R OUTE 29 & L INTON H ALL R OAD I NTERCHANGE PA R D O N O U R D U.

Download Report

Transcript R OUTE 29 & L INTON H ALL R OAD I NTERCHANGE PA R D O N O U R D U.

R OUTE 29 & L INTON H ALL R OAD
I NTERCHANGE
PA R D O N O U R D U S T M E E T I N G
J U LY 3 1 , 2 0 1 3
SCHEDULE
PROJECT MILESTONES
– NOTICE TO PROCEED
– JUNE 15, 2011
– FINAL ACCEPTANCE
– JUNE 30, 2015
SCHEDULE
PROJECTED INTERIM MILESTONES
– DETOUR OPEN TO TRAFFIC (STAGE 1)
– JANUARY 7, 2012
– ROUTE 29 SHIFTED OVER RR (STAGE 2)
(WEATHER PERMITTING)
– AUGUST 16 2013
– LINTON HALL SHIFTED OVER RT 29 & RR
(STAGE 3)
– FALL 2014
– STAGE 4 COMPLETE
– WINTER 2014
– STAGE 5 COMPLETE
– SPRING 2015
– FINAL ACCEPTANCE
– JUNE 30, 2015
** ALL DATES ARE APPROXIMATE & SUBJECT TO CHANGE
TRAFFIC SWITCH IMPACTS
– 8/16 9 PM
– Rt 29 NB Left & Right Turns Closed
– Rt 29 SB Left Turns Closed
– Linton Hall Rd WB Limited Lanes (Right, Left & Straight movements
permitted)
– John Marshall Hwy WB closed and detoured via Catharpin (Local
traffic permitted to Dave's Store Lane) Linton Hall & Rt 29
Intersection Construction
– 8/17
– Rt 29 NB moved into Stage 3 Configuration Single Lane early
morning
– Midnight I66 WB to RT 29 SB ramp closed. Traffic detoured to Rt
29 NB Exit and allowed to make a left at the Rt 29 Signal.
– Rt 29 SB moved into Stage 3 Configuration Single Lane early
morning
– Midday Linton Hall Rd & Rt 29 Signal would be reopened to its
complete Stage 3 Configuration with the exception of single lane
closures on RT 29 NB & SB.
All Dates and times shown are approximate and subject to change with out notice
TRAFFIC SWITCH IMPACTS
– 8/17 Cont. & 8/18
– Construction of the Ramp G (I66 WB to RT 29 SB) detour would
begin immediately following the closure of the existing ramp and
the moving of SB Rt 29 into the Stage 3 Configuration. Construction
of this Detour is anticipated to be completed on 8/18.
Traffic shift has been rescheduled for the weekend of August 24th
due to Jimmy Buffet concert at Jiffy Lube Live. The traffic shift
will start on Friday night August 23rd and should be completed on
Sunday August 25th
All Dates and times shown are approximate and subject to change with out notice
TRAFFIC SWITCH IMPACTS
John Marshall Highway EB
TRAFFIC SWITCH IMPACTS
I66 EB to Route 29 SB
TRAFFIC SWITCH IMPACTS
Linton Hall Road & Route 29 (Part 1)
TRAFFIC SWITCH IMPACTS
Linton Hall Road & Route 29 (Part 2)
TRAFFIC SWITCH IMPACTS
WB I66 Exit 43A
PROJECT STATISTICS TO DATE
WHY CONSTRUCTION TAKES SO LONG!
– Onsite Excavation: 100,000 CY
– Offsite Dirt Import: 640,000 CY
– Storm Drainage Installed: 11,000 LF
– Aggregate Subbase Placed: 125,000 TN
– Asphalt Pavement Placed: 51,000 TN
– MSE Walls Constructed: 124,000 SF
– Structural Concrete Placed: 9,000 CY
– Reinforcing Steel Installed: 1,660,000 LB
PROGRESS PHOTOS
ROUTE 29 LOOKING SOUTH (From Hotel)
PROGRESS PHOTOS
ROUTE 29 LOOKING SOUTH (From Hotel)
PROGRESS PHOTOS
ROUTE 29 LOOKING SOUTH (From Hotel)
PROGRESS PHOTOS
ROUTE 29 LOOKING SOUTH (From Hotel)
PROGRESS PHOTOS
ROUTE 29 LOOKING SOUTH (From Hotel)
PROGRESS PHOTOS
ROUTE 29 LOOKING NORTH (From Old McDonalds)
PROGRESS PHOTOS
ROUTE 29 LOOKING NORTH (From Old McDonalds)
PROGRESS PHOTOS
ROUTE 29 LOOKING NORTH (From Old McDonalds)
PROGRESS PHOTOS
ROUTE 29 LOOKING NORTH (From Old McDonalds)
PROGRESS PHOTOS
ROUTE 29 LOOKING NORTH (From Hotel)
PROGRESS PHOTOS
ROUTE 29 LOOKING NORTH (From Hotel)
PROGRESS PHOTOS
ROUTE 29 LOOKING NORTH (From Hotel)
PROGRESS PHOTOS
ROUTE 29 LOOKING NORTH (From Hotel)
FUTURE UPDATES AND PROGRESS INFORMATION
QUESTIONS ??????