Capital Improvement Program (CIP)

Download Report

Transcript Capital Improvement Program (CIP)

Capital Improvement
Program (CIP) Overview
Dean Fisher, P.E., PMP, CCM
July 25, 2013
OCSD Service Area
479
210
2.5
21
580
15
2
square miles
million gallons per day
million population
cities, 3 special districts
miles of sewers
pump stations
treatment plants
Los Angeles
Orange County
Service
Area
San Diego
Reclamation Plant No. 1
Fountain Valley
Treatment Plant No. 2
Huntington Beach
Background
• EPA Consent Decree
Secondary Treatment
2002 - 2012
• Full Secondary
December 2012
• Future Renewal,
Replacement and
Rehabilitation
Strong Financial Position
• Revenues from user fees and
connection fees
• Proactive forecasting
and planning
• AAA Bond Rating
More than 70 Projects
$1.8 Billion Dollars invested in our
Infrastructure
Increasing
Level of Service
•
•
•
•
•
•
•
•
100% Secondary Standards
70 mgd Reclamation
Increased System Reliability
Lower Engine Emissions
Less Odors
Disinfection
Treat Urban Runoff
Fire & Safety Code Compliance
CIP Drivers
Enhanced Planning Methodology
Capacity
Condition
Of Assets
Plant or
Collection
System
Business Efficiency
& Research Outcome
Level of
Service
or
Regulatory
Change
CIP Drivers
Enhanced Planning Methodology
Capacity
Condition
Of Assets
Plant or
Collection
System
Level of Service
or
Regulatory Change
Business Efficiency
& Research Outcome
CIP Drivers
Transition to Rehabilitation
Dome
Support
Outer Wall
Primary
Influent
Line
Mechanism
Coating
Failure
Projected Cash Flow
$350
$300
Millions
$250
$200
$150
$100
$50
$-
Fiscal Year
Future Projects
Budgeted Projects
Actuals
Current Projects in Design/Construction
•
•
•
•
•
Biosolids Dewatering
Digester Improvements
Ocean Outfall Rehabilitation
Plant Utility/Safety Rehabilitations
Newport Beach Collections
Upcoming Newport
Beach Projects
Upcoming Planned Projects
•
•
•
•
•
•
•
•
Headworks Rehabilitation - $50 Million
Outfall Pump Station Rehabilitation - $20 Million
Primary Clarifier Rehabilitation - $120 Million
Digesters Rehabilitation - $50 Million
Digester Gas Facilities Rehabilitation - $40 Million
Collections Rehabilitations - $100 Million
Odor Control Master Planning - $20 Million
Admin. Facilities Master Planning - $40 Million
Upcoming Design Proposals
Next 2 Years (2013-2015)
No. of Projects
Construction
Estimate
Trunk / Collections
6
$ 51.1 M
Treatment Plant
9
$ 191.7 M
17
$ 242.8 M
Total
Also – Upcoming Planning Studies RFP in August
Upcoming Construction Bidding
Next 2 Years (2013-2015)
No. of Projects
Construction
Estimate
Trunk / Collections
7
$ 57.0 M
Treatment Plant
12
$ 108.4 M
19
$ 165.4 M
Total
Questions?