Alabama’s Seaport
One of the Nation’s Largest In Total Trade
Alabama State Port Authority
Over $700+ Million Invested Since 2001
Record FY2012: $144+ Million in
Revenues Handling More than 25 Million
Tons of Cargo
Generates 127,591 Jobs in Alabama
(direct, indirect, and related user jobs)
Generates $506+ million in direct and
indirect tax impact in Alabama
ASPA Total Economic Value: $18.7 Billion
to Alabama
Serving Alabama Industry
Listing Represents a Sampling of ASPA Customers by Region
Northern Region of Alabama
GREAT SOUTHERN
NUCOR
SOLUTIA
WAYNE FARMS
IP
PILGRIM’S
TYSON FOODS
WEYERHAEUSER
Central Region of Alabama
ACIPCO
HONDA
MERCEDES
O’NEAL STEEL
ALABAMA POWER
KIA
WALTER ENERGY
US PIPE
Southern Region of Alabama
AKER SOLUTIONS
EVONIK
HYSCO
MITSUBISHI
SSAB
BERG / EUROPIPE
GEORGIA PACIFIC
INEOS
OUTOKUMPU AMERICAS
STANDARD FURNITURE
MARSHALL DURBIN
ROCK TENN
VULCAN MATERIALS
DRUMMOND
KRONOSPAN
NUCOR
DUPONT
HYUNDAI
MASLAND CARPETS
POSCO
THYSSENKRUPP
ASPA Five Year Capital Program
Project Cost
Pier C North Rehabilitation
Intermodal Rail (ICTF – Phase I)
Rail Bridge and Site Work
Pier D Steel Warehouse
Container Terminal Phase II
Garrows Bend Logistic Park
New Shiploader/Rail Loop Track/Yard 5
@ McDuffie Coal Terminal
Intermodal Rail (ICTF – Phase II)
Truck/Vehicle Bridge Connector
Automobile RO-RO Terminal
Middle Bay Port Pier/Yard
Interchange Rail Yard Expansion
Axis Inland Dock Expansion
Total Cost
$18M
$36M
Schedule
Ongoing
2013
$36M
$68M
$110M
$70M
2013-2014
2014-2015
2014-2016
2014-2016
$44M
2015-2017
$54M
$21M
$5M
$5M
$467M
2015-2018
2015-2018
2015-2018
2015-2018
Automobile Terminal - $54M
Theodore Ship Channel
McDuffie - $70M
Export Enhancements
Choctaw Point ICTF Phase I
Site Prep, Rail Bridge, Facility – $36M
Choctaw Point Logistics Park - $110M
New Steel Warehouse - $36M
New Steel Warehouse Underway
Complements $18
Million in Recent and
Ongoing Investments for
Iron/Steel Shippers
Serves High Growth in
Steel Products
ThyssenKrupp
SSAB
Nucor
Severstal
Outokumpu NA
Public/Private Venture
with Alabama Steel
Terminals, LLC
APM Terminals Mobile
Choctaw Point Complex
ICTF
Logistics Park
Future Ro/Ro Terminal
Greenfield Project Located
on Theodore Ship Channel
Highway / Rail Served
Phased Construction
Phase I: Ship Berth
with ~ 100 Acres
Phase II: ~ 250
Additional Acres
Market Study and
Preliminary Engineering
Underway
Alabama State Port Authority
Serving Alabama