MRB on SLAC NCR 226
Excess of Disconnected MCM Channels
R.P. Johnson
November 9, 2004
1. Description of Non-Conformance
• MCM part number LAT-DS-00898, SN 11378 was found to have 151
channels disconnected between the amplifiers and the pitch
adapter.
• This MCM had zero non-conductive cracked traces (from the visual
inspection) and zero dead amplifiers.
• This problem was found Friday, November 5, at SLAC while testing
42 MCMs using the new electronic pitch-adapter test fixture.
• Earlier the same week 1 MCM already attached to a tray and SSDs
at G&A was found to have about 300 disconnected channels.
• Also, at G&A and Pisa 2 trays were found to have a disconnection of
1 or more bias lines, which may be from the same root cause.
November 9, 2004
MRB, SLAC NCR 226
2
Inspections and Tests
• A new fixture designed at SLAC solves our old problem of not being
able to test the connections to the amplifier inputs until SSDs are
attached. This became a critical problem when the MCM mounting
changed from screws to gluing.
• Initially our assurance was based on
– Wire bond quality control at Teledyne
– Visual inspection of all wire bonds and bond feet at MIP-2 at Teledyne
– Sample testing of several preproduction MCMs by probing each pitchadapter trace.
• After an MCM on Tower-0 was found with 25 cracked traces, we did
the following:
– Visual inspection for cracks in pitch-adapter (and manual probing with a
DVM for continuity) traces before shipment to Italy. This appears to be
quite effective, albeit with a rejection rate of 14%, requiring no more
than 8 such cracked, nonconductive traces.
– Tested with 200 thermal cycles whether the incidence of non-conductive
cracks gets worse (it does not).
– Stepped up existing efforts to get an electrical test method developed.
November 9, 2004
MRB, SLAC NCR 226
3
The Electrical Test Method
• Use a conductive, flexible strip (zebra strip) to short circuit 100% of
the pitch-adapter traces to ground.
– Bias HV is turned off, to protect it.
– AVDDA must be turned on, but the resistance of the zebra strip is high
enough that it does not draw enough current to cause any problem.
• Run a charge-injection scan and measure the response of each
channel.
– Channels with inputs shorted to ground will look dead.
– Channels not connected to the pitch adapter will look alive, unless the
amplifier is already dead for some other reason.
• So, if a channel measures good in the normal electrical test, with the
input floating, AND it measures dead with the zebra strip applied,
then we are certain that it is a good, connected channel.
• If a channel measures good with the zebra strip applied, then either
– it is disconnected from the pitch adapter, or
– the zebra strip did not make contact with the pitch adapter (false
negative).
November 9, 2004
MRB, SLAC NCR 226
4
Pitch-Adapter Electrical Test Fixture
STORAGE CASE BASE
Designed by Peter
Amnuaypayoat
ZEBRA CONNECTOR
SOFTWARE/
ELECTRICAL FIXTURE
MCM WITH
PITCH ADAPTER
TEST FIXTURE
CONNECTOR SAVER
GROUND LEAD
November 9, 2004
MRB, SLAC NCR 226
5
Disconnected Ch. vs. Cracked Traces
10
9
8
Cracked (visual)
7
6
5
4
3
2
1
0
0
2
4
6
8
10
Disconnected (electrical)
Visual inspection and test data from 41 MCMs. Note that the number of
disconnected channels is probably a little bit overestimated, due to
occasional false negatives given by the test fixture. (False positives are
not possible, unless the connection is intermittent.)
November 9, 2004
MRB, SLAC NCR 226
6
Disconnected Ch. vs. Cracked Traces
20
35
18
30
14
Number of MCMs
Number of MCMs
16
12
10
8
6
25
20
15
10
4
5
2
0
0
0
5
10
15
20
0
Disconnected Channels
5
10
15
20
25
Cracked Traces
Visual inspection and test data from 41 MCMs.
The 42nd MCM had 151 disconnected and 0 cracked traces.
November 9, 2004
MRB, SLAC NCR 226
7
Bias Disconnects
• The pitch-adapter electrical test fixture will not detect problems with
the bias traces.
• Our visual inspection rejected MCMs with even 1 cracked
nonconductive bias trace, but this does not catch all problems.
• Up to now we relied on
– 100% electrical test of the PWB.
– Visual inspection of the bias resistor.
– Wire-bond QC and visual inspection at MIP-2 at Teledyne.
• Still, there are 2 cases of MCMs in Italy with bad (sometimes
intermittent) bias connections.
• Therefore, we are now doing the following procedure on all MCMs
before shipping to Italy:
– Turn the bias voltage down to 2.5 V, and turn on the MCM power.
– Using a voltmeter, probe each of the 16 bias traces past the bend
region, and verify that the appropriate voltage (2.5 V or 1.5 V) is seen.
November 9, 2004
MRB, SLAC NCR 226
8
2. Overstress Analysis & Additional Testing
• We tried out the test fixture on the 4 nonflight MCMs that we recently
passed through 200 thermal cycles from 30C to +85C.
– 3 were not bad, with the worse case being 15 disconnected channels.
– 4th had 60 to 80 disconnected traces, depending on the test trial. The
results were variable, and we found clear cases of false positives. The
pressure from the fixture was causing reconnections of some of the
failed traces.
• This experiment would be more interesting if we had a measurement
before the thermal cycles as well as after.
• A more relevant test will be to check the connections at MIP-3 (i.e. at
Teledyne) and then again after thermal cycles and burn-in at SLAC.
November 9, 2004
MRB, SLAC NCR 226
9
3. Suspected Root Cause
• We suspect failure of the wire bonds where they connect to the pitch
adapter. They are not visible (black encapsulant), but we have
indirect evidence:
– Cracked traces in the visible region of the pitch adapters are eliminated
by our thorough visual scans.
– Our visual inspection at MIP-2 ensures that the wire bonds were there
and were initially connected (we couldn’t fail to see 151 disconnected or
missing bonds!).
– The MIP-2 visual inspection also rules out that any significant number of
the disconnected channels could be due to pitch-adapter cracks close to
the cut edge.
– The very low failure rate of wire bonds on the power and digital I/O
GTFE connections nearly rules out wire-bond failure on the ASIC side of
the bond.
– The pitch-adapter substrate is the more difficult material to wire bond to.
• So, we believe that either the bonds failed during encapsulation or
later during thermal cycling. The intermittent ones must have failed
after encapsulation in order to have the foot still so close to the
pitch-adapter trace.
November 9, 2004
MRB, SLAC NCR 226
10
Impacts to Inventory
• The 1-in-42 (2.4%) occurrence of large numbers of disconnected
bonds is not a big problem for MCM availability.
• The 14% loss due to >8 cracked traces is a big problem. At that rate
we have to review again whether we will have enough parts to
complete the build, given that this is not the only source of loss of
MCMs (e.g. Tower-0). I suggest that we consider raising the
maximum number of bad channels from 8 to 15. This is the limit
used at the tray level and corresponds to a worst-case inefficiency of
1%.
November 9, 2004
MRB, SLAC NCR 226
11
5. Corrective Action
• Test all MCMs with the PA test fixture both at MIP-3 and before
shipping to Italy. We need to manufacture one more fixture.
• Review and possibly improve the Teledyne wire-bonding controls.
The present procedure calls for the following:
– Plasma clean in Tepla (Recipe #1) prior to wire bonding.
– At the start of each shift, wire bond the test pattern on a single die on
the wire bond set up PCB. Perform 100% destructive pull test. During
actual wire bonding, perform Non destructive Pull Testing (NDPT) on
every 3rd unit. NDPT test on 2 die, 30 wires on a single PCB only.
• Update and re-release the burn-in and test procedure LAT-TD02367.
• Verification plan:
– Test our remaining MCMs with the PA fixture asap.
– Consider doing extra thermal cycles on some non-flight MCMs, with
tests before and after.
November 9, 2004
MRB, SLAC NCR 226
12
6. Effectiveness of Corrective Action
• The PA test fixture is almost guaranteed to find the missing
connections, the only exception being cases where the pressure
from the fixture results in a temporary reconnection. This will not
happen on all or even most of any large number of missing
connections on a given MCM.
• There is some concern that the tray-level thermal cycles could
produce more disconnections.
– The burn-in procedure thermal cycles are more severe in terms of
number of cycles (20 vs. 4) and range (30C to +85C vs. 30C to
+55C).
– This would be the reason to try some more extensive thermal cycle
testing on non-flight MCMs.
November 9, 2004
MRB, SLAC NCR 226
13
7. Recommended Disposition
• Scrap (use for EGSE) the MCM that is the subject of NCR 226.
• Return all MCMs to SLAC that have not been tested with the PA
fixture and bias-circuit hand probing.
• Begin mounting to trays those MCMs that passed the PA and bias
probing tests.
November 9, 2004
MRB, SLAC NCR 226