SPIRE & PACS SORPTION COOLERS INSTRUMENT BASELINE DESIGN REVIEW 30 000 K

Download Report

Transcript SPIRE & PACS SORPTION COOLERS INSTRUMENT BASELINE DESIGN REVIEW 30 000 K

SPIRE & PACS SORPTION COOLERS
INSTRUMENT BASELINE DESIGN REVIEW
30 000 K
3000 K
300 K
30 K
3K
0.3 K
Lionel Duband, L. Clerc, L. Miquet, L. Guillemet,
R. Vallcorba, D. Guillaume, D. Communal, Patrick
Dupont/Eric Dubois (BV)
SERVICE DES BASSES TEMPERATURES
DRFMC / DSM - CEA GRENOBLE
CEA-Grenoble / DSM / DRFMC / SBT / Lionel DUBAND - Instrument Baseline Design Review - PACS and SPIRE Cooler - Feb. 27/28 2002
1
COOLER STATUS - 1
DESIGN : completed
(full compatibility with PACS/SPIRE)
Mechanical performance :
Full numerical modelling done
CQM/STM Manufacturing : completed
All anomalies dealt with and traced
All parts available
CEA-Grenoble / DSM / DRFMC / SBT / Lionel DUBAND - Instrument Baseline Design Review - PACS and SPIRE Cooler - Feb. 27/28 2002
2
COOLER STATUS - 2
CQM & STM Assembling : 90% done
STM unit
Slight delay due to subcontractors
Cooler heart ready
for EB welding
CEA-Grenoble / DSM / DRFMC / SBT / Lionel DUBAND - Instrument Baseline Design Review - PACS and SPIRE Cooler - Feb. 27/28 2002
3
GROUND SUPPORT EQUIPEMENT (MAIN)
TEST CRYOSTAT
(2 "small" cryostats available)
LHe
LN2
New large test cryostat delivered Feb. 2002
Instrumentation in progress (wiring, thermometry, etc..)
Needed for performance test (> 48 hours autonomy)
CLEAN ROOM : Implementation in progress
Expected to be available April 2002
CEA-Grenoble / DSM / DRFMC / SBT / Lionel DUBAND - Instrument Baseline Design Review - PACS and SPIRE Cooler - Feb. 27/28 2002
4
COOLER AIV PLAN
Assembling
(Techmeta/SNLS/OMG
/Thermocompact/SBT)
Proof pressure tests
(20 MPa)
Thermal tests #1
[Health Check ref]
Vibration tests
(room T)
Thermal tests #2
(health check)
One week bake out
(80°C)
Thermal tests #3
(health check)
Performance test
(nominal)
Packing
Delivery
CEA-Grenoble / DSM / DRFMC / SBT / Lionel DUBAND - Instrument Baseline Design Review - PACS and SPIRE Cooler - Feb. 27/28 2002
5
SCHEDULE
CQM
January
2002
February
Note : Planning can
be impacted by ECR
on electrical isolation
Mars
April
May
Assembling PreTests +
Integration
Machining
Winter
Assembling
July
Vibration
Thermal
Tests
Vacuum
Aug
Available for
delivery
Thermal Tests
PFM & FS
2002
2003
Autumn
June
Spring
Summer
Autumn
Delivery PFM
Qualification PFM
Winter
Delivery FS
Qualification FS
CEA-Grenoble / DSM / DRFMC / SBT / Lionel DUBAND - Instrument Baseline Design Review - PACS and SPIRE Cooler - Feb. 27/28 2002
6
PA PLAN - 1
• PA requirements implemented
- covers all project life
- Potential risks & hazards identification done
- Cleanliness and contamination control
- Material evaluation program in progress (Kevlar)
- DML & DPL done
- Subcontractors evaluated
- Non conformance reporting system implemented
- Configuration control system done
- Traceability (acceptance data package)
CEA-Grenoble / DSM / DRFMC / SBT / Lionel DUBAND - Instrument Baseline Design Review - PACS and SPIRE Cooler - Feb. 27/28 2002
7
MAIN PROJECT DOCUMENTATION
doc. Name
completion
status
Cooler Specifications
ICD
PA Plan
Developement Plan
Detailed Planning
DML/DPL
H/W tree
MAIV Flow Chart
AIV Plan
FMECA
Cleanliness Philosophy
All procedures
Released
Released
Released
Released
Released
Released
Released
Released
Released
Released
Released
In progress
Not formally approved
Not formally approved
Approved
Not formally approved
under review
under review
Not formally approved
Not formally approved
Under review
Not formally approved
Internal to SBT
CEA-Grenoble / DSM / DRFMC / SBT / Lionel DUBAND - Instrument Baseline Design Review - PACS and SPIRE Cooler - Feb. 27/28 2002
8
TO DATE : PROBLEMS & SOLUTIONS
Deformation of structure
after EB welding
Anomaly spotted
and traced
MRBs
(internal & subcontractors)
Deformation max. :
≈ 400 µm on 150 mm plate
Angle iron added
Impact on FM : None
Structure modified accordingly
No delta qualification expected
Implementation
of solution
Qualification
CEA-Grenoble / DSM / DRFMC / SBT / Lionel DUBAND - Instrument Baseline Design Review - PACS and SPIRE Cooler - Feb. 27/28 2002
9
OPEN ISSUES AND CRITICAL AREAS
ELECTRICAL ISOLATION
SPIRE ECR issued - Recently agreed by PACS (Feb. 15)
Impact : - need to identify/qualify solution
- but cooler already built
- planning : to be evaluated, but some margin
available today
KEVLAR TENSION
development of dedicated tool
- various solutions being evaluated
CEA-Grenoble / DSM / DRFMC / SBT / Lionel DUBAND - Instrument Baseline Design Review - PACS and SPIRE Cooler - Feb. 27/28 2002
10
CONCLUSION
•
•
•
•
•
No major problems to date
CQM first thermal tests : ≈ April
STM available end of March
Electrical isolation : to be adressed
Kevlar : experiments continue
data built up
• out of SBT "territory" : cryostat straps need attention
CEA-Grenoble / DSM / DRFMC / SBT / Lionel DUBAND - Instrument Baseline Design Review - PACS and SPIRE Cooler - Feb. 27/28 2002
11