Temperature De-rating - HPHT Materials
© 2016 Baker Hughes Incorporated. All Rights Reserved.
Bill Bailey
1
© 2016 BAKER HUGHES I NCORPORATED. ALL RI GHTS RESERVED. TERM S AND CONDI TI ONS OF USE: BY ACCEPTI NG THI S DOCUM ENT, THE RECI PI ENT AGREES THAT THE DOCUM ENT TOGETHER W I TH ALL I NFORM ATI ON I NCLUDED THEREI N I S THE
CONFI DENTI AL AND PROPRI ETARY PROPERTY OF BAKER HUGHES I NCORPORATED AND I NCLUDES VALUABLE TRADE SECRETS AND/ OR PROPRI ETARY I NF OR M ATI ON OF BAKER HUGHES (COLLECTI VELY "I NFORM ATI ON"). BAKER HUGHES RETAI NS
ALL RI GHTS UNDER COPYRI GHT LAW S AND TRADE SECRET LAW S OF THE UNI TED STATES OF AM ERI CA AND OTHER COUNTRI ES. THE RECI PI ENT FURTHE R AGREES THAT THE DOCUM ENT M AY NOT BE DI STRI BUTED, TRANSM I TTED, COPI ED OR
REPRODUCED I N W HOLE OR I N PART BY ANY M EANS, ELECTRONI C, M ECHANI CAL, OR OTHERW I SE, W I THOUT THE EXPRESS PRI OR W RI TTEN CONSENT OF BAKER HUGHES, AND M AY NOT BE USED DI RECTLY OR I NDI RECTLY I N ANY W AY DETRI M ENTAL
TO BAKER HUGHES’ I NTEREST.
Members - Temperature De-rating WI
© 2016 Baker Hughes Incorporated. All Rights Reserved.
Abhay Singh (Hamilton Metals) Hernan Rincon (ConocoPhillips)
Marco Deuterio (SQA)
Al Coffey (Sigma Tube)
Iain MacLeod (Howco Group)
Pat Markle (ATI Metals)
Al Gavenas (Energy Alloys)
Jim Burk (BP)
Rashmi Bhavsar (SLB)
Bill Bailey (Baker Hughes)
Joel Russo (FMC)
Rogerio Cotta (VillaresMetals)
Bob Hargrave (Chevron)
John Groth (VDM-Metals)
Stan Gregory (Foroni)
Chris Carlton (Chevron)
Joshua Rooker (Voestalpine)
Steve Tassen (Special Metals)
Ed Marotta (GE Oil & Gas)
Kevin Johnson (OneSubsea)
Tim Haeberle (GE Oil & Gas)
Greg Chitwood (Bohler)
Manuel Gonzalez (Shell)
Weiji Huang (Exxon Mobil)
Willie Howie (Weatherford)
2
Temperature De-rating Status Update
API CSOEM approval to initiate PO
API determined that a management company was needed
A proposal was submitted by Howco and API issued a contract
A bar was received @ Howco from Foroni/Howco
Bars were received from VDM and Villares
Howco contacted the “low cost” vendor and obtained quotes
Howco started getting the wire EDM and testing companies on their ASL
Dec.
Preliminary bar sawing, boring, turning was completed.
Jan. ASL additions completed. PO's issued and materials shipped for EDM.
© 2016 Baker Hughes Incorporated. All Rights Reserved.
Jun.
Jul.
Aug.
Sept.
Oct.
Nov.
3
Other Activities
© 2016 Baker Hughes Incorporated. All Rights Reserved.
Bill Bailey was invited to attend and provide a presentation
on this API Work Item to a NOIA/BSEE workshop in the
Washington DC area on Oct. 28th, 2015.
4
Next Steps After Testing Completed
1. Review data for significant anomalies
2. Assess statistical validity of data
3. Determine additional tests for outliers
4. Determine best form for data
© 2016 Baker Hughes Incorporated. All Rights Reserved.
5. Summary/conclusions report
6. Recommend how data/conclusions
should be distributed
5
API Funds
A. $150K was approved
B. ~$50K will remain after Alloy 718 tests
C. Determine additional tests
a) Precision Elastic Modulus
b) Measured True Stress Strain
© 2016 Baker Hughes Incorporated. All Rights Reserved.
c) Additional Alloys
d) Other Properties (e.g. Poisson’s ratio)
6
7
© 2016 Baker Hughes Incorporated. All Rights Reserved.
The End - Questions