MERIT Experiment Status MERcury Intense Target K. McDonald for the MERIT Collaboration August 30, 2007 Build.272: Offices & Control Room Racks & electronics TT2/TT2A: MERIT Solenoid & Hg loop PS ring Upstream.
Download ReportTranscript MERIT Experiment Status MERcury Intense Target K. McDonald for the MERIT Collaboration August 30, 2007 Build.272: Offices & Control Room Racks & electronics TT2/TT2A: MERIT Solenoid & Hg loop PS ring Upstream.
PS ring
MERIT Experiment Status MER cury I ntense T
August 30, 2007
arget
K. McDonald for the MERIT Collaboration
Build.272: Offices & Control Room
Racks & electronics
TT2/TT2A: MERIT
Solenoid & Hg loop Upstream beam elements (new) Quadrupoles for final focusing Collimator Beam profile measurement Beam intensity measurement
24 August: 8 Pulses of 1.5 10 11 Protons Delivered to TT2A Tunnel
24 August: Secondary Particles Observed in Diamond and in Al Cathode Electron Multipliers
28 August: 9 Hour Access: Gate-Barrier installed to permit access to TT2 tunnel during PS/SPS operations
28 August: 9 Hour Access: Cryogenic Hardware Installed in TT2/TT2A Tunnels
28 August: 9 Hour Access: MERIT Mercury System Operational, MERIT Solenoid Ready for Power/Cooling
Hg-jet hydraulic system Solenoid Hg container Target chamber Prot on Bea m
29 August: Mercury Jets Produced in TT2A Tunnel
15m/s jet Viewport #1, FV camera Viewport #2, CERN camera Viewport #3, FV camera 20m/s jet Viewport #1, FV camera Viewport #2, CERN camera Viewport #3, FV camera