PNRA Licensing Basis
Under section 20 of PNRA Ordinance, PNRA is empowered to grant authorization which states that “The Authority may, on application made to it accompanied by such information and documents, as may be prescribed by regulations, grant an authorization for carrying out of such activities as are specified in the authorization for such period as it may specify. Accordingly PNRA has established its regulatory framework for the licensing/authorization of nuclear installations named as “Regulations for Licensing of Nuclear Installation(s) in Pakistan PAK/909”.
2
Regulated Facilities
Nuclear Installations and Nuclear Grade Equipment Manufacturer Nuclear Medical Centers & Agriculture Research Centers
PNRA
X-Ray Machines , Diagnostic Radiology & Irradiators used for sterilization of medical equipment Industrial Radiography & Industrial applications of radiation
PNRA Regulations
Technical Regulations Regulations on Radiation Protection (PAK/904) Regulations on the Safety in NPP Site Evaluation (PAK/910) Regulations for the Safety of NPP Design (PAK/911) Regulations on the Safety of NPP Quality Assurance (PAK/912) Regulations on the Safety of NPP Operation (PAK/913) Regulations on Management of a Nuclear or Radiological Emergency (PAK/914 ) Regulations on Radioactive Waste Management (PAK/915) Regulations for the Safe Transport of Radioactive Material (PAK/916)
PNRA Regulations
Administrative Regulations
Regulations on Licensing Fee (PAK/900) Regulations for Licensing of Nuclear Installations (PAK/909) Regulations for Licensing of NPP Equipment Manufacturers (PAK/907) Regulations for Licensing of Radiation Facilities other than Nuclear Installations (PAK/908) PNRA Enforcement Regulations (PAK/950)
Licensing Stages for Nuclear Power Plants
Closure/ Removal from Regulatory Control Control Authorization for Decommissioning Licence Revalidation Site Registration Construction Licence
PNRA Licensing Stages
Annual Renewal Permission for Commissioning Loading of nuclear material in the system Operating Licence
6
Applicable Nuclear Safety and Security Standards
All nuclear installations, for the purposes of siting, design, construction, commissioning, operation and decommissioning/closure, shall conform to the existing PNRA regulations. In areas where the PNRA regulations are not available, relevant latest US Nuclear Regulatory Commission regulations shall be deemed to be applicable. Alternately, the licensee may choose to follow the latest revisions of the applicable IAEA Safety and Security Standards. In case the nuclear safety and security standards of another country are proposed to be followed, the applicant/licensee shall demonstrate to the entire satisfaction of the Authority that the standards, proposed to be followed, offer the same or better standards of safety, security, quality and reliability than would have been offered by the nuclear safety and security standards mentioned above.
7
Design and Safety Criteria
The licensee is required to establish design and safety criteria and obtain PNRA approval Comprising a list of standards and practices to be followed such as o o o o Requirements to be followed (Regulations, IAEA Nuclear Safety Standards, 10CFR, etc.) Regulatory and Safety Guides (PNRA, IAEA, NRC) Industrial Codes and Standards (International) Experience Feedback & Practices to be followed 8
Licensing Stages & Submission Requirements
Site Registration
Application
Construction License
Preliminary Safety Analysis Report (PSAR) Site Evaluation Report (SER) No Objection Certificates (NOC) from relevant government departments Quality Assurance Program for Siting Design PSA of full power internal initiating events (for NPPs only) Quality Assurance Program for design and construction phases
Permission for Commissioning
Commissioning Program Quality Assurance Program for Commissioning Phase
Licensing Stages & Submission Requirements
Permission to Introduce
FSAR
Nuclear Material (FLP)
QAP for Operation Physical protection program Emergency Preparedness Plans Environmental monitoring program PSA Level-1 Radioactive waste management program Initial decommissioning plan Radiation protection program PSI/ISI program
Operating License (OL) Revalidation of operating license
Result of Commissioning tests Latest reports of periodic safety review (PSR) Update of all documents submitted for FLP
Licensing Stages & Submission Requirements
Licensing Beyond Design Life
Latest Periodic Review reports Update of all sub-missions for OL of Safety licensing required PSA Level 1 Plus based on actual plant data (for NPPs only) Decommissioning Program
License for Decommissioning Or Closure
Final decommissioning Plan Radioactive waste management program Technical specifications during decommissioning Physical protection program Environmental monitoring program Radiation protection program Emergency Preparedness Plan (EPP)
Removal from Regulatory Control
Decommissioning completion report Final radiological survey report
Licensing Process
Submission of Safety Case Review & Assessment Safety Regulations License Conditions Inputs from inspections Inputs of consultants Issuance of Authorization Yes Case Acceptable No Comments sent Responses received Regulatory Position prepared Yes Conduct of Review Meetings No Issues Resolved Actions taken and reports submitted Actions identified
Regulatory Oversight During Different Phases
PNRA has established a well defined Regulatory Oversight Process which will be effectively used during different phases/stages of nuclear installation. For the assessment and analysis of documents submitted by licensee during different phases of nuclear installation as regulatory requirement are subjected to the process of review and assessment and results of these review & assessment are being followed-up, documented and recorded for regulatory compliance during all phases of nuclear installation. Similarly, inspection & enforcement are carried out to ensure compliance with the national regulations, licence and licensing conditions, and commitments made by the applicant/licensee for the safety of nuclear power plants.
13
Inspection Program
Regulatory Inspections
Manufacturing Construction Commissioning Inspectors ensures Conformity with the actual conditions • • • Compliance with PNRA regulations Licensing submissions Terms and conditions of the license Operation Includes third party inspections and inspections at manufacturing works Decommissioning
Conclusion
PNRA Licensing process is quite effective and is in accordance with international standards.
PNRA always believe on proven technology and processes.
So for PNRA issued Operating Licenses to three operational NPPs.
Two construction licenses has been issued to two NPPs.
15
THANK YOU