ECR MarathonBattery

Download Report

Transcript ECR MarathonBattery

Marathon Site

Marathon Battery Cold Spring, NY CERCLA Cleanup

Project Goals

Project Description

Resources

Procedures

Competitive Analysis

Schedules & Status

4/26/2020 Technology

Related Documents W. Fish, Portland State University

Site Description

   On the Hudson River in NY; Two components: East Foundry Cove Marsh (EFCM) Constitution Marsh 4/26/2020  W. Fish, Portland State University Click for Details

Site Map

4/26/2020

East Foundry Cove Marsh

4/26/2020

History: US Army

   1952: U.S. Army Corps of Engineers Constructed 1953, under Contract with the Army Signal Corps, Sonotone Corporation operated plant to produce nickel-cadmium batteries for use in the Nike missile program Run under Army ownership 1953-1962; declared “ excess proprty in 1962.

 W. Fish, Portland State University Click for Data Sheet 4/26/2020

Private Owners

  1962: U.S. sold it to Sonotone Corporation. 1967: Sonotone Corporation became a wholly-owned subsidiary of Clevite Corporation 4/26/2020 W. Fish, Portland State University

Marathon

   1969, Clevite Corporation Merged with Gould, Inc.

1969, Gould, Inc. sold the Plant to Business Fund, Inc.; later changed its name to Marathon Battery Company (MBC) MBC operated the plant until March 1979.

4/26/2020 W. Fish, Portland State University

After the Battery Era

   Plant inactive from 3/79 until 11/80 Battery manufacturing equipment removed and shipped to an MBC plant in Waco, Texas Sold to the current owner, Merchandise Dynamics, incorporated, for use as a book storage facility  W. Fish, Portland State University Click for Details 4/26/2020

Contaminants of Concern

     Cadmium: Cd Toxic to humans, animals and plants Carcinogenic Waste stream had huge amounts of Cd, mostly as Cd hydroxide (10 ’ s-100 ’ s mg/L) Also caustic wastes (pH 12-14) 4/26/2020 W. Fish, Portland State University

   

Original Wastewater Treatment System

A lift station and piping for transfer of all process wastewater into the Cold Spring sewer (100,000-200,000 gal/day) Discharged directly into the Hudson River Bypass Valve Was Installed When the Lift Station Was Shut down or Overloaded, direct Gravity Discharge Could Be Made into a Storm Sewer 4/26/2020  W. Fish, Portland State University Click for Detailed Schedule

Discharges to EFCM

   High dissolved solids and pH 12-14 of the effluent resulted in extreme fouling within the pump and piping Pumps required shut down and maintenance Bypass valve was opened and the flow diverted to EFCM about twice a week 4/26/2020 W. Fish, Portland State University

Cadmium Load:

 

Approximately plant 50,000 kg (over 52 tons) of cadmium may have been discharged to the cove during the life of the About did not half the metal purchased make in into batteries

4/26/2020

New Sewage Plant

     1965: New York State Department of Health said Cold Spring must build sewage treatment plant Battery Plant effluent could not be handled: too toxic Sonotone ordered to disconnect from sewer Entire waste flow diverted to storm sewer USACE (1966) told company to quit discharging to the Hudson 4/26/2020

Attempts at Treatment

     January 1967: NY Dept of Health advised Sonotone it was in violation Plant given Jan 1, 1970 deadline to comply with state discharge regulation Sonotone installed treatment equipment Never really worked, Cd kept on flowing NY found lots of Cd in marsh, river 4/26/2020

70 Civ. 4110

   Judgement of Federal Court Suit brought under Federal Water Pollution Control Administration against Marathon (pre-EPA) Enforcement then shifted to new EPA 4/26/2020

Relief Sought by U.S.

   Permanent injunction against further discharge of Cd and other metals into Foundry Cove Demanded removal of Cd in sediments Sept. 1971: Complaint amended, named Sonotone, Cleveite and Gould as additional defendants 4/26/2020

Final Judgment (70 Civ.4110)

    June 1972: Remove all sediment with Cd >900 ppm (mg/kg) 1971: Discharge was stopped; routed back to sewer after treatment 1972-1973: Hydraulic dredging by GOULD Design: Dr. Harry Gregor, Columbia U.

4/26/2020

1st Dredging Operation

    Hydraulic dredging of “ hot ” areas Dr. Gregor instructed crew to remove all soft sediment from outfall area (~2-4 ft deep) Gravel base fairly clean In Cove, Gregor delineated with stakes 22 acres with Cd > 1000 ppm 4/26/2020

On-Site Soil Handling

    Spoils dewatered in parking lot inside a temporary dike dewatering leaked all over the place Effluent settle overnight, discharge to marsh Solids mixed with limestone, scored in underground vault on site 4/26/2020

Areas Dredged

    Outfall area Channel leading to the marsh Cove:Winter ’ 72 ice uprooted stakes and Gregor had to redelineate and finish in spring 1973 About 4000 cu.m. stored in vault 4/26/2020

Satisfaction

”     April 24, 1974: US Attorney issues “ satisfaction of judgment ” Site is off the hook … or isi it?

Agreement included monitoring by NYS Dept. of Environmental Conservation (NYSDEC) Studies by NYSDEC, EPA, NYU 4/26/2020

Whoops, There it Is

    Studies showed much of area was still > 900 mg/kg Channel area was recontaminated In fact in 1973 Gregor had to have channel redredged, but he did not worry about surrounding marsh Only about 10% of Cd had been removed 4/26/2020

Dr. Theo Kneip, NYU

    1974: Found the recontamination Found the 1000 ppm zone was larger 50% than Gregor ’ s zone just one year before >50,000 ppm within the area dredged the prior year! (= 5% Cd by weight) 135,000 pmm near the outfall 4/26/2020

Cd Data of Kneip et al. 1974

4/26/2020

MBC Internal Memos:

 “ He told Jack that he was working on a Federal grant and, as a matter of courtesy wanted us to know the Cd background level of the Hudson River is higher in many cases after the dredging than before ” 4/26/2020

MBC Internal Memos

 [10 days later] “ At any rate he now reports increased Cd levels in the cove and the river due to the dredging. This does not necessarily bother or surprise us, since this was our prediction and which was basically ignored by the Final Jedgment [sic].

” 4/26/2020

CERCLA

     1980: CERCLA Passed 1981: First National Priority List (NPL) Prepared Guess what was one of the first sites proposed for the interim NPL?

1983 went on Final NPL Also OSHA found high Cd dust inside book warehouse 4/26/2020

CERCLA Units

 1986 Record of Decision (ROD): Three “ Operating Units ” (OU ’ s)    Area I: EFCM & Constitution Marsh Area II: Plant, grounds, vault Area III: Cove itself and Hudson 4/26/2020

RI/FS Findings

 ~8% of EFCM had >1000 mg/kg Cd 4/26/2020

Sediment Cd Profiles

4/26/2020

Cd Accumulation in Biota

 High levels of Cd found in a number of organisms (e.g., Limnodrilus hoffmeisterii) 4/26/2020

Cd Accumulation in Muskrats

4/26/2020

 Muskrats in Cold Spring Exhibit Odd behavior  http://www.youtube.com/watch?v=Lbh9c0noR4s 4/26/2020

ROD Plan: 1986

     Dredge Hudson near old sewer outfall Dredge Cove and EFCM, dewater, haul offsite Re-vegetate EFCM Leave Constitution Marsh alone  Monitored Natural Attenuation (MNA) 2 other RODS issued ‘ 88, ‘ 89 4/26/2020

Final Consent Decrees

   Marathon, Gould, USACE are Responsible Parties (RP ’ s) Total cost $109 million  Gould $57M   ACOE $43 M Marathon $9M Insurance paying much of Gould and MBC 4/26/2020

Dredging Began 1993

    Dredging removed 55,000 cu.yd sediment to depth of 1 ft.

Assumed to get about 95% of Cd this way Unlike 1972-73, did not shoot for a specific target concentration Dredging completed in 1994 4/26/2020

Marsh Cleanup

   1800 ’ dike, 6-7 ft high 31,000 cu.yd soil excavated, treated, shipped of site Reconstructed and revegetated the marsh 4/26/2020

Marsh Cleanup

Foundry Cove Dike Dike Drainage Treatment Stored Sludge 4/26/2020 Dewatering Pond RR Line Rail Transfer

Sediment Cd

Fixation

” 4/26/2020

Rail Line for Removal

4/26/2020

DELISTING

 Declared finished and delisted from NPL, October 1996 4/26/2020