SNS Experience with a High-Energy Superconducting Proton Linac J. Galambos CARE-HHH-APD Beam 07 Workshop 1-5 October, 2007
Download ReportTranscript SNS Experience with a High-Energy Superconducting Proton Linac J. Galambos CARE-HHH-APD Beam 07 Workshop 1-5 October, 2007
SNS Experience with a High-Energy Superconducting Proton Linac J. Galambos CARE-HHH-APD Beam 07 Workshop 1-5 October, 2007 The SNS Linac SNS is a pulsed, accelerator driven spallation neutron source It is driven by a high power linac 1.5 MW baseline (constructed device) 3 MW upgrade power (ongoing project, CD-0 approved) It is the first high power or high energy superconducting proton linac 80% of the acceleration is provided by superconducting cavities We are writing the book on tuning it as we go OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 2 A Brief History of the SNS Superconducting Linac Fall 1998: SNS receives approval and funds to build SNS (copper linac) Summer – Fall 1999: Y. Cho leads a task force to investigate the feasibility to change to a Superconducting Linac Dec. 1999 – Jan. 2000: SNS advisory panel and DOE review panel approves the change, Jefferson Lab joins the SNS collaboration June 2003 - First cryo-module delivered to Oak Ridge August 2004– First cryo-module cool-down March 2005 – July 2005: High power RF tests August 2005: Beam commissioning Jan.- Feb. 2006: Support Ring Commissioning Oct. 2006 – present: Support neutron production runs OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 3 Superconducting Linac Designed an built by Jefferson Laboratory SCL accelerates beam from 186 to 1000 MeV SCL consists of 81 cavities in 23 cryomodules Two cavities geometries are used to cover broad range in particle velocities Cavities are operated at 2.1 K with He supplied by Cryogenic Plant Medium beta cavity High beta cavity OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 4 Linac RF Systems Designed and procured by LANL All systems 8% duty factor: 1.3 ms, 60 Hz 7 DTL Klystrons: 2.5 MW 402.5 MHz 4 CCL Klystrons: 5 MW 805 MHz 81 SCL Klystrons: 550 kW, 805 MHz 14 IGBT-based modulators 81 SCL Klystrons High Voltage Converter Modulators 2nd largest klystron and modulator installation in the world! DTL Klystrons CCL Klystrons OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 5 Layout of Linac RF with NC and SRF Modules 402.5 MHz, 2.5 MW klystron 805 MHz, 5 MW klystron Warm Linac RFQ DTL (1) (6) 805 MHz, 0.55 MW klystron CCL (4) 86.8 MeV 2.5 MeV 186 MeV SRF, ß=0.61, 33 cavities 379 MeV SRF, ß=0.81, 48 cavities 1000 MeV SCL from CCL Linac 1 (81 total powered) •SCL has 81 independently powered cavities Many parts to keep running Many values to set w.r.t. the beam OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 6 Cavity Limitations I – Field Emission Electrons emitted from high field surface Radiation ~ constant throughout the RF pulse PM Radiation detector RF waveform The primary cavity gradient limitation OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 7 Cavity Limitations II – “Cavity-Coupler Interaction” Radiation waveform Electron probe signal Some cavities have both effects Another gradient limitation – not completely understood OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 8 Cavity Limitations III - Collective behavior (clear indication at higher rep. rate) •Amplitude and phase setpoints of one cavity affect heating at other places •Need to find setpoints that are friendly to neighboring cavities Example: CM13 individual limits 19.5, 15, 17, 14.5 MV/m CM13 collective limits at 60 Hz ; 14.5, 15, 15, 10.5 MV/m a b c d OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 9 SCL Sub-component Concern I – HOM Coupler HOM couplers added as insurance even though probability that they are needed was very low HOM feed-through is susceptible to damage (FE, MP interactions + fundamental mode coupling) Some cavities are limited by coupling of fundamental power coupling (stray field + filter not set properly). We would not include HOM filters if we were starting over OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 10 SCL Subcomponent Concern II – CCG Vacuum Gauges Used to monitor vacuum activity at the coupler window – interlock input Often takes a long time for them to “wake up” when turning on a cavity Erratic signals often observed when they do “wake up”. Inconsistent with electron probe signals ~5K CCG Flange Temperature Coupler Temperature The CCGs do not limit the performance of any cavities, but they do complicate operation. Moving towards interlocking on electron detectors and we have developed procedures for cavity turn on to avoid non-physical signals. OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 11 SCL Subsystem Concern III – Piezo Tuner Piezo tuners added to cancel Lorentz detuning Never have been used Some have broken – rendering the cavity useless 3 We are removing them. Lesson – keep the design as simple as possible Piezo tuner 1. CAD Model 2. Tuner + Bare Cavity 3. Reality – Pretty Complicated OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 12 Accelerating gradients and statistics 30 10 Hz individual limits 60 Hz collective limits 25 15 10 5 CM19; removed 23 b 22 c 21 a 21 d 19 c 20 b 18 a 18 d 17 b 15 d 16 c 14 b 15 a 13 c 12 a 12 d 10 a 11 a 9a 8a 7a 6a 5a 4a 3a 2a 0 1a Eacc (MV/m) 20 Cavity number Design gradient Average limiting gradient (collective) Average limiting gradient (individual) Large fundamental power through HOM coupler Field probe and/or internal cable (control is difficult at rep. rate >30 Hz) OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 13 Accelerating gradients and statistics (II) 25 25 Collective Limits at 60 Hz Collective Limits at 60 Hz Individual Limits Operating setpoints at 60 Hz 20 no. of cavities no. of cavities 20 15 10 5 15 10 5 0 0 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 5 6 7 8 9 Ea (MV/m) 10 11 12 13 14 15 16 17 18 19 20 21 Ea (MV/m) OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 14 SCL Cavity Amplitudes 81 81 77 77 77 73 73 69 69 65 65 61 61 57 57 53 53 49 49 45 45 41 41 37 37 33 33 29 29 25 25 21 21 17 17 13 13 99 555 30 35 35 30 30 25 25 25 20 20 20 15 15 15 10 10 10 555 000 111 E0 (MV/m) (MV/m) E0 E0 (MV/m) (MV/m) Cavity Second Run Run First Design Run Ring Commissioning cavity cavity Strategy is to run cavities at their maximum safe amplitude limit Need to be flexible – SRF capabilities change, not near the design Linac output energy is a moving target OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 15 Tune-up Strategy RF group provides allowable RF gradients Calculate expected output energy Devise an appropriate RF and Quad tune Longitudinal: ~ constant focusing Transverse: scale design values with Br Local optimization for matching sections Step through each cavity to set the phase relative to the beam Scale downstream transfer line and accumulator ring magnets with beam energy OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 16 Setting the Phase of the SCL Cavities Example SCL Phase Scan BPM Phase Difference Black line = measurement fit Dot = model Red = cosine fit A beam based measurement must be done to initially set each cavity RF phase setpoint Scan the cavity phase of a cavity 360, and observe the resultant change in the Time of Flight (TOF) between 2 downstream detectors Compare this difference with a model calculations. Gives the input beam energy, cavity voltage and RF phase offset calibration Need good relative phase measurements from the detectors (~ 1degree!) Scan each cavity sequentially RF Cavity Phase OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 17 Drifting Beam Method to Determine Cavity Phase and Amplitude Setpoints proton beam 422MeV, 15mA, 40us simulations from the model with superimposed measured noise signals measured with/without cavity detuning 100 80 Signal Phase (deg) Signal Phase (deg) 100 60 40 0 Hz 200 Hz 20 400 Hz 80 60 40 0 Hz 200 Hz 20 0 400 Hz 0 0 20 40 t (us) 60 80 100 0 20 40 t (us) 60 80 100 Allow beam to drift through a cavity Beam excites the cavity, and by comparing to a model one can calibrate the LLRF phase and amplitude readings Phase prediction ~ 1 degree, amplitude ~ 4% compared to phase scan technique OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 18 SCL Cavity Phase Setup Times are Getting Shorter August 2005: 48 hrs 560 MeV, initial run, > 20 cavities off Dec. 2005: 101 hrs 925 MeV, turned on all planned cavities July 2006: 57 hrs 855 MeV Oct 2006: 30 hrs 905 MeV, used established cavity turn on procedure Power cavities on sequentially Jan. 2007: 6 hrs 905 MeV, beam blanking used, which allowed all cavities to be on during the tuning process The procedures used to setup the superconducting linac have matured, and the setup time is now minimal Still exists a need for fast recovery from changes in the SCL setup OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 19 SCL Tune-up – Linac Energy Gain is Understood and Predictable Predicted - Measured Energy Gain 10_01_2006 1_16_2007 1.00 0.00 Energy Gain per Cavity Prediction Error -1.00 30 21 31 41 51 61 71 81 15 10 Energy gain per cavity is predictable to a few 100 keV and distributed about 0. 5 Final energy is predictable to within a few MeV -1 -0 .8 -0 .6 -0 .4 -0 .2 Cavity 1_16_2007 20 0 1 11 10_07_2006 0. 4 1 Frequency 25 0. 8 -2.00 0. 6 LLRF Cable 0 0. 2 D E (MeV) 2.00 Energy Gain Error (MeV) OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 20 Scaling Method for Cavity Fault Recovery New cavity phases Use beam measurements for original beam arrival times New Beam Energy User inputs changes to the SCL RF setup Model predicts changes in the beam arrival times (RF phase setpoint changes), sends them to the machine and predicts the new beam energy Takes < 1 second to calculate and apply the new SCL setup However – we have applied this technique to recover from “events” that take hours / days to evaluate and proceed OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 21 Application of the Cavity Fault Recovery Scheme (I) 6 Phase Change Measured Error 200 4 100 2 0 0 -100 -2 -200 -300 -4 -400 -6 1 Measured Error (deg) Phase Change (deg) 300 7 13 19 25 31 37 43 49 55 61 67 73 79 Cavity In the spring 2006, 11 cavities had to be either turned off or have their amplitudes reduced for safe operation, 1 cavity was returned to operation The fault recovery scheme was applied “all at once” Phase scan spot checks indicate the scaling was within 4 degrees No detectable change in beam loss OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 22 Application of the Cavity Fault Recovery Scheme (II) 30 20 -500 10 -1000 0 -1500 -10 -2000 -20 -2500 -30 D Amplitude (MV/m) D Phase (deg) 0 Phase Change Amplitude Change 1 6 11 16 21 26 31 36 41 46 51 56 61 66 71 76 81 cavity In April 2007 the SCL was lowered from 4.2K to 2 K to facilitate 30 Hz operation. About 20 cavity amplitudes changed. The fault recovery scheme restored beam to the previous loss state. OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 23 Some SNS Linac Beam Performance Measures (through the entire linac) Energy (GeV) Rep Rate (Hz) Pulse Length (mSec) Beam Current * (mA) Beam Power (MW) Design Highest Ever (Individual) Highest Beam Power (Simultaneous) 1.0 60 1 1.01 60 1 0.88 30 0.55 26 20 13 1.5 0.18 0.18 * Time average including ~ 30% chopping OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 24 Energy Jitter – Pulse to Pulse 160 140 120 100 80 60 40 20 0 •Average phase diff = 112.63 deg : average energy = 866.02 MeV •RMS phase diff = 0.278 : energy jitter = 0.15 MeV 11 3 11 3. 3 11 3. 6 11 3. 9 ~ 0.4 MeV RMS jitter, •Max phase diff = 1.2 deg out of 886 MeV: energy jitter = 0.66 MeV 11 1. 5 11 1. 8 11 2. 1 11 2. 4 11 2. 7 Frequency BPM 27-25 Delta phi (deg) Energy control pulse-to-pulse nor within a pulse has not been a concern OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 25 Power Ramp-up Progress ISIS Power Record We are starting to get to real beam power levels OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 26 Beam Loss / Activation Contact / 30 cm dose in mRem/hr SCL has a large aperture and should easily transport beam This past summer we observed higher than expected activation levels in some warm sections (with quadrupoles) between the cryomodules – not expected based on loss monitor levels Not well understood, possibly longitudinal loss Purposeful detuning of the warm linac results in loss patterns with similar shape as the activation patterns “Dark current” from the ion source ? OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 27 SRF Test Facility RF/Coupler processing Test Cave Cryomodule Assembly VTA Cryomodule Assembly Chemistry Class 10 Class 10,000 Class 100 Mezzanine (lab space) OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 28 Summary We have been operating the SNS SCL for ~ 2 years with beam Generally it is quite forgiving Run with many cavities off / entire cryo-module removed / gradients far from design Need tools to adapt to rapidly changing conditions Cavities are like individuals – each has it’s own set of difficulties / strengths OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 29 Normal Conducting Linac CCL Systems designed and built by Los Alamos 402.5 MHz DTL was designed and built by Los Alamos 805 MHz CCL accelerates beam to 186 MeV Six tanks accelerate beam to 87 MeV System consists of 48 accelerating segments, 48 quadrupoles, 32 steering magnets and diagnostics System includes 210 drift tubes, transverse focusing via PM quads, 24 dipole correctors, and associated beam diagnostics OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 30 The Beam Power Ramp Up Goal We need to ramp to full design power, at full final reliability with decreasing beam study time by Oct. 2009 OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 31 Cavity Fault Impact on Beam Arrival Times for a Proton Linac Arrival Time: Cavity: Arrival Time: Cavity: Proton beams for high power applications (< 10 GeV) are not fully relativistic and the velocity is energy dependent If a cavity fails, the beam arrives at downstream cavities later For SNS if an upstream cavity fails, the arrival time at downstream cavities can be delayed up to 5 nsec This is over 1000 degrees phase setting of an 805 MHz RF cavity Our goal is to set the cavity to within ~ 1 degree OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 32 50 30 10 -10 -30 -50 -70 -90 … … -110 0.52 Beam-RF Phase (deg) Longitudinal Acceleration Modeling (Application Programs – Online Model) Medium-Beta (g=0.61) 0.57 0.62 Parmila 0.67 0.72 OLM Drift-kick-drift method Assume design field profiles throughout the cavity Transit Time Factor is calculated at each gap, based on a fit of Superfish calculations The beam sees a large phase slip from gap to gap as it traverses the cavity OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 33 Test of the Cavity Recovery Method – Single Cavity “Failure” Turn off cavity 7 Turned off cavity 7, rescaled the downstream cavity phase setpoints Downstream cavity phase setpoints changed > 1000 degrees A beam measurement check with the last cavity showed it was within 1 degree of the scaled prediction OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 34 Phase Scaling Error (deg) Expected Errors from the Scaling Method (I) Beam Energy (MeV) Uncertainty in the cavity positions leads to errors in the predicted change in phase Relative cavity positions are known to a few mm, so < 1 degree error is expected from this uncertainty OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 35 Phase Scaling Error (deg) Expected Errors from the Scaling Method (II) Beam Energy (MeV) Uncertainty in the energy gain/cavity results in errors in the predicted change in cavity phase Energy gain is known to within a few hundred keV, so the error from this uncertainty is 1-2 degrees OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 36 Cavity Fault Recovery Scheme at SNS Additional applications of the cavity recovery scheme Missing cryo-module tests to evaluate the impact on beam loss from removing entire cryo-modules from service for repairs. Recovery from a control system failure that resulted in 3 broken cavity tuners. While intended for use in recovering from a single cavity failure, the scheme has been used more often to recover from more severe situations Usually takes days to assess the situation, minutes to apply the recovery scheme Previously took days to setup the cavities (now ~ 1 shift) with beam based measurement techniques This technique is considered a “standard practice” by now at SNS Future improvements may include a more automated invocation OAK RIDGE NATIONAL LABORATORY U. S. DEPARTMENT OF ENERGY 37