B.4 Binary Fixed Costs

Download Report

Transcript B.4 Binary Fixed Costs

Readings

Readings

Chapter 7 Integer Linear Programming

BA 452 Lesson B.4 Binary Fixed Costs 1

Overview

Overview

BA 452 Lesson B.4 Binary Fixed Costs 2

Overview Fixed Costs of Production are those production costs that are present whenever production is positive. The simplest model of fixed costs in a linear program restricts decision variables to binary (0 or 1). Fixed Costs of Assignment are modeled like Fixed Costs of Production. The simplest model of fixed costs restricts decision variables (the fraction of work completed) to be binary. Location Covering Problems are a special kind of Linear Programming problem when outputs are fixed because the firm has only established customers, who require coverage by service centers. Worker Covering Problems are like Location Covering Problems, where customers require scheduling workers so that at each time period is covered by a prescribed minimal number of workers. Transportation Problems with New Origins are Transportation Problems extended so that new origins may be added, at a fixed cost. They choose the best plant locations and how much to ship. Transshipment Problems with New Nodes are Transshipment Problems extended so that new transshipment nodes may be added, at a fixed cost. They choose the best transshipment locations. BA 452 Lesson B.4 Binary Fixed Costs 3

Tool Summary Tool Summary  Use binary variables to indicate whether an activity, such as a production run, is undertaken.

 Write a multiple-choice constraint: The sum of two or more binary variables equals 1, so any feasible solution choose one variable to equal 1.

   Write a mutually-exclusive constraint: The sum of two or more binary variables is at most 1, so any feasible solution chooses at most one variable to equal 1. All variables could equal 0.

Write a conditional constraint: An inequality constraint so that one binary variable cannot equal unless certain other binary variables also equal 1.

Write a corequisite constraint: An equality constraint of binary variables, so are either both 0 or both 1.

BA 452 Lesson B.4 Binary Fixed Costs 4

Fixed Cost of Production

Fixed Cost of Production

BA 452 Lesson B.4 Binary Fixed Costs 5

Fixed Cost of Production

Overview Fixed Costs of Production

are those production costs that are present whenever production is positive. The simplest way to model fixed costs in a linear program is to restrict decision variables to be binary (0 or 1). For example, suppose the cost of producing quantity x is 5x. On the one hand, if x can take on any non-negative value (like x is the pounds of hamburger produced), then 5 is the constant unit cost of production. On the other hand, if x can take on only binary values (like x is the number of new books adopted), then cost is 0 if there is no production and 5 if there is positive production, so 5 is the fixed cost of production.

BA 452 Lesson B.4 Binary Fixed Costs 6

Fixed Cost of Production

Question: W. W. Norton & Company,

the oldest and largest publishing company wholly owned by its employees, must decide which new textbooks to adopt next year. The books considered are described along with their expected three-year sales: Book Business Calculus Finite Math General Statistics Mathematical Statistics Business Statistics Finance Financial Accounting Managerial Accounting English Literature German Projected Sales 20 30 15 10 25 18 25 50 20 30 BA 452 Lesson B.4 Binary Fixed Costs 7

Fixed Cost of Production Three individuals in the company can be assigned to these projects, all of whom have varying amounts of time available. John has 60 days, Susan has 52 days, and Monica has 43 days. The days required by each person to complete each project are showing in the following table. For example, if the business calculus book is published, it will require 30 days of John’s time and 40 days of Susan’s time.

Book Projected Sales John Susan Monica Business Calculus Finite Math General Statistics Mathematical Statistics Business Statistics Finance Financial Accounting Managerial Accounting English Literature German 20 30 15 10 25 18 25 50 20 30 30 16 24 20 10 X X X 40 x 40 24 X X X X 24 28 34 50 X X 30 24 16 14 26 30 30 36 BA 452 Lesson B.4 Binary Fixed Costs 8

Fixed Cost of Production Norton will not publish more than two statistics books or more than one accounting book in a single year. In addition, one of the math books (business calculus or finite math) must be published, but not both. Which books should be published, and what are the projected sales? If Monica has 1 more day available, which books should be published, and what are the projected sales? Comment.

BA 452 Lesson B.4 Binary Fixed Costs 9

Fixed Cost of Production 8 9 10

i

1 2 3 4 5 6 7 Book Business Calculus Finite Math General Statistics Mathematical Statistics Business Statistics Finance Financial Accounting Managerial Accounting English Literature German BA 452 Lesson B.4 Binary Fixed Costs 10

Fixed Cost of Production 8 9 10

i

1 2 3 4 5 6 7 Book Business Calculus Finite Math General Statistics Mathematical Statistics Business Statistics Finance Financial Accounting Managerial Accounting English Literature German Projected Sales 20 30 15 10 25 18 25 50 20 30 John 30 16 24 20 10 X X X 40 x Susan 40 24 X X X X 24 28 34 50 Monica X X 30 24 16 14 26 30 30 36 Max s.t.

20

x

1 + 30

x

2 + 15

x

3 + 10

x

4 + 30

x

1 + 40

x

1 + 16

x

2 + 24

x

2 24

x

3 + 20

x

4 + 30

x

3 +

x

3 + 24

x

4

x

4 + +

x

1 +

x

2 25

x

5 + 10

x

5 18

x

6 + 16

x

5

x

5 + + 14

x

6 + 25

x

7 + 24

x

7 + 26

x

7 +

x

7 + 50

x

8 + 20

x

9 + + 28

x

8 + 30

x

8 + 40

x

9 34

x

9 + 30

x

9 +

x

8 30

x

10 50

x

10 36

x

10      = 60 John 52 Susan 43 Monica 2 No. of Stat Books 1 Account Book 1 Math Book BA 452 Lesson B.4 Binary Fixed Costs 11

Fixed Cost of Production Max s.t.

20

x

1 + 30

x

2 + 15

x

3 + 10

x

4 + 30

x

1 + 40

x

1 + 16

x

2 + 24

x

2 24

x

3 + 30

x

3 +

x

3 + 20

x

4 + 24

x

4

x

4 + + 25

x

5 + 10

x

5 18

x

6 + 16

x

5

x

5 + + 14

x

6 +

x

1 +

x

2 25

x

7 + 24 26

x x x

7 + 7 + 7 + 50

x

8 + 20

x

9 + + 28

x

8 + 30

x

8 + 40

x

9 34

x

9 + 30

x

9 +

x

8 30

x

10 50

x

10 36

x

10      = 60 John 52 Susan 43 Monica 2 No. of Stat Books 1 Account Book 1 Math Book BA 452 Lesson B.4 Binary Fixed Costs 12

Fixed Cost of Production 8 9 10

i

1 2 3 4 5 6 7 Book Business Calculus Finite Math General Statistics Mathematical Statistics Business Statistics Finance Financial Accounting Managerial Accounting English Literature German Publish finite math, business statistics, and financial accounting. Projected sales are 80,000.

BA 452 Lesson B.4 Binary Fixed Costs 13

Fixed Cost of Production 8 9 10

i

1 2 3 4 5 6 7 Book Business Calculus Finite Math General Statistics Mathematical Statistics Business Statistics Finance Financial Accounting Managerial Accounting English Literature German Publish finite math, business statistics, and financial accounting. Projected sales are 80,000.

BA 452 Lesson B.4 Binary Fixed Costs 14

Fixed Cost of Production If Monica is available 1 more day (44 days total), optimal projected sales are now 98,000. A big (discrete) gain for a small increase in a constraint.

BA 452 Lesson B.4 Binary Fixed Costs 15

Fixed Cost of Assignment

Fixed Cost of Assignment

BA 452 Lesson B.4 Binary Fixed Costs 16

Fixed Cost of Assignment

Overview Fixed Costs of Assignment

are modeled like Fixed Costs of Production. The simplest model of fixed costs restricts decision variables to be binary. For example, suppose the cost of worker

i

performing the fraction

x ij

of job

j

is 5

x ij

. On the one hand, if

x ij

any non-negative value between 0 and 1 (like

x ij

can take on is the fraction of the job performed), then 5 is the constant unit cost of assignment (like the time cost of working). On the other hand, if

x ij

can take on only binary values, then cost is 0 if you are not assigned (

x ij

= 0) and 5 if you are assigned the entire job (

x ij

= 1), so 5 is the fixed cost of assignment (like the cost of commuting to a job across town).

BA 452 Lesson B.4 Binary Fixed Costs 17

Fixed Cost of Assignment

Question: Tina's Tailoring

has five idle tailors and four custom garments to make. The estimated time (in hours) it would take each tailor to make each garment is shown in the next slide. (An 'X' in the table indicates an unacceptable tailor-garment assignment.)

Tailor Garment 1 2 3 4 5

Wedding gown 19 23 20 21 18 Clown costume 11 14 X 12 10 Admiral's uniform 12 8 11 X 9 Bullfighter's outfit X 20 20 18 21 BA 452 Lesson B.4 Binary Fixed Costs 18

Fixed Cost of Assignment

Formulate an integer program for determining the tailor garment assignments that minimize the total estimated time spent making the four garments.

No tailor is to be assigned more than one garment, and each garment is to be worked on by only one tailor.

This particular problem can be formulated as either a binary program or as an integer program. Any feasible solution to the latter program is binary (0-1).

BA 452 Lesson B.4 Binary Fixed Costs 19

Fixed Cost of Assignment Answer: Define the decision variables

x ij

= 1 if garment i is assigned to tailor

j

= 0 otherwise.

 Find the number of decision variables  = [(number of garments)x(number of tailors)] - (number of unacceptable assignments) = [4x5] - 3 = 17 Find the number of constraints. 1 for each garment and each tailor = 9.

BA 452 Lesson B.4 Binary Fixed Costs 20

Fixed Cost of Assignment  Define the objective function Minimize total time spent making garments: Min 19

x

11 + 23

x

12 + 20

x

13 + 21

x

14 + 18

x

15 + 11

x

21 + 14

x

22 + 12

x

24 + 10

x

25 + 12

x

31 + 8

x

32 + 11

x

33 + 9x 35 + 20

x

42 + 20

x

43 + 18

x

44 + 21

x

45 BA 452 Lesson B.4 Binary Fixed Costs 21

Fixed Cost of Assignment 

Define the constraints of exactly one tailor per garment:

1)

x

11 +

x

12 +

x

13 +

x

14 +

x

15 = 1 2)

x

21 +

x

22 +

x

24 +

x

25 = 1 3)

x

31 +

x

32 +

x

33 +

x

35 = 1 4)

x

42 +

x

43 +

x

44 +

x

45 = 1 BA 452 Lesson B.4 Binary Fixed Costs 22

Fixed Cost of Assignment 

Define the constraints of no more than one garment per tailor:

5)

x

11 +

x

21 +

x

31 < 1 6)

x

12 +

x

22 +

x

32 +

x

42 < 1 7)

x

13 +

x

33 +

x

43 < 1 8)

x

14 +

x

24 +

x

44 < 1 9)

x

15 +

x

25 +

x

35 +

x

45 < 1 BA 452 Lesson B.4 Binary Fixed Costs 23

Fixed Cost of Assignment Minimum time: 55 hours Optimal assignments:

Tailor Garment 1 2 3 4 5

Wedding gown 19 23 20 21 18 Clown costume 11 14 X 12 10 Admiral's uniform Bullfighter's outfit 12 8 11 X 9 X 20 20 18 21 BA 452 Lesson B.4 Binary Fixed Costs 24

Location Covering

Location Covering

BA 452 Lesson B.4 Binary Fixed Costs 25

Location Covering

Overview Location Covering

Problems are a special kind of Linear Programming problem when outputs are fixed because the firm has only established customers. Commitments to established customers require building service centers so that each customer area is covered by a prescribed minimal number of service centers. The objective is to minimize the cost of building service centers. If each center is equally costly, the objective reduces to minimizing the number of service centers. The simplest way to model the all-or-nothing decision to build or not build a serve center is to restrict the fraction of the center built to be a binary (0 or 1) decision variable. BA 452 Lesson B.4 Binary Fixed Costs 26

Location Covering

Question: UPS

is drawing up new zones for the location of drop boxes for customers. The city has been divided into the four zones shown below. You have targeted six possible locations for drop boxes (numbered 1 through 6). The list of which drop boxes could be reached easily from each zone is listed below.

Zone Downtown Financial Downtown Legal Can be Served by Drop Box Locations: 1, 2, 5, 6 2, 4, 5 Retail South 1, 2, 4, 6 Retail North 3, 4, 5 BA 452 Lesson B.4 Binary Fixed Costs 27

Location Covering Formulate and solve a model to provide the fewest drop box locations yet make sure that each zone is covered by at least two boxes. BA 452 Lesson B.4 Binary Fixed Costs 28

Location Covering

Answer:

Min x 1 + x 2 + x 3 + x 4 + x 5 + x 6 s.t.

x 1 + x 2 + x 5 + x 6 x 2 + x 4 + x 5 > 2 > 2 x 1 + x 2 + x 4 + x 6 > 2 x 3 + x 4 + x 5 > 2 BA 452 Lesson B.4 Binary Fixed Costs 29

Worker Covering

Worker Covering

BA 452 Lesson B.4 Binary Fixed Costs 30

Worker Covering

Overview Worker Covering

Problems are like Location Covering Problems. Outputs are fixed because the firm has only established customers. Commitments to established customers require scheduling workers so that at each time period customer needs are covered by a prescribed minimal number of workers. The objective is to minimize the cost of scheduling workers. If each worker is equally costly, the objective reduces to minimizing the number of workers scheduled. The simplest way to model the all-or nothing decision to schedule a worker is to restrict the number of workers scheduled at each time period to be an integer decision variable. BA 452 Lesson B.4 Binary Fixed Costs 31

Worker Covering

Question:

Amazon.com is open 24 hours a day. The number of phone operators need in each four hour period of a day is listed below.

Period Operators Needed 10 p.m. to 2 a.m.

2 a.m. to 6 a.m.

6 a.m. to 10 a.m.

10 a.m. to 2 p.m.

2 p.m. to 6 p.m.

6 p.m. to 10 p.m.

8 4 7 12 10 15 BA 452 Lesson B.4 Binary Fixed Costs 32

Worker Covering Suppose operators work for eight consecutive hours. Formulate and solve the company’s problem of determining how many operators should be scheduled to begin working in each period in order to minimize the number of cashiers needed? (Hint: Workers can work from 6 p.m. to 2 a.m.) BA 452 Lesson B.4 Binary Fixed Costs 33

Worker Covering Answer: Define the decision variables TNP = the number of operators who begin working at 10 p.m.

TWA = the number of operators who begin working at 2 a.m.

SXA = the number of operators who begin working at 6 a.m.

TNA = the number of operators who begin working at 10 a.m.

TWP = the number of operators who begin working at 2 p.m.

SXP = the number of operators who begin working at 6 p.m.

Min TNP + TWA + SXA + TNA + TWP + SXP s.t.TNP + TWA > 4 TWA + SXA > 7 SXA + TNA > 12 TNA + TWP > 10 TWP + SXP > 15 SXP + TNP > 8, all variables > 0 BA 452 Lesson B.4 Binary Fixed Costs 34

Worker Covering BA 452 Lesson B.4 Binary Fixed Costs 35

Transportation with New Origins

Transportation with New Origins

BA 452 Lesson B.4 Binary Fixed Costs 36

Transportation with New Origins

Transportation Problems with New Origins

are Transportation Problems extended so that new origins may be added, at a fixed cost. Also called Distribution System Design Problems, they choose the best plant locations and determine how much to ship from each plant. The simplest way to model those fixed costs in a linear program is with binary (0 or 1) variables. For example, consider a Transportation Problem extended by allowing the possibility of developing a new origin. Suppose the fixed development cost is 5 and the new origin’s supply capacity is 7. That is a linear program with a supply of 7Y at the new origin and added cost term of 5Y, where Y = 0 indicates the new origin is not developed and Y = 1 indicates the new origin is developed. BA 452 Lesson B.4 Binary Fixed Costs 37

Transportation with New Origins

Question: Linksys

operates a plant to produce its wireless routers in St. Louis with an annual capacity of 30,000 units. Product is shipped to regional distribution centers in Boston, Atlanta, and Houston. Because of an anticipated increase in demand, Linksys plans to increase capacity by constructing a new plant in one or more of the following cities: Detroit, Toledo, Denver, or Kansas City. The estimated annual fixed cost and annual capacity for the four proposed plants are as follows: Proposed Plant Annual Fixed Cost Annual Capacity Detroit Toledo Denver Kansas City $175,000 $300,000 $375,000 $500,000 BA 452 Lesson B.4 Binary Fixed Costs 10,000 20,000 30,000 40,000 38

Transportation with New Origins The company’s long-range planning group forecasts of the anticipated annual demand at the distribution centers are as follows: Distribution Center Boston Atlanta Houston Annual Demand 30,000 20,000 20,000 BA 452 Lesson B.4 Binary Fixed Costs 39

Transportation with New Origins The shipping cost per unit from each plant to each distribution center is as follows: Plant\Distribution Detroit Toledo Denver Kansas City St. Louis Boston $5 $4 $9 $10 $8 Atlanta $2 $3 $7 $4 $4 Houston $3 $4 $5 $2 $3 Formulate and solve the problem of minimizing the cost of meeting all demands.

BA 452 Lesson B.4 Binary Fixed Costs 40

Transportation with New Origins

Answer:

Define binary variables for plant construction, Y1 = 1 if a plan is constructed in Detroit; 0, if not Y2 = 1 if a plan is constructed in Toledo; 0, if not Y3 = 1 if a plan is constructed in Denver; 0, if not Y4 = 1 if a plan is constructed in Kansas City; 0, if not Define shipment variables just as in transportation problems, Xij = the units shipped (in thousands) from plant i (i = 1, 2, 3, 4, 5) to distribution center j (j = 1, 2, 3) each year.

BA 452 Lesson B.4 Binary Fixed Costs 41

Transportation with New Origins The objective is minimize total cost. From cost data Plant\Distribution Detroit Toledo Denver Kansas City St. Louis Boston $5 $4 $9 $10 $8 Atlanta $2 $3 $7 $4 $4 Houston $3 $4 $5 $2 $3 shipping costs (in thousands of dollars) are 5X11 + 2X12 + 3X13+ 4X21 + 3X22 + 4X23 + 9X31 + 7X32 + 5X33 + 10X41 + 4X42 + 2X43 + 8X51 + 4X52 + 3X53 BA 452 Lesson B.4 Binary Fixed Costs 42

Transportation with New Origins From cost data Proposed Plant Detroit Toledo Denver Kansas City Annual Fixed Cost $175,000 $300,000 $375,000 $500,000 Annual Capacity 10,000 20,000 30,000 40,000 plant construction costs (in thousands of dollars) are 175Y1 + 300Y2 + 375Y3 + 500Y4 Hence, the objective to minimize total costs is Min 5X11 + 2X12 + 3X13+ 4X21 + 3X22 + 4X23 + 9X31 + 7X32 + 5X33 + 10X41 + 4X42 + 2X43 + 8X51 + 4X52 + 3X53 + 175Y1 + 300Y2 + 375Y3 + 500Y4 BA 452 Lesson B.4 Binary Fixed Costs 43

Transportation with New Origins From capacity data Proposed Plant Detroit Toledo Denver Kansas City Annual Fixed Cost $175,000 $300,000 $375,000 $500,000 Annual Capacity 10,000 20,000 30,000 40,000 Detroit capacity constraint is X11 + X12 + X13 < 10Y1 Toledo capacity constraint is X21 + X22 + X23 < 20Y2 Denver capacity constraint is X31 + X32 + X33 < 30Y3 Kansas City capacity constraint is X41 + X42 + X43 < 40Y4 And St. Louis capacity constraint is X51 + X52 + X53 < 30 BA 452 Lesson B.4 Binary Fixed Costs 44

Transportation with New Origins From demand data Distribution Center Boston Atlanta Houston Annual Demand 30,000 20,000 20,000 Boston demand constraint is X11 + X21 + X31 + X41 + X51 = 30 Atlanta demand constraint is X12 + X22 + X32 + X42 + X52 = 20 Houston demand constraint is X13 + X23 + X33 + X43 + X53 = 20 Non-negativity constraints complete the linear programming formulation.

BA 452 Lesson B.4 Binary Fixed Costs 45

Transportation with New Origins From demand data Distribution Center Boston Atlanta Houston Annual Demand 30,000 20,000 20,000 Boston demand constraint is X11 + X21 + X31 + X41 + X51 = 30 Atlanta demand constraint is X12 + X22 + X32 + X42 + X52 = 20 Houston demand constraint is X13 + X23 + X33 + X43 + X53 = 20 Non-negativity constraints complete the linear programming formulation.

BA 452 Lesson B.4 Binary Fixed Costs 46

Transportation with New Origins The

Management Scientist

solves this mixed integer linear program of 4 binary variables Yj and 15 continuous variables Xij, and 8 constraints. BA 452 Lesson B.4 Binary Fixed Costs 47

Transportation with New Origins BA 452 Lesson B.4 Binary Fixed Costs 48

Transportation with New Origins The

Management Scientist

solves this mixed integer linear program of 4 binary variables Yj and 15 continuous variables Xij, and 8 constraints. BA 452 Lesson B.4 Binary Fixed Costs 49

Transportation with New Origins All variables at the optimum are zero except: X42 = 20, X43 = 20, X51 = 30, and Y4 = 1.

So, the Kansas City plant should be built; 20,000 units should be shipped from Kansas City to Atlanta; 20,000 units should be shipped from Kansas City to Houston; and 30,000 units should be shipped from St. Louis to Boston.

BA 452 Lesson B.4 Binary Fixed Costs 50

Transshipment with New Nodes

Transshipment with New Nodes

BA 452 Lesson B.4 Binary Fixed Costs 51

Transshipment with New Nodes

Overview Transshipment Problems with New Transshipment Nodes

are Transshipment Problems extended so that new transshipment nodes may be added, at a fixed cost. They choose the best transshipment locations and determine how much to ship through each location. The simplest way to model those fixed costs in a linear program is with binary (0 or 1) variables. BA 452 Lesson B.4 Binary Fixed Costs 52

Transshipment with New Nodes Question: Zeron Industries supplies three firms (Zrox, Hewes, Rockrite) with customized shelving for its offices. Zeron orders shelving from the same two manufacturers, Arnold Manufacturers and Supershelf, Inc. Currently, weekly demands by the users are 50 for Zrox, 60 for Hewes, and 40 for Rockrite. Both Arnold and Supershelf can supply up to 75 units to its customers.

Zeron currently ships from its Northside facilities, but it can develop Southside facilities for a fixed cost of 8. Unit costs from the manufacturers to the suppliers are: Arnold Supershelf Zeron N Zeron S 5 8 7 4 The costs to install the shelving at the various locations are: Zrox Hewes Rockrite Zeron N 1 5 8 Zeron S 3 4 4 BA 452 Lesson B.4 Binary Fixed Costs 53

Transshipment with New Nodes 75 7 75 Super Shelf 4 5 8 Zrox 50 Zeron N 1 5 8 3 Zeron WASH S 4 4 60 Rock Rite 40 BA 452 Lesson B.4 Binary Fixed Costs 54

Transshipment with New Nodes 

Define decision variables:

x ij

= amount shipped from manufacturer

i

to supplier

j x jk

= amount shipped from supplier

j

to customer

k

where

i

= 1 (Arnold), 2 (Supershelf)

j

= 3 (Zeron N), 4 (Zeron S)

k

= 5 (Zrox), 6 (Hewes), 7 (Rockrite)

y

= 1 if Zeron S is developed,

y

developed = 0 if Zeron S is not BA 452 Lesson B.4 Binary Fixed Costs 55

Transshipment with New Nodes          Define objective function: Minimize total shipping costs plus setup costs. Min 5

x

13 4

x

47 + 8

y

+ 8

x

14 + 7

x

23 + 4

x

24 + 1

x

35 + 5

x

36 + 8

x

37 + 3

x

45 + 4

x

46 + Constrain amount out of Arnold:

x

13 +

x

14 Constrain amount out of Supershelf:

x

23 +

x

24 < 75 < 75 Constrain amount through Zeron N:

x

13 +

x

23 -

x

35 -

x

36 -

x

37 = 0 = 0 Constrain amount through Zeron S:

x

14 +

x

24 -

x

45 -

x

46 -

x

47 Constrain amount into Zrox:

x

35 +

x

45 Constrain amount into Hewes:

x

36 +

x

46 = 50 = 60 Constrain amount into Rockrite:

x

37 +

x

47 = 40 Setup indicator for Zeron S:

x

45 +

x

46 +

x

47 < 150

y

(The first 4 constraints imply constraint “

x

45 +

x

46 +

x

47

x

45 +

x

46 +

x

47 < 150, so the setup indicator < 150

y

” means, at an optimum,

y

= 1 if any material

x

45 material

x

45 or or

x x

46 46 or or

x x

47 47 transships through Zeron S, and

y

transships through Zeron S.) = 0 if no BA 452 Lesson B.4 Binary Fixed Costs 56

BA 452 Quantitative Analysis

End of Lesson B.4

BA 452 Lesson B.4 Binary Fixed Costs 57