CD-3 Review May 12-16, 2003
EGRET all-sky survey
(70 MeV – 10 GeV)
Document: LAT-PR-01967
Section 1 Introduction & Science Overview
6
GLAST LAT Project
CDR/CD-3 Review May 12-16, 2003
3rd EGRET Catalog
AGN - blazars
pulsars
unidentified
Document: LAT-PR-01967
LMC
Section 1 Introduction & Science Overview
7
GLAST LAT Project
CDR/CD-3 Review May 12-16, 2003
rd EGRET Catalog
3
Survey: ~10,000 sources
GLAST
(2days)
years)
GLAST Survey: ~300 sources (2
Document: LAT-PR-01967
Section 1 Introduction & Science Overview
8
GLAST LAT Project
CDR/CD-3 Review May 12-16, 2003
GLAST Observatory
Gamma Ray Burst Monitor (GBM)
Spacecraft
Launch Vehicle
Launch Location
Orbit Altitude
Orbit Inclination
Orbit Period
Orientation
Launch Date
Document: LAT-PR-01967
Large Area Telescope (LAT)
Person
Delta II – 2920-10H
Kennedy Space Center
575 Km
28.5 degrees
95 Minutes
+X to the Sun
September 2006
Section 1 Introduction & Science Overview
9
GLAST LAT Project
Si Tracker
CDR/CD-3 Review May 12-16, 2003
GLAST Observatory
pitch = 228 mm
8.8 105 channels
Gamma
Ray Burst
Monitor
(GBM)
18 planes
(16 with
converters)
Spacecraft
g
ACD
segmented
scintillator
tiles
Large Area Telescope
(LAT)
Person
Grid
Launch Vehicle
Delta II – 2920-10H
mechanical
+
e
e
CsI Calorimeter
Launch Location
Kennedy Space Center
backbone
hodoscopic
array
(8 layers)
Orbit
Altitude
575 Km
3
6.1 10 channels
Orbit Inclination
28.5 degrees
Orbit Period
95 Minutes
LAT: 4 x 4 modular array
Orientation
+X to the3000
Sunkg, 650 W
Data Acquisition
20 MeV
Launch Date
September
2006– 300 GeV
Document: LAT-PR-01967
Section 1 Introduction & Science Overview
10
GLAST LAT Project
CDR/CD-3 Review May 12-16, 2003
GLAST
g
Single Photon Angular
Resolution
3.5o @ 100 MeV
0.15o @ 10 GeV
Wide Energy Range: 20 MeV - >300 GeV
GLAST measures the direction, energy &
Field of View
arrival time of celestial gamma rays Wide
(> 2 sr)
40 times
EGRET’s
- LAT
measures gamma-rays in the energy range
sensitivity
~20and
MeV - >300 GeV
extends
- GBM provides correlative observations of
energy
transient events in the energy range ~20 keV – 20
MeVrange to
300 GeV
Point Source
Sensitivity:
< 6 x 10-9 ph cm-2s-1
e+
e-
Low dead time:
< 100 ms/event
Large Effective Area
(Aeff)peak > 8,000 cm2
(est. performance:
< 3 x 10-9 ph cm-2s-1)
Source
Localization:
0.3’ – 1’
Document: LAT-PR-01967
Good Energy Resolution
DE/E ~ 10%; 100 MeV – 10 GeV
~ < 20%; 10 GeV – 300 GeV
Section 1 Introduction & Science Overview
11
GLAST LAT Project
CDR/CD-3 Review May 12-16, 2003
Transition from design to flight hardware fabrication
•
Engineering Models constructed for each hardware subsystem – under
test and evaluation
•
have carried out subsystem Peer Design Reviews of each subsystem;
Jan - March 2003
•
Production readiness reviews
•
long-lead parts ordered and long-lead fabrication initiated
•
finalizing flight instrument design details: comprehensive review at LAT
Critical Design Review (CDR) – CD-3; May 12-16, 2003
Document: LAT-PR-01967
Section 1 Introduction & Science Overview
12
GLAST LAT Project
CDR/CD-3 Review May 12-16, 2003
LAT Schedule highlights
Calendar Years
2000
2001
2002
PDR
Balloon
Flight
2003
Critical
Design
Review
2004
TKR & CAL
FM A/B
2005
2006
2011
Schedule
Float
Scheduled
Scheduled
Completion
LAT Delivery
Begin
LAT I&T
Launch
Ops.
Prelim. & Sys. Design
Final Design
Engr’g Models
Build & Test
Flight Units
FABRICATION PHASE
LAT I&T
Observatory
I&T
COMMISSIONING
PHASE
GLAST scheduled for launch in September 2006
Document: LAT-PR-01967
Section 1 Introduction & Science Overview
13
GLAST LAT Project
CDR/CD-3 Review May 12-16, 2003
Summary Schedule
COMMISSIONING
PHASE
FABRICATION PHASE
15
• recently
moved beam test to after completion
Electronics
Fab & Test
of instrument
I&T
Tracker
Fab & Test LAT completion date
• preserves
Calorimeter
Fab & Test
12
• adds schedule float between subsystem
ACD Fab & Test
deliveries and I&T need dates
LAT Complete 5/25/05
GRID Fab & Test
14 wks Schedule Float
9
{
Begin assembly 6/15/04
6
Ship Instrument
Observatory I&T
Launch
3
LAT Operations & Data Analysis
}
Instrument I&T
Beam Test
3 wks
Schedule Float
9/22/05
9/06
0
FY02
Document: LAT-PR-01967
FY03
FY04
FY05
FY06
Section 1 Introduction & Science Overview
FY07
14
GLAST LAT Project
CDR/CD-3 Review May 12-16, 2003
Budgeted Fabrication Cost
Budgeted DOE + NASA Costs for Fabrication Phase
(escalated $M)
Budgeted Cost at Completion
Contingency
Total Estimated Cost (TPC=TEC)
Budgeted costs at risk
Contingency fraction
Document: LAT-PR-01967
Baseline
3/31/03
100.0
21.2
121.2
107.5
14.2
121.7
Baseline
3/31/03
72.7
29%
59.4
24%
Section 1 Introduction & Science Overview
15
GLAST LAT Project
CDR/CD-3 Review May 12-16, 2003
LAT Hardware: International Contributions
g
Si Tracker
ACD
Grid (& Thermal
Radiators)
CsI Calorimeter
e+
e–
Electronics, Data Acquisition
& Flight Software
Document: LAT-PR-01967
Section 1 Introduction & Science Overview
16
GLAST LAT Project
CDR/CD-3 Review May 12-16, 2003
Status of International Contributions
• Since baseline, international partners have delivered on commitments
–
–
–
–
Italy: (ASI/INFN) tracker
Japan: tracker (Si-strip detectors)
Sweden: calorimeter (CsI xtals)
France: calorimeter (CDEs, mechanical structure)
• On Thursday, April 24, CNES (the French Space Agency) announced
their withdrawal from planned commitments to the French
contributions to GLAST
– impacting critical procurements by our partners at CEA and IN2P3
– we are working with CEA, IN2P3, and NASA and DOE, to understand the
available options for maximizing the continued French contributions
– in the short term (next few weeks), our French partners at CEA and IN2P3
will continue working; we are beginning implementation of backup plans
for production in the U.S. of calorimeter flight components (.e.g. CDEs).
– by the end of May, a revised plan will be presented to the collaboration
sponsors
Document: LAT-PR-01967
Section 1 Introduction & Science Overview
17
GLAST LAT Project
CDR/CD-3 Review May 12-16, 2003
status summary and highlights of next year
• International Finance Committee formed to regularly review
funding agency commitments – 1st meeting, February 18-19, 2003
• the transition from design to flight fabrication is currently
underway
• first flight hardware deliveries to SLAC scheduled for FebruaryMarch, 2004
– first 4 calorimeter and tracker flight modules will arrive at SLAC
– LAT Grid delivered June 2004 – LAT integration begins
• collaboration meeting planned for Sept 15-19, 2003 in Rome, Italy
– meeting will concentrate on collaboration plan for operations phase:
instrument operations, science data analysis, etc.
Document: LAT-PR-01967
Section 1 Introduction & Science Overview
18
GLAST LAT Project
CDR/CD-3 Review May 12-16, 2003
Challenges
• loss of CNES support for French contributions
– schedule impacts being mitigated now by application of
contingency;
– by end of May, will have revised CAL manufacture plan for
presentation to DOE/NASA JOG, including CEA and IN2P3
contributions that can be confirmed
• very demanding schedule
– subsystem development delays compensated by rescheduling
beam test
• identification and closure of remaining design issues
– issues identified (e.g. peer reviews, etc.); plans exist to close open
issues
Document: LAT-PR-01967
Section 1 Introduction & Science Overview
19
GLAST LAT Project
CDR/CD-3 Review May 12-16, 2003
GLAST:
`
Exploring
Nature’s
Highest Energy
Processes
September 2006
launch
Document: LAT-PR-01967
Section 1 Introduction & Science Overview
20