Potential Transmission Construction Scheduling In Southern
Minnesota--- Fall 2004- Spring 2006
• Xcel Energy has posted Significant Transmission
construction during this time frame associated with its
Wind Development in Southern Minnesota
• There are a number of Large Generators in the counties
generally south of the Twin Cities identified as still active
in the MISO queue with requested in service dates within
or near this same time frame
Transmission Construction Scheduling In Southern
Minnesota Fall 2004- Spring 2006
• Of these generators, the following have completed the
facility study phase.
– #37305-01 300 MW Rice Co
– #37540-02 667 MW Blue Earth Co
– #37911-01 385 MW Scott Co
• Using the interconnection and facility study results of just
these generators, the following map shows the location of
the transmission construction projects of the wind 825 Mw
projects and these generator interconnections should they
continue.
Southern Minnesota Potential Transmission
Work
Fall 2004-Spring 2006
Transmission work
Fall 04- Spring 2006
To Fergus Falls
Require outages during
construction
Little Falls
Grant Co.
To Riverton
Douglas Co.
Morris
Benton Co.
To Granite Falls
Rush City
St Cloud
Glenwood
Panther
Note: we expect some
additional work to come from
delivery studies based on
interconnection study results
Chisago Co.
Sherco
Monticello
Benson
Willmar
A.S. King
Parkers Lake
To Morris
Blue Lake
Granite Falls /
Minnesota Valley
Buffalo Ridge
to Eau Claire
Red Rock
Prairie
Island
Franklin
Marshall
Lake Yankton
Wilmarth
W.Faribault
Winona
Pipestone
Byron
Chanarambie
West Owatonna
To Rochester
Lakefield Jct.
Split Rock
To Raun
J:/DSPPLAN/schd67/outminn.ppt
Adams
To Hazleton
To Austin
#37305-01 300 MW Rice Co.
• Based on the Facility study for this interconnection, this
generation plant is located just north of Faribault MN and
will require the following major transmission work:
–
–
–
–
Replace W. Faribault 115-69 kV Transformers
Rebuild Fair Park- Northfield 69 kV line
New Faribault Energy Park 115 kV substation
Rebuild Lake Marion-W. Faribault 115 kV line
• Construction duration: 23 Months
• Interconnection study strongly suggests additional
transmission will be needed by this project for delivery.
#37540-02 667 MW Blue Earth
Co.
• Based on the Facility study for this interconnection, this
generation plant is located Xcel Energy’s Wilmarth
Substation and will require the following major
transmission work:
– Major rebuild 69, 115 and 345 kV substation
– Requires completion of Eastwood 115 kV conversion project.
• Construction duration: 21 Months
• Interconnection study strongly suggests additional
transmission will be needed by this project for delivery.
#37540-02 667 MW Scott Co.
• Based on the Facility study for this interconnection, this
generation plant is located Xcel Energy’s Blue Lake
Substation and will require the following major
transmission work:
– Major Blue Lake 115 kV substation expansion
– Move Black Dog 230-115 kV transformer to Blue Lake
– >1 mile 230 kV double circuit
– Re-conductor Blue Lake-Black Dog Line
• Construction Duration:
– First learned about in October 2003
– Will just make May 2005 in-service
• Generator entered Facilities Construction Agreement to allow pre- IA
Engineering and procurement.
Additional Large Generator Interconnection requests in
MISO’s queue
•
•
•
•
•
#37551-02 105 MW Martin Co
#37804-01 200 MW Dakota Co
#37830-01 180 MW Carver Co
#37967-01 100 MW Martin Co
#38034-01 350 MW Goodhue Co
2004
2007
2005
2006
2006