Current Subcontractor and Supplier Miller Act and State Payment Bond Claim Issues: Avoiding the Common Pitfalls to a Subcontractor or Material Supplier’s.
Download ReportTranscript Current Subcontractor and Supplier Miller Act and State Payment Bond Claim Issues: Avoiding the Common Pitfalls to a Subcontractor or Material Supplier’s.
Current Subcontractor and Supplier Miller Act and State Payment Bond Claim Issues: Avoiding the Common Pitfalls to a Subcontractor or Material Supplier’s Recovery on Federal and State Projects © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 1 The Miller Act governs performance and payment bonds and claims upon such bonds on federal construction projects "Little Miller Acts" are state statutes, based upon the federal Miller Act, requiring prime contractors on state construction projects to post bonds State courts generally interpret Little Miller Acts in conformance with federal statute with local variations Some state statutes have stronger payment protection than Miller Act o See, e.g., Sloan Constr. Corp. v. Southco Grassing, Inc., 659 S.E.2d 158 (S.C. 2008) (where original payment bond surety became insolvent and prime contractor failed to respond to SCDOT’s request for replacement bond, SCDOT liable to subcontractor) State-By-State Review of Public Project Payment Bond Laws by NACM: o Reprinted with permission by James D. Fullerton at http://www.fullertonlaw.com/docs/appendices/50_state_survey_of_payment_ bond_rights.pdf © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 2 Proper Claimants Labor and Material Covered Notices Required Time for Filing Suit Amount of Bond Required Contracts Excluded Penalties for Not Providing Bond © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 3 Miller and Little Miller Acts: Proper Claimants © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 4 Although the Miller Act payment bond is intended to protect "all persons supplying labor and material in carrying out the work provided for in the contract," the parties that may assert a claim under it are limited to those who have direct relationship with prime or first-tier subcontractor: o o o o Second-tier material supplier who supplied a first-tier material supplier (and not first-tier subcontractor) cannot recover under Miller Act payment bond. o First-tier subcontractors; i.e., subcontractors who contract directly with prime contractor Second-tier subcontractors; i.e., subcontractors who contract with a first-tier subcontractor First-tier material suppliers; i.e., suppliers who contracted directly with prime contractor Second-tier material suppliers who contract with a first-tier subcontractor City of Kansas City, MO ex rel. Lafarge North America Inc. v. Ace Pipe Cleaning, Inc., 349 S.W.3d 399(Mo. Ct. App. W.D. 2011) (holding that Missouri's Little Miller Act extends bond protection only to those providing labor and material to first-tier subcontractor) Many Little Miller Acts do not limit subcontractor tiers (e.g., Washington, California, North Carolina, New Mexico, Georgia, Wyoming) o Tom Barrow Co. v. St. Paul Fire & Marine Ins. Co., 205 Ga. App. 10, 11 (1992) (holding Georgia’s Little Miller Act permits supplier to recover from second-tier subcontractor) © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 5 Third-tier and more remote subcontractors and material suppliers cannot recover against the Miller Act and many Little Miller Act bonds. Beware of Straw Parties and Sham Transactions o o o o o Glen Falls Insurance Co. v. Newton Lumber & Manufacturing Co., 388 F.2d 66 (10th Cir. 1967) (prime contractor contracted with a relative that performed no work in order to limit Miller Act payment bond exposure) United States ex rel. M.A. Bruder & Sons, Inc. v. Aetna Casualty & Surety Co., 480 F. Supp. 659 (D.D.C. 1979) (court disregarded an entity in the contracting framework that was an alter ego of subcontractor and held that a material supplier to that straw party was entitled to make a claim on the bond). U.S. v. Southwind Const. Services, LLC, 510 Fed. Appx. 688 (10th Cir. 2013) (refusing to collapse the distinction between the prime contractor and its affiliated subcontractor that would have given Miller Act payment bond recourse to a second tier unpaid equipment rental company). Ragan v. Tri-County Excavating, Inc., 62 F.3d 501 (3d. Cir 1995) (court pierced the corporate veil and found subcontractor was a dummy of the prime contractor, allowing claimant to recover on payment bond) U.S. ex rel. Johnson Pugh Mech., Inc v. Landmark Constr. Corp., 318 F.Supp.2d 1057 , 2073 (D. Colo. 2004) (setting out 10 factors to determine whether subcontractor was alter ego or joint venturer of prime contractor) © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 6 Distinction between “supplier” and “subcontractor” is critical for remote suppliers Landmark case: Clifford F. MacEvoy Co. v. U.S. for Use and Benefit of Calvin Tomkins Co., 322 U.S. 102, 110-111 (1944) o Has the party assumed a “significant and definable” part of the construction project? If so, party is a “subcontractor.” Two tests have developed for the subcontractor/material supplier distinction: o o the on-site work test (e.g., Louisiana and Indiana); and the substantial relationship test (federal and majority of states) – Factors to weigh when determining subcontractor/supplier relationship set forth in U.S. ex rel. Conveyor Rental v. Aetna, 981 F.2d 448, 451–452 (9th Cir.1992) – Extremely fact-sensitive analysis © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 7 Factors in favor of “subcontractor”: 1) 2) 3) 4) 5) 6) 7) 8) 9) 10) 11) 12) 13) the product supplied is custom fabricated; the product supplied is a complex integrated system; a close financial interrelationship exists between the companies; a continuing relationship exists with the prime contractor as evidenced by the requirement of shop drawing approval by prime contractor or the requirement that the supplier's representative be on the job site; the supplier is required to perform on site; there is a contract for labor in addition to materials; the term “subcontractor” is used in the agreement; the materials supplied do not come from existing inventory; the supplier's contract constitutes a substantial portion of the prime contract; the supplier is required to furnish all the material of a particular type; the supplier is required to post performance bond; there is a backcharge for cost of correcting supplier's mistakes; and there is system of progressive or proportionate fee payment. © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 8 Factors in favor of “material supplier”: 1) 2) 3) 4) 5) 6) a purchase order form is used by the parties (de minimus consideration); the materials come from preexisting inventory; the item supplied is relatively simple in nature; the contract is a small percentage of the total construction cost; sales tax is included in the contract price; and Fixed payment requirement (e.g., “full payment within 90 days”) © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 9 General principles: o “Subcontractor” does not require performance of on-site work so long as custom work (e.g., fabrication of pipe, millwork, doors, windows, curtainwall and structural steel) performed per detailed requirements of the contract plans and specifications – Just a “material supplier”… U.S. ex rel. E&H Steel Corp. v. C. Pyramid Enterprises, Inc., 2006 WL 2570849 (D.N.J. 2006) (analyzing "how much does a steel fabricator have to do to qualify as a subcontractor under the Miller Act," and concluding that the steel fabricator was a mere "materialman" outside the coverage of the bond). Berlin Steel Const. Co. v. Salah & Pecci Leasing Co., Inc., 5 A.3d 608 (Del. 2010) (denying payment bond claim of crane owner who leased a crane to a crane operator who in turn contracted with a steel erection company who contracted with a prime contractor) Farwest Steel Corp. v. Mainline Metal Works, Inc., 48 Wash. App. 719 (Div. 1 1987) (holding that a supplier was too remote under Washington Little Miller Act since first-tier party deemed “materiaman;” even though it furnished custom fabricated goods, contract was less than 1% of prime contract and performed no on-site work on site was a "materialman”). E. Indus. Mktg. Inc. v. Desco Elec. Supply, 651 F. Supp. 140 (W.D. Pa. 1986) (supplier of custom conduit not subcontractor because “coating, cutting and threading operations” did not constitute custom manufacturing) © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 10 General principles: (cont’d) o “Subcontractor” does not require performance of on-site work so long as custom work (e.g., fabrication of pipe, millwork, doors, windows, curtainwall and structural steel) performed per detailed requirements of the contract plans and specifications (cont’d) – Yes, a “subcontractor”… Preussag Intern. Steel Corp. v. March-Westin Co., 221 W. Va. 472 (2007) (holding that a steel fabricator was a "subcontractor" under West Virginia law and following the general rule in the MacEvoy case). Eggers Industries v. Flintco, Inc., 201 Cal. App. 4th 536 (2011) (following the MacEvoy determination that a manufacturer of custom-made doors was a “subcontractor” under Little Miller Act even though all custom work was subcontracted to another entity; essential factor was what manufacturer “agreed” to do) Barton Malow Co. v. Metro Mfg., Inc., 214 Ga. App. 56 (1994) (same result involving fabricated pipe under Georgia "Little Miller" Act); U.S. ex rel. Capital Computer Group, LLC v. Gray Ins. Co., 453 Fed. Appx. 905 (11th Cir. 2011) (holding that a person who took a subcontract from a prime contractor and then subcontracted all of the work other than provision of insurance and indemnification of the prime contractor was nevertheless a “subcontractor” for Miller Act payment bond rights) Aquatic Plant Mgmt., Inc. v. Paramount Eng'g, Inc., 977 So. 2d 600, 602 (Fla. Dist. Ct. App. 2007) (firm providing specially fabricated plants deemed “subcontractor” though material never incorporated into wetlands project) © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 11 Substantial relationship test = “Subcontractor” o F.D. Rich Co. v. Industrial Lumber Co., 417 U.S. 116 (1974) – Court applied “substantial relationship test” and determined party claimant furnished material to was a “subcontractor” where it was clearly intertwined with the prime contractor, had a long term working relationship with the prime contractor, and had been awarded both a supply and installation contract in a particular federal project. o U.S. ex rel. E&H Steel Corp. v. C. Pyramid Enters., Inc., 509 F. 3d 184 (3d Cir. 2007) – Court held that a supplier acted as a “subcontractor” for Miller Act purposes when it supplied pre-fabricated structural steel pursuant to a purchase order, prepared shop drawings and erection drawings, designed connectors, and performed design-assist engineering amounting to 7.8% of the prime contract. o LaGrand Steel Products v. A.S.C. Constructors, 108 Idaho 817 (Ct. App. 1985) – Court found that steel fabricator was a subcontractor for the purpose of Idaho Little Miller Act. Relying on substantial relationship test, court determined that: (1) subcontractor provided custom fabrication of steel; (2) work was not unduly complicated and performed exclusively off-site; and (3) contract involved no erection or supervision thereof. BUT, contract was $1 million and constituted 10% of the total prime contract and prime contractor required personal performance guarantees. © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 12 Substantial relationship test = “Material Supplier” o U.S. v. Ellis Const. Co., 398 F. Supp. 719 (E.D. Tenn. 1975) – Party determined to be material supplier who custom manufactured steel items for the project and whose contribution to the total cost of improvement was less than 9% o Aetna v. Gibson Steel Co., 382 F.2d 615 (5th Cir. 1967) – Party determined to be material supplier when it fabricated steel items such as stairs, ladders, and trench covers and frames for federal project where: (1) contract was 2% of total project; and (2) party did not have a sufficiently important relationship with the prime contractor because there was no on-site work (either installation or supervision). © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 13 1. o o Are you in privity of contract with the prime contractor? If not, who are you in privity of contract with? Please provide a copy of your contract or purchase order. 2. Describe the nature and scope of your subcontract, including the type and quantity of labor and/or materials you are furnishing under your subcontract. o o o o Are you performing any on-site work (e.g., erection, installation, supervision, etc.)? Describe. Are you performing any 0ff-site work (e.g., fabrication, shop drawings)? Describe. Are you supplying stock items or specially manufactured materials to meet project specifications? Describe. Are there others supplying similar goods for the project, or are you the sole supplier of these types of goods? © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 14 3. What is the total contract price of your subcontract? 4. What is the total contract price of the project? 5. Are you giving any performance guarantees or bonds to the prime contractor? 6. How are you being paid? Monthly payment applications based upon progress or fixed payment? 7. Are you including sales tax in your invoice? 8. Are you referred to as “subcontractor” in your the supplier is required to post performance bond; 9. Is retention being withheld from your progress payments? 10. Does your contract allow the prime contractor to backcharge you for corrections? © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 15 Miller and Little Miller Acts: Labor and Materials Covered © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 16 Types of Labor and Material Covered o o o Labor and materials “incorporated into,” “used” or “consumed” in performance of work “Laborers” include engineers, architect, surveyors and others providing incidental services. (See AIA A312-1984, Standard Form Bond, ¶ 15.1) Labor includes “field supervisors” – U.S. for Use and Benefit of Olson v. W.H. Cates Const. Co., Inc., 972 F.2d 987, 990 (8th Cir. 1992) (holding that a contractor's unpaid project manager who provided supervisory services on site was a "laborer" within the protection of the Miller Act, even though not performing a job listed in the labor) – CM firms generally not covered – Employee leasing services generally not covered Tri-State Employment Services, Inc. v. Mountbatten Sur. Co., Inc., 99 N.Y.2d 476 (2003) (a "employee leasing service" had no right to recover for its unpaid labor under a public contractor's payment bond because it was a mere "provider of administrative and human resources services" that exercise no direction or control over the work performed by its "employees" on site) – Executive home office positions (above level of “field supervision”) not covered © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 17 Types of Labor and Material Covered (Cont’d) o Payment bond liability for “indirect wage liabilities” – Prevailing wage penalties Board v. Eurostyle, Inc., 998 S.W.2d 810 (Mo. Ct. App. S.D. 1999) (surety was held liable for double wage penalty imposed under Missouri's prevailing wage statute); but see North Marion School Dist. #15 v. Acstar Ins. Co., 205 Or. App. 484, 136 P.3d 42 (2006) (payment bond surety not liable to unpaid laborers for statutory damages and penalties for late payment of wages) – Unpaid withheld taxes Island Ins. Co., Ltd. v. Hawaiian Foliage & Landscape, Inc., 288 F.3d 1161 (9th Cir. 2002) (payment bond surety liable to federal and state governments for unpaid employment taxes owed by the defaulting bond principal because, even though those governmental bodies were not named obligees in the bond, because they clearly were intended third-party beneficiaries) – Unpaid withheld fringe benefit contributions Forsberg v. Bovis Lend Lease, Inc., 2008 UT App 146 (Utah Ct. App. 2008) (allowing recovery under a payment bond for unpaid fringe benefits owed to union-related trusts as constituting payment for “labor” under the applicable payment bond statute); Hartford Fire Ins. Co. v. Trustees of Const. Industry, 125 Nev. 16, 208 P.3d 884 (2009) (allowing recovery of unpaid fringe benefits because the trust “stood in the shoes” of the workers); but see Trustees Of Sheet Metal Workers' Local Union No. 17 v. U.S. Fire Ins. Co. (2009) (denying recovery against a payment bond for unpaid union benefit contributions because the bond provided coverage only for providers of labor and material who had a direct contract with the contractor). ERISA generally not interpreted to preclude fringe benefit claims. © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 18 Types of Labor and Material Covered (Cont’d) o o Fuel, tires, parts, tools, form work, transportation, food and lodging Reasonable value of rental equipment generally covered – Larson v. Martin, 2006 WL 3437602 (D.N.D. 2006), aff'd, 532 F.3d 724 (8th Cir. 2008) (subcontractor not permitted to recover payment from surety for idle equipment and operators on project site before execution of the bonds). – Payment bond sureties scrutinize lease-to-own arrangements. See King Consultants, Inc. v. Bee Equipment Sales, Inc., 2003 WL 22351805 (Tex. App. Fort Worth 2003) (rejecting equipment rental claim on bond, where the equipment was leased under a "lease with purchase option" construed by the court to be a conditional sale of capital equipment not covered by the payment bond). – Most widely used equipment rate manuals for contractor-owned equipment are (1) Construction Equipment Ownership and Operating Expense Schedule published by the United States Army Corps of Engineers and (2) Rental Rate Bluebook published privately by Data Quest Incorporated o Insurance premiums generally not covered. – Some Little Miller Acts expressly provide coverage for insurance premiums. See Minn. Stat. Ann. § 574.26 (2000); Iowa Code § 573.1 © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 19 Types of Labor and Material Covered (Cont’d) o Lost Profits for First-Tier Subcontractors – Lost profits for breach of contract and other foreseeable economic damages flowing from prime contractor’s breach? Maybe… See Taylor Const. Inc. v. ABT Service Corp., Inc., 163 F.3d 1119 (9th Cir. 1998) (subcontractor, under a cost-plus guaranteed maximum price subcontract that contained a clause granting 50% of savings to the subcontractor as additional profit, could recover the unpaid savings from the payment bond surety) Downey, Inc. v. Bradley Center Corp., 188 Wis. 2d 435, 524 N.W.2d 915 (Ct. App. 1994) (lost profits suffered on unrelated project were recoverable under common-law payment bond for the reason that consequential damages resulting from delayed performance were reasonably foreseeable). But see Sloan Const. Co. v. American Renovation and Const. Co., 313 F. Supp. 2d 24 (D.P.R. 2004) (a Miller Act payment bond surety was not liable for lost profit damages arising out of the alleged breach on an obligation to award a subcontract, because a Miller Act payment bond provided coverage only for persons owed payment for having furnished labor and materials); see also Gals, Inc. v. Gemma Const. Co., Inc., 784 N.Y.S.2d 51 (1st Dep't 2004) (language of payment bond covered only labor performed at the site and materials and supplies actually used at the site, and did not cover lost profits). – Lost profits not recoverable by Second-Tier Subcontractors and Suppliers See Vaughn Excavating and Const., Inc. v. P.S. Cook Co., 981 P.2d 485 (Wyo. 1999) (payment bond surety under state "Little Miller" Act held not liable to supplier for payment of lost profits and contractual economic damages— a 10% late payment fee, 2% monthly interest and attorney's fees) © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 20 Types of Labor and Material Covered (Cont’d) o Delay and Acceleration Damages Generally Recoverable – Compensable delay generally deemed to be part of true cost of work Consolidated Elec. & Mechanicals, Inc. v. Biggs General Contracting, Inc., 167 F.3d 432, 434-435 (8th Cir. 1999) (Miller Act payment bond surety liable for subcontractor's delay damages caused by government because the contractor and surety could pursue recovery from the government); see also Metric Elec., Inc. v. Enviroserve, Inc., 301 F.Supp.2d 56 (D. Mass. 2003). U.S. for Use and Benefit of T.M.S. Mechanical Contractors, Inc. v. Millers Mut. Fire Ins. Co. of Texas, 942 F.2d 946 (5th Cir. 1991) (subcontractor allowed to recover its increased labor and material costs due to contractor's delay) Lighting & Power Services, Inc. v. Roberts, 354 F.3d 817, 823 (8th Cir. 2004) (allowing a subcontractor to recover delay damages using the "total cost" damage measure and recognizing that under the Miller Act, a subcontractor can recover additional expenses incurred because of delay regardless of the fault of the general contractor). Lexicon, Inc. v. Safeco Ins. Co. of America, Inc., 436 F.3d 662, 2006 FED App. 0053P (6th Cir. 2006) (surety held liable for increased labor and material costs due to delay because costs were necessary for contract completion) See also Fisk Elec. Co. v. Travelers Cas. and Sur. Co., 2009 WL 196032 (S.D. Fla. 2009) (recognizing the right of a subcontractor to recover costs incurred due to delay attributable to issuance of thousands of changes). – Time-related claims for acceleration generally recoverable Tremack Co. v. Homestead Paving Co., 582 So. 2d 26 (Fla. Dist. Ct. App. 3d Dist. 1991) (payment bond surety liable for costs due to acceleration of the project schedule). But see Samuel Grossi & Sons, Inc. v. U.S. Fidelity & Guar. Co., 2006 WL 3307465 (Pa. C.P. 2006) (subcontractor's acceleration costs constitute delay damages and thus are not recoverable under a payment bond). © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 21 Types of Labor and Material Covered (Cont’d) o Tort damages due to prime contractor’s conduct generally not recoverable – Rarely, bond expressly covers damages caused by negligence – Surety not liable for punitive damages against prime contractor C & I Steel, LLC v. Travelers Cas. and Sur. Co. Of America, 70 Mass. App. Ct. 653 (2007) (holding that a payment bond surety was not liable for bad faith punitive damages awarded by an arbitrator against its bond principal). – Bad-faith claims made directly against surety, not under bond U.S. ex rel. SimplexGrinnell, LP v. Aegis Ins. Co., 2009 WL 90233 (M.D. Pa. 2009) (holding that a payment bond surety was not liable under Pennsylvania's bad faith statute because a bond is not an "insurance policy") Missouri Dept. Of Transp., ex rel. PR Developers, Inc. v. Safeco Ins. Co. Of America, 2002 WL 1968264 (Mo. Ct. App. E.D. 2002) (payment bond surety which refused to pay a delay claim of $1.6 million in deference to its principal, was not liable for punitive damages because it was not guilty of "vexatious refusal to pay"). © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 22 Types of Labor and Material Covered (Cont’d) o Prejudgment interest generally allowable – Federal Miller Act silent (“sums justly due”), but most circuits approve – Some Little Miller Acts expressly provide interest See, e.g., Cal. Civ. Code § 3250; Colo. Rev. Stat. Ann. § 38-26-06; Conn. Gen. Stat. Ann. § 49-42(a); Or. Rev. Stat. 742.061; Roman Mosaic and Tile Co. v. Thomas P. Carney, Inc., 1999 PA Super 73 (Pa. Super. Ct. 1999) (prejudgment interest awarded on subcontractor claim against payment bond surety); but see Vaughn Excavating and Const., Inc. v. P.S. Cook Co., 981 P.2d 485 (Wyo. 1999) (payment bond did not cover supplier's claim for interest) – Legal rate of interest only; no contractual service charges. e.g., New York, Wyoming, Pennsylvania, Colorado – Federal and State Prompt Payment Penalties Washington Intern. Ins. Co. v. Superior Court (G.K. Backlund, Inc.), 62 Cal. App. 4th 981 (1998) (payment bond surety liable for interest penalty under California Prompt Payment Act where statutory provisions of Prompt Payment Act were construed to be incorporated into the statutory bond); but see U.S. ex rel. Virginia Beach Mechanical Services, Inc. v. SAMCO Const. Co., 39 F. Supp. 2d 661 (E.D. Va. 1999) (holding that the Prompt Payment Act does not provide an independent basis for recovery under Miller Act bond); – Surety liability generally runs from date of demand for payment upon surety and surety’s refusal to pay, rather than date payment originally due But see John W. Egan Co., Inc. v. Major Const. Management Corp., 46 Mass. App. Ct. 643 (1999) (holding prejudgment due from earlier date of contractor default). © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 23 Types of Labor and Material Covered (Cont’d) o Attorney’s Fees – Not expressly recoverable under Miller Act F. D. Rich Co., Inc. v. U. S. for Use of Indus. Lumber Co., Inc., 417 U.S. 116 (1974) – Fees may be recovered if there is fee provision between claimant and prime contractor U.S. ex rel. Maddux Supply Co. v. St. Paul Fire & Marine Ins. Co., 86 F.3d 332, 336 (4th Cir. 1996) (attorney's fees recoverable under Miller Act payment bond where a contract between the bond principal and claimant provides for recovery of attorney's fees) U.S. ex rel. SCCB, Inc. v. P. Browne & Associates, Inc., 751 F. Supp. 2d 813 (M.D. N.C. 2010) (granting attorney's fees to a Miller Act claimant where the sub-subcontract authorized recovery of attorney's fees); U.S. ex rel. Thyssenkrupp Safway, Inc. v. Tessa Structures, LLC, 2011 WL 1627311 (E.D. Va. 2011) (same result). – Many Little Miller Acts permit fee awards See, e.g., Ariz. Rev. Stat. Ann. § 34-222-F; Cal. Civ. Code §§ 3248(b), 3250; Conn. Gen. Stat. Ann. § 49-42(a); Fla. Stat. Ann. §§ 255.05, 627.756; La. Rev. Stat. Ann. § 38:2246; Mass. Gen. Laws Ann. ch. 49, § 29; Minn. Stat. Ann. § 574.26; Miss. Code Ann. § 31-5-57; N.Y. State Fin. Law § 137.4(c); Or. Rev. Stat. § 742.061; Tex. Gov't Code Ann. § 2253.074; Utah Code Ann. § 63-56-38(5). See also In re Grubbs Const. Co., 306 B.R. 372 (Bankr. M.D. Fla. 2004) (allowing attorney’s fees to a payment bond claimant under a Florida statute permitting "the prevailing party" to recover reasonable attorney’s fees in any action brought to enforce a claim against a payment bond) © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 24 Types of Labor and Material Covered (Cont’d) o o Offsite materials covered Diverted materials covered – Claimant must only prove material furnished in “the good faith belief” or “reasonable expectation” material intended for project. U.S. ex rel. Thyssenkrupp Safway, Inc. v. Tessa Structures, LLC, 2011 WL 1627311 (E.D. Va. 2011) (upholding the claim of an unpaid supplier who reasonably believed in good faith that its materials were incorporated into or used on the bonded project). Advanced Kiosks v. LM Holdings, LLC, 25 Mass. L. Rptr. 357, 2009 WL 1448948 (Mass. Super. Ct. 2009) (holding that a product supplier could recover under a payment bond by proving that his product had been “furnished by virtue of a contract,” without proving that the product actually was incorporated into the structure). State ex rel. Solsbury Hill, LLC v. Liberty Mut. Ins. Co., 2012-NMCA-032, 273 P.3d 1 (N.M. Ct. App. 2011) (requiring a supplier seeking recovery under the New Mexico Little Miller Act to prove only that it had a reasonable good faith belief, as reflected in its invoices, that materials it supplied were used in the prosecution of the work under the bonded contract). Bethlehem Steel Corp. v. U.S. Fidelity and Guar. Co., 193 A.D.2d 1058, 598 N.Y.S.2d 873 (4th Dep't 1993) (holding steel supplier needed to establish only that it provided "material used or reasonably required for use in the performance of" the prime construction contract.) © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 25 Types of Labor and Material Covered (Cont’d) o Diverted materials OK (Cont’d) – Claimant must only prove material furnished in “the good faith belief” or “reasonable expectation” material intended for project. U.S. for Use and Benefit of Dragone Bros. Inc. v. Moniaros Contracting Corp., 882 F. Supp. 1267, 40 Cont. Cas. Fed. (CCH) ¶76779 (E.D. N.Y. 1995) (good faith delivery to site sufficient). But see Trestle & Tower Engineering, Inc. v. Star Ins. Co., 13 F. Supp. 2d 1166 (D. Kan. 1998) (materials or supplies stolen or converted after delivery not recoverable under payment bond). Farmer's Union Cent. Exchange, Inc. v. Reliance Ins. Co., 675 F. Supp. 1534 (D.N.D. 1987) (suppliers of bulk asphaltic oil products to central locations from which the products were indiscriminately used in performance of both bonded and unbonded contracts, were unable to furnish evidence that any of the products were used solely on a given bonded project and thus were unable to recover from the payment bond surety). Graham Architectural Products Corp. v. St. Paul Mercury Ins. Co., 303 F. Supp. 2d 274 (E.D. N.Y. 2004) (though court recognized liberal “good faith” standard, bond claim of window supplier/fabricator denied when supplier/fabricator withheld specialty manufactured goods absent COD payment and surety bought from another source) © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 26 Miller and Little Miller Acts: Notice Requirements © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 27 Little Miller Act notice requirements generally conform to Miller Act with some local variations. Common law reflects both “strict notice” requirements, with trend to favor enforcement unless improper notice is “prejudicial” Notice must be given by claimant without privity with prime contractor within 90 days from the last date claimant furnished labor or materials. o Timing of notice strictly construed – See Brer-Four Transp. Corp. v. Zurich American Ins. Co., 913 N.Y.S.2d 109 (2d Dep't 2010) (denying a subsubcontractor's statutory payment bond claim due to failure to give timely required notice) – Precision Development of Chappaqua, Inc. v. Hartford Fire Ins. Co., 809 N.Y.S.2d 483 (Sup 2005) (denying a secondtier subcontractor's bond claim because the subcontractor had failed to give the bond principal notice of its claims within the 120-day notice period allowed by statute) o Notice must be received (not just mailed) within 90-day period. – See U.S. for Use and Ben. of B & R, Inc. v. Donald Lane Const., 19 F. Supp. 2d 217 (D. Del. 1998) (mailing of notice within 90 days insufficient); See also Pepperburn's Insulation, Inc. v. Artco Corp., 970 F.2d 1340 (4th Cir. 1992) © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 28 Notice must be given by claimant without privity with prime contractor within 90 days from the last date claimant furnished labor or materials (cont’d) o Little Miller Acts generally require 90 day notice, but vary from 60 to 180 days – Electrical Specialties, Inc. v. Siemens Building Technologies, Inc., 837 N.E.2d 1052 (Ind. Ct. App. 2005) (construing the Indiana "Little Miller" Act to require filing of claim within 60 days after "the last material is provided or the last labor or service is performed" by anyone on the project) – Minnesota, New York, Connecticut and North Carolina = 180 days o Some states require two notices from lower-tier claimants – See, e.g., Nev. Rev. Stat. § 339.035 (requiring first notice within 30 days after furnishing first item of labor or material, and a second notice 90 days after furnishing the last item of labor or material). – See also W.T. Andrew Co., Inc. v. Mid-State Sur. Corp., 221 Mich. App. 438 (1998) (holding that under Michigan's "Little Miller" Act, a supplier required to provide two notices—the first notice 30 days after furnishing the first item of labor or material and the second notice within 90 days after furnishing the last labor or materials—and a supplier that failed to provide the first notice was precluded from pursuing a statutory payment bond claim). o What happens if claimant performs work (or has a series of deliveries of materials) more than 90 days apart? © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 29 Notice must be given by claimant without privity with prime contractor within 90 days from the last date claimant furnished labor or materials (cont’d) o Notice period not extended by performance of repair/warranty work – U.S. For Use and Benefit of Rocking D&R Ranch, Inc. v. James Talcott Const., Inc., 2007 WL 4334170 (D. Mont. 2007) (concluding that a payment bond claimant's HVAC system balancing work was part of the original contract rather than repair work, and ruling the 90-day notice deadline ran from the date that the balancing work was completed) o o o Notice period not extended by furnishing items not required by contract Notice period not extended by furnishing items not included in claim Early claim notice may generally be given, but limited to unpaid furnished work Notice must state amount claimed with “substantial accuracy” and the name of the party to whom labor or materials was provided – Safety Signs, LLC v. Niles-Wiese Const. Co., Inc., 820 N.W.2d 854 (Minn. Ct. App. 2012), aff'd, 840 N.W.2d 34 (Minn. 2013) (dismissing a subcontractor's statutory payment bond claim, where notice of claim failed to comply with strict statutory requirements) – CTI/DC, Inc. v. Selective Ins. Co. of America, 271 F. Supp. 2d 758 (D. Md. 2003), aff'd, 392 F.3d 114 (4th Cir. 2004) (supplier's demand letter to contractor did not constitute required written notice) – Bridgeport Inc. v. Rinker Materials Corp., 849 So. 2d 1193 (Fla. Dist. Ct. App. 4th Dist. 2003) (lien notice did not constitute proper payment bond claim notice) © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 30 Notice must be served “by any means that provides written, third-party verification of delivery to the contractor.” o Oral notice insufficent. – Pittsburgh Builder Supply Co. v. Westmoreland Const. Co., 702 F. Supp. 106 (W.D. Pa. 1989) (holding that actual, but not written, notice was insufficient to satisfy the 90-day notice requirement). o Letter via U.S. Mail insufficent because no “third party verification.” – U.S. ex rel. Viking Disposal Corp. v. W. Sur. Co., 2007 WL 5287926 (W.D. Wis. 2007) o E-mail notice deemed sufficient. – United States v. Fid. & Deposit Co. of Maryland, 2013 WL 4829051 (D. Md. Sept. 9, 2013) (distributor forwarded copies of open invoices and demand letters sent to subcontractor to prime contractor via e-mail) Notice must expressly or impliedly inform prime contractor that claimant is looking to it or surety for payment. o Bowden v. U.S. for Use of Malloy (9th Cir. 1956) 239 F.2d 572, 577; see also U.S. ex rel. Bailey v. Freethy (9th Cir. 1972) 469 F.2d 1348, 1351 (following phrase: “[w]e would appreciate any help you may be able to give us in bringing this account up to date…” found in the supplier’s letter to prime contractor coupled with exact balance sufficient to infer that the supplier was looking to prime contractor for payment) © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 31 Miller and Little Miller Acts: Lawsuit to Enforce Bond Claim © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 32 Time for Filing Lawsuit on the Bond o o The statute of limitations contained in the Miller Act provides that a suit must be brought within one year after the last day on which materials were supplied or labor was performed. Little Miller Acts of 21 states and D.C. follow Miller Act; other states have shorter periods – See W. F. Hayward Co. v. Transamerica Ins. Co., 16 Cal. App. 4th 1101 (2d Dist. 1993) (holding statutory payment bond claim barred because suit was not commenced within six months after the 90-day period in which stop notices may be filed); Comtel Technologies, Inc. v. Paul H. Schwendener, Inc., 710 F. Supp. 2d 704 (N.D. Ill. 2010) (denying a subcontractor's payment bond claim because it was not commenced within six months after the owner's constructive acceptance of the project). o Some states commence limitation period from date of “final payment,” “date of completion,” date of “final settlement,” or date of “completion and acceptance” or date of issuance of COO – See Inner City Drywall Corp. v. Reliance Ins. Co. of New York, 694 N.Y.S.2d 31 (1st Dep't 1999) (one-year period commenced on date certificate of occupancy was issued and later remedial work did not toll the running of the time) © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 33 Time for Filing Lawsuit on the Bond (Cont’d) o Suit limitation period not extended by performance of repair/warranty work – U.S. ex rel. Miller Proctor Nickolas, Inc. v. Lumbermens Mut. Cas. Co., 2009 WL 962273 (E.D. N.Y. 2009) (holding that the one year period for commencing suit against the surety's payment bond was not tolled or restarted when the contractor returned to the project a year later to perform some training and testing at no cost to the owner following receipt of a list of complaints about the work) – Dunn Const., L.L.C. v. Gray Ins. Co., 2010 WL 231742 (W.D. La. 2010)) (holding that a subcontractor's one-year statutory period for commencing a payment bond suit was not tolled by work to correct punch list items); but see Arch Ins. Co. v. Precision Stone, Inc., 584 F.3d 33 (2d Cir. 2009) (holding that punch list work was part of the contractor's original undertaking, and thus the one year period for commencement of suit did not begin until that punch list work was completed) – See also U.S. v. Hartford Fire Ins. Co., 2010 WL 5026950 (E.D. Va. 2010) (holding that a claimant's replacement of defective sidewalk did not restart the Miller Act's one-year suit commencement limitation period). o Claimants must wait 90-days after they last furnished labor or material to the project before they can pursue a civil action against the Miller Act payment bond. 40 U.S.C. § 3133(b)(2). – The 90-day period is considered a reasonable amount of time for money to flow down from the owner and the general contractor to the subcontractor performing the work. © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 34 Miller and Little Miller Acts: Final Note about Payment Bonds © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 35 Wave of the future? o o o California Civil Code Section 8700 et seq. Owner must post project security for prime contractor when contract price is above $5 million (TI projects - $1 million+). Security may take 3 forms: – Bond of 15% to 25% of contract price – Irrevocable letter of credit of 15% - 25% of contract price – Escrow account with 15% - 25% of contract price ` © 2014 Gibbs Giden Locher Turner Senet & Wittbrodt LLP - All Rights Reserved 36