ERCOT Planning Horizon SOL Methodology Update Jeff Billo RPG December 7, 2012 Background • Per FAC-010-2.1 the Planning Authority (ERCOT) is to establish a documented SOL.

Download Report

Transcript ERCOT Planning Horizon SOL Methodology Update Jeff Billo RPG December 7, 2012 Background • Per FAC-010-2.1 the Planning Authority (ERCOT) is to establish a documented SOL.

ERCOT Planning Horizon SOL
Methodology Update
Jeff Billo
RPG
December 7, 2012
Background
• Per FAC-010-2.1 the Planning Authority (ERCOT) is to establish
a documented SOL methodology for its area
– ERCOT has issued a change to the methodology and
communicated that change per Requirement 4
• Why are we making these changes?
– Better align planning horizon SOL/ IROL methodology with TPL003 and PRC-023
– Learn from Southwest Event
• What changes are we making?
– General rewrite
– Add SOL/ IROL identification for steady-state cascade conditions
– Better define IROL identification
– Effective January 1, 2013
December 7, 2012
2
RPG
How does PRC-023 fit in?
• Defines transmission circuit relay loadability requirements for
Transmission Owners
• Provides 13 different methods for TOs to set their phase
protective relay settings
– Based on this we have used the conservative assumption that
transmission circuits loaded above 150% of their normal rating or
115% of their emergency (2-hour) rating will trip
– Assumption used for screening purposes only
• Limitation
– Applies only to facilities 200 kV or higher or 100-200 kV facilities
that the Planning Coordinator identifies as ‘critical to the
reliability of the BES’
December 7, 2012
3
RPG
PRC-023 Side Note
• Assume all 345 kV facilities set per PRC-023
• Run separate analysis to identify 138 kV circuits that will lead
to Cascade event if relays are set between 100% loading and
PRC-023 loadability requirements
– Report 138 kV circuits as ‘critical to reliability’ if meet this
criterion
December 7, 2012
4
RPG
How is ERCOT applying this?
• In ERCOT’s TPL standard analysis, no facilities should be
loaded above 100% for Category A or B contingencies
• If the analysis shows that for a Category C (multi-element)
contingency facilities will be loaded above 150% of the normal
rating or 115% of the emergency rating then we will assume
that the facility will trip
– If this causes a Cascade condition then ERCOT Planning will
investigate and take one or more of the following actions if the
Cascade condition is confirmed (per Category C Planning
process):
• Plan an upgrade
• Plan a Mitigation Plan (including RAPs and/or load shed)
December 7, 2012
5
RPG
How is ERCOT applying this?
• An SOL will be created when …
1. Manual system adjustment (switching, load shed, etc.) is
required in order to prevent cascading or voltage collapse;
2. A stability limit is identified;
3. Voltage stability margin is less than 5% for NERC Category B
contingencies or 2.5% for Category C contingencies; or
4. Post disturbance frequency is not within 59.4 Hz to 60.4 Hz
• The SOL will be classified as an IROL if the load loss (either via
manual load shed or as a consequence of the event) is greater
than four times 1% of the load in the case
• The IROL Tv will be defined as the lower of the relay trip setting
time delay or 30 minutes
December 7, 2012
6
RPG
Comments or Questions?
Send formal comments to:
[email protected]
December
March 12, 7,
2010
2012
7
RPG
Appendix
December
March 12, 7,
2010
2012
8
RPG
Quick Example on Facility Ratings (courtesy of WECC)
Load Shed (15 min)
Limit Exceedance = Go beyond limit
Emergency (2 hour)
Limit Violation = Exceed limit for a
time duration longer than
required mitigation time
Normal (continuous)
0 MVA
December 7, 2012
9
RPG
Quick Example on Facility Ratings
Load Shed (15 min)
Emergency (2 hour)
Normal (continuous)
Operate in this range all
you want. Nothing is
being exceeded, nothing
is being violated.
0 MVA
December 7, 2012
10
RPG
Quick Example on Facility Ratings
Load Shed (15 min)
Operate in this range for
no more than 2 hours:
Emergency (2 hour)
Normal (continuous)
1.
2.
You are exceeding
the normal rating.
You are violating the
limit if you operate
in this range for
longer than 2 hours.
0 MVA
December 7, 2012
11
RPG
Quick Example on Facility Ratings
Load Shed (15 min)
Operate in this range for no
more than 15 minutes:
Emergency (2 hour)
1.
Normal (continuous)
2.
You are exceeding the
emergency rating.
You are violating the
limit if you operate in
this range for longer
than 15 minutes.
0 MVA
December 7, 2012
12
RPG
Quick Example on Facility Ratings
You can’t operate over this
limit. If you do you may
damage equipment, cause
safety problems and/or trip
the facility
Load Shed (15 min)
Emergency (2 hour)
1.
Normal (continuous)
2.
You are exceeding the
load shed rating.
To exceed the highest
time-limit rating
established is to violate
the limit.
0 MVA
December 7, 2012
13
RPG
Quick Example on Facility Ratings
Normal (continuous) = Emergency (2 hour) = Load Shed (15 min)
If all ratings are the same,
you can never operate over
the normal limit. If you do
you may damage
equipment, cause safety
problems and/or trip the
facility
1.
0 MVA
2.
December 7, 2012
14
You are exceeding the
load shed rating.
To exceed the highest
time-limit rating
established is to violate
the limit.
RPG