Critique of NPV 04/29/08 Ch. 6 Merits and Flaws of NPV We will examine issues that are sometimes problematic for NPV Project Interactions –
Download
Report
Transcript Critique of NPV 04/29/08 Ch. 6 Merits and Flaws of NPV We will examine issues that are sometimes problematic for NPV Project Interactions –
Critique of NPV
04/29/08
Ch. 6
Merits and Flaws of NPV
We will examine issues that are sometimes
problematic for NPV
Project Interactions – Mutually Exclusive
Unequal Lives
Replacement Decisions
Capital Rationing
Side Costs
Synergy
Embedded Options
But it is still the best model…
2
Project Interactions
Mutually Exclusive Projects
Definition: Accepting one project means rejecting
another project
Example: When two projects require the same scare
resource
Scare resource, plot of land
Projects, build restaurant or build service station
Assumes you can not acquire a similar scarce
resource, another plot of land
Assumes you can not have a dual use of the
land…Taco Bell Express at a Service Station
NPV does a nice job of picking the right project but
IRR may not...diagram to explain…
3
Unequal Lives
If two or more projects have different lives, the NPV
model favors the longer lived project
Can you correct for this bias?
Extend shorter project to match life of longer project
Assumptions are that you can “invest” at the
termination of the short-term project in a very similar
project, the cost of capital has not changed and you
do not have access to additional capital at start of the
project
Compute NPV for the short project and the extension
Compute Equivalent Annuities
Equivalent Annuity = NPV x (r / [1-(1+r)-n]
Problem 3, Heating System for a Building
4
Unequal Lives – Equivalent Annuity
Problem 3
Solar Heating, Cost $12,000 with annual costs of $500,
infinite life
Gas Heating, Cost $5,000 with annual costs of $1,000, and
will last twenty years
Oil Heating, Cost $3,500 with annual costs of $1,200 and will
last fifteen years
Compute present value of costs at 10% cost of capital
(1) Solar $17,000 (2) Gas $13,514 (3) Oil $12,627
Compute Equivalent Annuities
(1) Solar $1,700 (2) Gas $1,587 (3) Oil $1,659
Pick the lowest equivalent annuity…Gas
Issues with this approach?
5
Replacement Decision
Fits Mutually Exclusive as we only want one choice…either
keep current system, immediately replace current system, or
wait and replace later (which is keep current system)
Issues that are important - Salvage Value
Let’s re-examine this and how we deal with salvage value
Example…replace delivery truck with new delivery truck
Old truck (five years old)…original cost $38,000
New truck (expected life is eight years) …cost of $64,000
Old truck depreciation life was five year life (MACRS), book
value is 5.76% x $38,000 = $2,189
What if “blue book” is $1,200 for old truck
What if “blue book” is $2,189 for old truck
What if “blue book” is $4,800 for old truck
Does replacement lower future costs? Does replacement
increase future revenues? Why replace now?
6
Solutions to Salvage Value
Book Value of Truck is 38,000 x 0.0576 = $2,189
At sales price of $1,200
Loss on Disposal is $1,200 - $2,189 = $989
Tax Credit (40% tax rate) $989 x 0.40 = $396
Cash Flow at Disposal = $1,200 + $396 = $1,596
At sales price of $2189
No loss or gain
Cash Flow at Disposal = $2,189
At sales price of $4,800
Gain on Disposal is $4,800 - $2,189 = $2,611
Tax (40% tax rate) $989 x 0.40 = $1,044
Cash Flow at Disposal = $4,800 - $1,044 = $3,756
7
Profitability Index Example
Problem #1 ($150 million max on spending)
Project
Initial Inv.
NPV
PI
A
$25
$10
0.40
B
$30
$25
0.83
C
$40
$20
0.50
D
$10
$10
1.00
E
$15
$10
0.67
F
$60
$20
0.33
G
$20
$10
0.50
H
$25
$20
0.80
I
$35
$10
0.28
J
$15
$ 5
0.33
8
Ranking by NPV vs PI
Outlay $
Rank by NPV
$ 30
B
$ 65
C & H*
$ 45
D, G & E
$140
* Can’t pick F as it puts
you over the $150
Outlay $
$ 10
$ 30
$ 25
$ 15
$ 60
$140
Rank by PI
D
B
H
E
C and G
Total NPV
$95
$95
With a portfolio approach both give the same answer!
9
Problems with PI
Assumes capital rationing applies to the
current period only and that projects can only
be done during current period…
Assumes all investment is up front
Projects with cash outflow in future periods will
be overstated with PI
Future cash outflow will constrain future
periods
PI may not spend all current capital – so other
combinations may produce higher NPV
10
Side Costs and Sunk Costs
Should be included as part of the incremental costs
of a project but may be difficult to quantify
Opportunity costs
Project must “carry” the lost revenues of other uses
People – taken for new project
Resources – taken for new project
Sunk Costs
Do not include if truly sunk costs
Erosion – Substitute Products
Include if truly eroding other products
11
Synergy, 2+2 = 5
When adding new projects in the whole is
greater than the parts, you get synergies
Often used for mergers
Firm A Value + Firm B Value < Firm (A+B)
Value
Where does synergy come from?
Reduction in duplicate costs
Using excess capacity
Complementary Products
Timing of synergy…immediate or much later?
12
Embedded Options
Not a problem with NPV…
But, difficulty to quantify and properly add into
the expected future cash flow
There is an element of probability here…the
probability that this project will lead to
additional projects
Option to delay…projects always compete
with themselves over time…again, just need
to find the NPV today versus the NPV
tomorrow
13
Embedded Options
Expansion
Once a project has been completed additional
projects become available
How do you incorporate this into the original NPV
decision of the initial project?
What happens if you do not take on the additional
projects?
Abandonment
Is this an option for every project?
How do you incorporate abandonment value in
the future cash flow of a project?
14
NPV remains the Best
The problem with NPV is not in theory but in
practice
Problems with finding the right WACC for the
project
Problems with finding the right future cash
flows for the project
Usually the only comfortable number in cash
flow is the initial outflow
Other models all have these same cash flow
estimation problems…plus other issues
15
Weekly Homework for Thursday
Problem 4 – Replacement, unequal lives
Problem 5 – Unequal lives
Problem 7 – Salvage Value
Problem 15 – Capital Rationing
Problem 16 – Opportunity costs
Problem 18 – Lease option
Problem 21 – Opportunity cost
16