CITY OF OWASSO
Roadway To Implementation – How A Small Oklahoma
Community Adopted A Successful Stormwater Program
Ana Stagg, PE, CFM, Meshek & Associates, PLC
Roger Stevens, City of Owasso
1437 SOUTH BOULDER AVE., SUITE 1080 TULSA, OKLAHOMA 74119 918.392.5620 (P) 918.392.5621 (F) WWW.MESHEKENGR.COM
PROJECT UNDERSTANDING
–
ABOUT OWASSO
–
WHAT HAPPENED
PROJECT APPROACH
–
MASTER PLANNING PROCESS
–
PUBLIC INVOLVEMENT PROGRAM
–
IMPERVIOUS AREA STUDY
–
CONSTRUCTION OF IMPROVEMENTS
PROJECT SCHEDULE
QUESTIONS
AGENDA – THE PROCESS
SPEAKERS QUALIFICATIONS
ROGER STEVENS, PUBLIC WORKS DIRECTOR
Served as Owasso Public Works
Director 2002-2007
Currently serves as Owasso Public
Works Director since 2007
Over15 years of experience in civil
engineering, management
consulting and municipal
government.
Certified Water and Wastewater
Works Operator OK-20972(B) OK95405(A)
Employed with the City of Owasso,
Public Works Department, since
1991
Member of INCOG (Transportation
Technical Committee)
Member of the Owasso Economic
Development Authority
BS, Civil Engineering, 1993 Florida
Institute of Technology
Member of the Owasso Annexation
Committee
ME, Environmental Engineering,
1997, Cornell University
1997 Eagle Award Winner for
Excellence in Public Service
At City of Owasso, Public
Department, since 1991. (P.S. In
1980, I was only 8 years old).
Certified Floodplain Manager OK06-00048
Oklahoma PE 20914
Certified Water and Wastewater
Works Operator OK-20972(B) OK95405(A)
MBA, Business Administration,
2003, Northwest University, Kellogg
Graduate School of Business
ABOUT THE SPEAKERS
ANA STAGG, CONSULTING ENGINEER
Country
State
Counties
Incorporated
United States
Oklahoma
Tulsa, Rogers
1904
Government – City Manager
• Mayor
Steve Cataudella
• City Manager Rodney J Ray
Area
• Total
10.1 sq mi (26.0 km2)
• Land
10.0 sq mi (26.0 km2)
• Water
0.1 sq mi (0.06 km2)
Population (2000)
• Total
18,502
• Density
1,844.4/sq mi
Annual Budget
•General
$ 5.5 million
•Utility
$ 7.3 million
Website
www.cityofowasso.com
ABOUT OWASSO, OKLAHOMA
Coordinates: 36°17′25″N 95°49′43″W /
36.29028°N 95.82861°W / 36.29028; -95.82861
growth rate was 7.5%.
2000, population of
18,502.
2010, population
projected at 35,000.
2000-2003, voted as
the highest growth
rate in Oklahoma for
cities of at least 10,000
people.
2000-2010, Owasso
transformed from a
small rural community
to a thriving suburban
city.
2000-2010 OWASSO BLOSSOMS…
1990-2000, annual
planning documents
Secure new financing
resources
Upgrade priority
infrastructure
Improve essential services
Support development
WITH GROWTH CAME PROSPERITY…
Update critical master
Overtopped bridges
Roadway closures
Public objection
WITH GROWTH CAME RUNOFF…
Increased flooding
DEVELOPING A PLAN OF ATTACK…
DON’Ts
Apply a watershed approach
Be reactive
Listen/inventory all
Ignore the problem
complaints
Investigate partnering
opportunities
Use quantitative
prioritization processes
Explain implementation plan
in detail
Provide ample comment
periods
Employ process mediators
Consult experts
Follow up with
agreements/promises
Start without a plan
Overlook the watershed
effect
Act in response to the
squeaky wheel
Use qualitative prioritization
processes
Neglect (overreact to)
development
Forget already developed
areas
FORMULATING THE PLAN…
DO’s
Beginning of Process –
USE QUESTIONNAIRES
Following Inventory Phase
Review Mitigation Measures
Draft Plan – OBTAIN
PUBLIC BUY-IN
Public Hearing @ Planning
Commission for Final Plan
City Council / County
Commission Public Hearing
for Final Plan – MAKE IT
FORMAL
SEEK PUBLIC SUPPORT EARLY…
Start Early – DO IT OFTEN
Television Coverage
Public Meetings
Newspapers
Radio/TV Public
Announcements
Community/Civic
Groups
ADVERTISE AND COMMUNICATE…
Utility Billing Inserts
TECHNICAL ADVISORY COMMITTEE
Appointees of Elected
City Manager/Asst. City
Officials
Manager
Flood Victims
Building Officials
Planning Commission
Utilities
Board of Adjustment
Emergency Management
Floodplain Board
Interested Citizens
Parks & Recreation
Economic Development
Floodplain Manager
PUBLIC INVOLVEMENT OPPORTUNITIES…
CITIZENS ADVISORY COMMITTEE
WHAT’S THE BENEFIT?
Existing problems
Prevent new problems
New land development
Correct existing problems
Increased impervious area
Enhance the community's
Speeding up surface flow
with paved streets and
parking lots, lawn areas
instead of pasture, etc.
(resultant shorter times of
concentration)
Loss of floodplain and
resultant loss of floodplain
storage
Constructed channels that
speed up the water
through a reach
safety, environment and
quality of life
EXPLAINING WHY A PLAN IS NECESSARY…
WHAT’S THE CAUSE?
approach to…
–
Problem areas
inventory,
–
Alternative evaluation,
–
Development of
solutions, and
–
Prioritization of projects.
Allows Hazard Mitigation
Plan – Appendix – Inclusion
Facilitates Grant Funding
Step One:
Organize to Prepare the
Plan
Step Two:
Involve the Public
Step Three:
Coordinate with Other
Agencies and
Organizations
Step Four:
Assess the Hazard
Step Five:
Assess the Problem
Step Six:
Set Goals
Step Seven:
Review Possible Activities
Step Eight:
Draft an Action Plan
Step Nine:
Adopt the Plan
Step Ten:
Implement, Evaluate, and
Revise
FOLLOWING FEMA’s PROCESS…
Provide detailed, logical
Application Process
Enables Flood Plain Maps
FEMA 10-STEP PROCESS
Revisions (CLOMRs)
14
Regional Stormwater
Detention/Retention
Channelization,
Bridge/Culvert/Storm
Sewer Replacement
Acquisition of Buildings in
PREVENTION OPTIONS
Regional Stormwater
Detention/Retention
Acquisition of Property in
the Floodplain
Stricter Regulatory
Controls
the Floodplain
Floodproofing
SELECTION AND PRIORITIZATION
Flood Damage Reduction
Benefits
Increased Safety
Nuisance Flooding
Abeyance
Allowance for Future
Development
Multi-use Facilities Where
Possible
COVERING DETAILS…
MITIGATION OPTIONS
10-YEAR FLOODPLAIN MAPPING
100-YEAR FLOODPLAIN MAPPING
FLOODPLAIN VISUALIZATION
ILLUSTRATING RESULTS…
2-YEAR FLOODPLAIN MAPPING
IMPLEMENTING THE ($30-MILLION) PLAN…
17
Protect human life, health, and property;
Minimize public and private storm and
flood losses from stormwater runoff in the
City;
(2003) Master Planning starts
(2003) Ordinance 754
Provide for development of Stormwater
Master Plan which will define the existing
and future drainage system, identify
drainage facilities improvements and
project long-range capital improvements
requirements; and
establishes Stormwater
Management Program
(2003) Resolution 2003-07
establishes ($2.50/ESU)
Service Fee…
Comply with the Phase II Stormwater
Management regulations.
ORDINANCE 754 (2003)
Customer Type
Residential
Non-residential
Meters > 2-inch
Meters < 2-inch
No. of
Customers
Annual
Unit
Charge
–
1 ESU – residential
–
3 ESU – nonresidential (w/ water
meters > 2-inch)
(2003) Stormwater Program
Total
7,450
$30.00
$ 223,500
65
310
$30.00
$90.00
$ 1,950
$ 27,900
$ 253,350
starts w/ annual budget of
$265,000
SECURING FUNDING…
ORDINANCE 754 (2003)
is completed
Over 30 Projects identified
Total cost of program is over
30 projects and $20 million
Top Ten Projects = $2.5
million
Implementation @
$250,000/year > 10 yrs
(2005) Commissioned
“Impervious Area Utility Fee”
(2005-present) Find Partners
PHASE I OF IMPLEMENTATION…
(2005) Master Drainage Plan
Detail edge of pavement, building
outlines and other impervious
planimetrics
Use developed polygons to measure
impervious areas
Determine size of Equivalent Service
Unit (ESU) for Owasso
Average ESU = 2,500 to 3,000 sq.ft
Recommend fee and estimate revenue
DELIVERABLES
Map of impervious surfaces linked to
GIS parcel data
Database containing:
IMPERVIOUS AREA STUDY…
TASKS
– Number of ESU’s per parcel
– Corresponding billing amount
Data Table developed in a format to
facilitate linkage to billing department
accounts
Customer Web Viewer identifying
parcel impervious area and/or ESU’s
20
Phased implementation used
potential 600% increase nonresidential revenues
to mitigate impact…
(2005) Commercial Service
Charge Implementation
Customer Type
Residential
Non-residential
Total
–
FY 05-06 25% of Fee
–
FY 06-07 50% of Fee
–
FY 07-08 75% of Fee
–
F Y 08-09 100% of Fee
FY 05-06
FY 06-07
FY 07-08
FY 08-09
$ 240,000
$ 45,000
$ 255,000
$ 90,000
$ 270,000
$ 135,000
$ 285,000
$ 180,000
$ 285,000
$ 345,000
$ 405,000
$ 465,000
IMPLEMENTATION OF IMPERVIOUS AREA
STUDY FINDINGS…
Impervious Study revealed
PARTNERS WANTED
Immediate 150% increase
Tulsa County
in Non-Residential Fee
2005-2006 Revenues
estimated at $285,000
Potential annual revenues
of $480,000
Maximum debt ability…
– 6%, 15 yr, $4.6 M
– 6%, 20 yr, $5.5 M
Need…
– Top Priority > $6.7 M
– Total > $20 M
Oklahoma Water
Resources Board
Development Community
FEMA - HMGP
CONSTRUCTION OF IMPROVEMENTS…
STORMWATER UTILITY FEE
(May 2000) First complaints
recorded
(June 2003) Study
commissioned
(July 2003) Council
approves immediate action
(August 2003) Design
completed
(October 2003)
Construction begins
(December 2003)
Construction ends
Cost to City = $250,000
CITY BEGINS IMPLEMENTATION…
GOLF COURSE USED TO REMEDIATE RESIDENTIAL FLOODING
(2004) Complaints received
on newly constructed
residential subdivision
(2004) City commissioned
study finds errors in
engineering assumptions
(2004) Developer asked to
construct remedial actions
(2005) Necessary
improvements constructed
and functional
Cost to City = $0
NEW DEVELOPMENT HELD TO STANDARDS…
DEVELOPER AGREES TO CONSTRUCT REMEDIAL DETENTION
detention facility serves as
Regional Detention
Developer contributed land
and built facility
City contributed 70% of
cost
Total project savings of
$600,000
2006 DEVELOPERS STEP TO BAT…
Residential development
Provides remedial storage
for downstream residential
structures
Provides detention storage
to future development
Enables larger
development of retail
space
Uses Fee-In-Lieu and
OWRB Loan for financing
Project Value = $3 MIL
Project Cost = $1.8 MIL
City Cost = $0
2008 CITY HITS HOME RUN…
GARNETT REGIONAL DETENTION
– 2006-present, Phase II Program compliant
– 2009, new FIRM maps adopted (City’s MDP maps)
– 2011, Completing GIS inventory of stormwater
infrastructure
– 2010-2011, $1.5 million Stormwater Budget
– 2010-2015, $6.5 million earmarked for Stormwater
Improvements
OWASSO LOOKS AHEAD…
– 2003-2010, Over $5 Million spent in Stormwater
Improvements
CITY OF OWASSO
QUESTIONS?
Roadway To Implementation – How A Small Oklahoma
Community Adopted A Successful Stormwater Program
Ana Stagg, PE, CFM, Meshek & Associates, PLC
Roger Stevens, City of Owasso
1437 SOUTH BOULDER AVE., SUITE 1080 TULSA, OKLAHOMA 74119 918.392.5620 (P) 918.392.5621 (F) WWW.MESHEKENGR.COM