Projects in Progress Fran Fruzen Intermediate School

Download Report

Transcript Projects in Progress Fran Fruzen Intermediate School

Joint School District of Beloit
Beloit City Council Meeting
Monday, February 24, 2014

5 primary buildings
◦
◦
◦
◦
◦
Converse
Robinson
Hackett
Todd
Merrill
The Swimming Pool

Cunningham Intermediate School

Gaston Primary School

Fitness Center

McNeel

Aldrich

Memorial
Update as of
January 29, 2014
Architect Renderings
North-East Exterior Front View
North-West Exterior Front View
Architect Renderings
West Exterior View
South-West Exterior View
Architect Renderings
South-East Exterior View
North-East Exterior View
Site Layout
Sidewalk
Storage
Building
16 x 16
4-6 Entrance
Plaza
7/8 Entrance
Dumpster
Enclosure
Hard
Surface
Play
Site Plan
First Floor
First Floor=
70,242 SF
Second Floor= 30,214 SF
Total=
100,456 SF
Second
Floor
First Floor=
70,242 SF
Second Floor= 30,214 SF
Total=
100,456 SF

Site Clearing/Demolition: March/April 2014

Bid Date: April 17, 2014

Construction Start: April 30, 2014

Construction Complete: July 31, 2015
 Tennis
Courts
 Big Field between 6th and 4th
 Scoreboards
 New Storage for Football
 Propane Tank outside of
Swimming Pool