Road Management Act – Works on Roads November 2011 Road Management Act – Works on Roads Presentation Summary Background Road Management Act.
Download
Report
Transcript Road Management Act – Works on Roads November 2011 Road Management Act – Works on Roads Presentation Summary Background Road Management Act.
Road Management Act – Works on Roads
November 2011
Road Management Act –
Works on Roads
Presentation Summary
Background
Road Management Act overview
Management of Roads
Use of the Road
Consent for Works
Applying for Consent
Notification of Works
Consent and Notification Process
Worksite Safety
Working Within the Road Reserve
Reinstatement of Works
Resolution of Disputes
Background
Infrastructure Reference Panel Working Group
Established to address issues that relate to works on roads as
identified by road authorities, utilities and providers of public
transport during the stakeholder consultation phase of the review of
the Road Management Act 2004
Implementation Program – drafted actions aimed at developing
improved and consistent processes for managing works on roads,
including:
communication and contact details – central database
utility service level agreements – timeframes for hazardous
temporary reinstatement repair and permanent reinstatement
road authority reinstatement standards – common across regional
areas
consent for works applications – common templates and processes
emergency works – definitions and guidelines
education and training – this presentation
Road Management Act 2004
OBJECTIVE OF THE ACT
Establish a coordinated management system for
public roads that:
promotes safe and efficient State and local
public road networks
provides for responsible use of road
reserves for other legitimate purposes, such
as provision of utility services
Sections 4 & 20 RMA
CoP
RM
(Wrks & Inf) R’ways/
Trams
Regs
RS
(Traff Mgmt)
Regs
Road
Safety
Act
CoP
Utilities
RM
(General)
Regs
CoP
RMPs
CoP
W’site
Safety
Road
Management
Act
VicRoads
RMP
Register
of Public
Roads
CoP
C’ways
Policy
Access
Mgmt
CoP
Operatnal
Resp
Management of Roads
Road Authorities
Statutory Duty
Section 40 of the Act imposes a statutory duty on road
authorities to inspect, maintain and repair public roads
Failure to do this can result in liability for “breach of statutory
duty” (“Highway rule” no longer applies)
What standard is required?
If the road authority has a road management plan, the
standard is set by that plan
Alternatively, the road authority may set a standard by a
policy decision
Note: If no RMP, or policy, the courts will determine the
standard.
Section 40 RMA
Management of Roads
Road Management Plans
Responsible road authorities may develop a Road
Management Plan:
standards for inspection, maintenance and repair
management systems and policies for road
management functions
accountability
policy defence
Section 52 RMA
Management of Roads
Utility and Public Transport Infrastructure
Managers
Statutory Duty
Schedule 7 (Part 1) imposes statutory duties on infrastructure
managers and works managers to conduct works on roads
safely and to maintain their infrastructure:
to an appropriate standard
to avoid causing damage to the road
to repair any damage caused to the road
Note: OH&S requirement for safe design to enable safe
maintenance
What standard is required?
Defence against claims for damages to prove reasonable care
was taken to ensure non-road infrastructure was not
dangerous to traffic
Schedule 7, clauses 6 & 11 and section 105(2) RMA
Management of Roads
Utility and Public Transport Infrastructure
Managers
Works on Roads
Duty to reinstate roads:
as soon as is reasonably practicable
as near as reasonably practicable to equivalent standard
as before works
Road Authority power to rectify works
may give notice that rectification works are required
may conduct the rectification works if road authority notice
not complied with
may recover costs from infrastructure manager or works
manager who conducted the original works
Schedule 7, clauses 6 & 19 RMA
Use of the Road
Non-Road Infrastructure in Road Reserves
Road authority, in exercising its functions and powers,
should:
“facilitate the appropriate use of the road reserve for
non-road infrastructure and the effective and
efficient delivery of utility and public transport
services.”
Section 38(2)(e) RMA
Use of the Road
Non-Road Infrastructure in Road Reserves
Positioning of Non-Road Infrastructure
comply with good engineering practice and industry standards
design and installation to minimise damage to roads and risk to safety of
road users
minimise cost to the community in providing infrastructure and services
Section 20 and Schedule 7 RMA
Code of Practice – Management of Infrastructure in Road Reserves
minimise sight distance obstructions
avoid longitudinal placement in freeway reserves
minimise damage to street trees and high conservation roadsides
consider future road infrastructure improvements or maintenance
Part 3, Division 1 Code of Practice - Management of Infrastructure in Road Reserves
Consent for Works
Works on Roads – section 63
Must have consent of the Coordinating Road
Authority (CRA)
Act & Regulations prescribe certain
exemptions from consent / notice for certain
works
Offence to conduct works without written
consent
Section 63 and clause 16, Schedule 7 RMA
Consent for Works
Exemptions from Consent – the Act
Works specified under other Acts
Eg tree clearing around power lines
(Electricity Safety Act)
As prescribed in Regulations
Works conducted in an emergency
Eg burst water main – but not short term
planned /unplanned works
Section 63 RMA
Consent for Works
Exemptions from Consent – the Regulations
Road Management (Works & Infrastructure) Regs
2005 (as amended)
“Minor works” other than “traffic impact works”
Applies to:
• a Utility or its Agent; or
• A Provider of Public Transport or its Agent;
or
• a Road Authority or its Agent
Regulation 5, Road Management (Works & Infrastructure) Regulations
Note: Other exemptions also apply
Consent for Works
“Minor Works” - Exemptions from Consent (1):
Works consisting of:
repair or maintenance of poles
replacement or relocation of a single pole in an urban area
replacement or relocation of not more than 3 poles in an area
that is not an urban area
installation, repair or maintenance of aerial cables or other
overhead non-road infrastructure
connection of a consumer to a service – other than “supply
extension works”
using an access hole for repairing or maintaining
infrastructure under a road
Regulation 4, Road Management (Works & Infrastructure) Regulations
Consent for Works
“Minor Works” - Exemptions from Consent (2):
Works consisting of:
repair or maintenance of street lighting
removal of a tree or vegetation in accordance with an Act
other than the Road Management Act
excavation of the roadway, pathway or shoulder less than
8.5 square metres.
excavation of any part of a road other than a roadway,
pathway or shoulder
Regulation 4, Road Management (Works & Infrastructure) Regulations
Consent for Works
“Minor Works” – Consent Required where Minor
Works are:
Traffic Impact Works – being works:
on a freeway
on an arterial road that requires deviation of vehicles into an
on-coming traffic lane
in a clearway when in operation
on, or that affects, a bridge or structure
that require closure to vehicles of part of a roadway for a
continuous period of more than 12 hours or more than 24
hours in 7 days
that cause a significant delay to traffic on an arterial road or
municipal road
Regulation 4, Road Management (Works & Infrastructure) Regulations
Consent for Works
“Minor Works” – Consent Required where Minor
Works are (cont’d):
Traffic Impact Works – being works affecting Public
Transport:
that require deviation (to a different road), replacement or
cancellation of a tram or bus
that cause a significant delay to a tram or bus
that have a significant impact on access to a tram stop or
bus stop
Regulation 4, Road Management (Works & Infrastructure) Regulations
Note: Future “Traffic Impact Works” are proposed to be declared by the Minister for
Roads under the Regulations – to clarify further the meaning of “significant”.
Consent for Works
“Minor Works” – Consent Required where Minor
Works are :
Supply Extension Works – being works involving the
connection of a consumer to a service:
in an urban area, by means of:
underground works exceeding 100 metres
overhead works involving installation of more than one
additional pole
in any other area, by means of:
underground works exceeding 300 metres
overhead works involving installation of more than 3
additional pole
Regulation 4, Road Management (Works & Infrastructure) Regulations
Consent for Works
Road Authority and Utility Works Affecting
Public Transport (1)
Notification of Works where:
works on or in the immediate vicinity of rail
infrastructure or rolling stock – likely to threaten its
safety
works conducted by another infrastructure manager or
works manager that could affect (public transport)
infrastructure
Sections 48EA & 48EB and Schedule 7, clause 8, RMA
works that require the closure of a tram or bus stop for
more than 2 hours – 10 business days notice
Table 1, clause 44, Code of Practice – Management of Infrastructure in Road Reserves
Consent for Works
Road Authority and Utility Works Affecting Public
Transport (2)
Consent for Works where:
‘minor works’ are “traffic impact works” that:
require deviation, replacement or cancellation of tram or
bus
cause significant delay to tram or bus
have significant impact on access to tram or bus stop
Regulation 4, Road Management (Works & Infrastructure) Regulations
road closure or closure of tram tracks – any duration
lane closure in peak period - >15 min duration of works and
tram / bus delay likely >2 min (Melbourne & regional centres)
lane closure in off-peak period - >2 hour duration of works
and tram / bus delay likely >5 min (Melb & regional centres)
Table 1, clause 44, Code of Practice – Management of Infrastructure in Road Reserves
Note: The Coordinating Road Authority should forward any consent
for works applications to the relevant provider of public transport
where works affect public transport.
Clause 45, Code of Practice – Management of Infrastructure in Road Reserves
Consent for Works
Utility Works Requiring Multiple Road Openings
Applications for Consent:
single utility project that has multiple road openings /
excavations should only require one consent for works
application
Minor Works Exemptions:
IRP Working Group agreed consent required where a
utility project has multiple road openings / excavations
which when combined exceed the ‘minor works’ threshold
(ie. 8.5 sq metres of roadway, pathway or shoulder)
Note: This position to be incorporated into relevant
guidance material.
Consent for Works
Works Conducted in an Emergency
Works conducted in an emergency by, or with the authority of, the
relevant infrastructure manager are exempt from consent
Make site safe is a priority
Examples: Gas main explosion, burst water main, power lines over
road (ie. conducted by a utility in relation to an emergency),
disruption of an essential service – not short term planned or
unplanned works – definition to be prepared
Section 63(2)(e) RMA
Notification of Emergency Works
Notify coordinating road authority as soon as is reasonably practicable
Schedule 7, clause 7(2) RMA
Permanent Reinstatement after Emergency - Consent
Consent for works required if permanent reinstatement is not planned
for completion within 20 days of temporary reinstatement
Consent for Works
Road Opening Permits
required under Council “local law” – Not permitted to be
used instead of consent for works application under Road
Management Act
Road Management Act overrides any other Act if there is
an inconsistency (includes local laws made under the Local
Government Act)
can not require both ‘consent for works’ and ‘road
opening permit’
Section 5 RMA
Asset Protection Permits
can not be used for works within the road reserve (ie
instead of, or in addition to, ‘consent for works’)
only used where works on land abutting road reserve may
damage Council assets
Applying for Consent
Application for Consent
Submit application form to Coordinating Road Authority (CRA):
includes information requirements to enable assessment
must notify other affected infrastructure managers
Consent application fee applies
Schedule 7, clauses 8 and 16 RMA
Applying for Consent
CRA Assessment Process
CRA must respond within 20 business days for all works other than:
supply extension works - 15 business days; or
connection of consumer to a service – 3 business days.
Consent may be “deemed” if no response from CRA within the
relevant periods above
Schedule 7, clause 17 RMA and Regulation 17, RM(W&I) Regulations 2005
CRA must consult with the responsible road authority if affected by
works by an infrastructure manager
Schedule 7, clause 16 RMA
CRA to include reasonable conditions requested by public transport
infrastructure manager or provider of public transport where works
will affect public transport infrastructure or services
Clauses 36 and 45, Code of Practice – Management of Infrastructure in Road Reserves
Note: A Memorandum of Authorisation (MoA) does not give consent to
conduct works
Applying for Consent
Conditions of Consent
CRA may impose reasonable conditions on a written
consent in relation to the works, however:
for utilities / PT providers, CRA cannot impose certain
conditions, including:
financial securities or indemnities (beyond 12 month
warranty period)
technical design or installation techniques
visual amenity or aesthetics
above ground infrastructure to be placed under a
road
Regulation 14, Road Management (Works and Infrastructure) Regulations 2005
Notification of Works
Notification of Works – to CRA
Proposed installation of non-road infrastructure or related works in road
reserve, but
exemptions apply:
to a utility, provider of public transport or responsible road
authority (or their agents)
in an emergency
Schedule 7, clause 7 RMA and Regulation 11 RM (W&I) Regulations 2005
Completion of works (including reinstatement works)
must be within 7 business days
exemptions apply:
where a condition of a written consent given by CRA.
minor works – other than:
- traffic impact works; or
- where any excavation of roadway, pathway or shoulder
Schedule 7, clause 13 RMA and Regulations 5 and 9 RM (W&I) Regulations 2005
Notification of Works
Notification of Works – to Provider of Public
Transport
Works affecting Tram and Bus services:
road closures
lane interruptions – peak or off-peak
tram or bus stop closure
Notification and consent requirements subject to duration
of works
Clauses 43 to 47, Code of Practice for Management of Infrastructure in Road Reserves
Consent and Notification Process
Standard ‘Works within Road Reserve’ Form encouraged
To be used by all CRAs, utilities and providers of public
transport when:
proposing to install non-road infrastructure or related works
in road reserve
applying for consent for works
notifying the completion of works
To help standardise communication process and minimise
administrative costs
Clause 35, Code of Practice – Management of Infrastructure in Road Reserves
Worksite Safety
Road Safety Act – section 99A – Safety of
Works
An offence if a person (eg. works manager) does not
conduct works safely by failing to:
– have in operation a traffic management plan;
– give appropriate warnings to road users;
– engage appropriately trained and qualified
persons to carry out the works or direct traffic; or
– give appropriate directions to the persons
carrying out the works
Penalty:
60 penalty units
Section 99A Road Safety Act
Worksite Safety
Responsibility for Safety of Works
The works manager must take all reasonable
measures to:
minimise disruption to traffic
ensure the safety of the works for road users
and adjoining properties;
make adequate provision for persons with a disability
Schedule 7, clause 11 RMA
Worksite Safety
Traffic Management Plans (TMP)
Must comply with the requirements as prescribed in the
Road Safety (Traffic Management) Regulations 2009
(Regulation 32)
Code of Practice for Worksite Safety – Traffic
Management provides good practice guidance
Must be maintained, and available for inspection, at the
worksite at all times when workers are present
Note: Penalty applies - 6 penalty units (or approx $700)
Regulations 32 & 33, Road Safety (Traffic Management) Regulations 2009
Works manager responsible for safety of worksite –
road authority approval of TMP not required
Works manager to keep records of any changes to TMP
Clauses 12 and 16, Code of Practice for Worksite Safety – Traffic Management
Worksite Safety – Traffic Management
(WS-TM) Code of Practice
Government Gazette No. S 351
Worksite Safety
Memorandum of Authorisation (MoA)
Authorisation in writing from the relevant road authority
(VicRoads or Council) to erect, remove or alter traffic
control devices
It can be for specific works or an event, or it may be
generic
Road Safety (Traffic Management) Regulations 2009
Worksite Safety
MoA - Works by Utilities / Public Transport
‘Works managers’ (including contractors) may use
without an MoA:
Works advisory devices
Hand-held stop signs
Works zone signs
Temporary works speed limit signs (but no less than
40 km/h)
provided
the works are “authorised” - ie. have consent of
coordinating road authority or are exempt from
consent (under Road Management Act)
all Traffic Control Devices are included in the TMP
Regulation 11, Road Safety (Traffic Management) Regulations 2009
Worksite Safety
MoA - Works by Utilities / Public Transport
Works advisory devices are defined as all devices used
to warn, guide or advise traffic at work sites.
They include:
roadworks or road workers ahead signs
no linemarking signs
detour or lane closure signs
road closed or part road closed signs
road humps
traffic cones or bollards
They exclude regulatory traffic control devices
Regulation 11, Road Safety (Traffic Management) Regulations 2009
Worksite Safety
MoA - Works by Utilities / Public Transport
Therefore, utilities & public transport operators ‘works
managers’ (including contractors) only need to apply to
VicRoads for an MoA in limited cases:
temporary traffic signals
speed limit signs less than 40 km/h
regulatory signs (other than speed limits), eg
No Right Turn, No Entry
Note: The MoA as required from VicRoads applies to works on
freeways, arterial roads and municipal roads
Regulation 11, Road Safety (Traffic Management) Regulations 2009
Working within the Road
Reserve
Utility Works - Boring vs Excavation of Roadway
If practicable, use methods which do not excavate or break up the
surface of the roadway or pathway
If necessary to excavate or break up roadway or pathway:
conduct works at time and in a manner that minimises
inconvenience to road users?
conduct works so as to minimise long term damage or disruption
Schedule 7, clause 5 RMA
Depth of Underground Utility Infrastructure
Underground utility infrastructure should be laid to depths that:
conform to utility regulations and standards
allow road authority maintenance and repair activities without
damaging underground utility infrastructure
allow tram and train operations and track maintenance
Note: Guidance on depths is provided in clause 24, Code of Practice –
Management of Infrastructure in Road Reserves
Clause 24, Code of Practice – Management of Infrastructure in Road Reserves
Working within the Road
Reserve
Hours of Work (1)
Principles for management of works and infrastructure:
the avoidance or minimisation of disruption to traffic
the avoidance or minimisation of disruption to delivery of
utility and public transport services
Section 20(2) RMA
“Traffic impact works” include:
works that cause a significant delay to traffic
Regulation 4, Road Management (Works & Infrastructure) Regulations
Plan location of utility infrastructure such that installation and
maintenance activities will:
minimise delays and inconvenience to traffic and road users
minimise interference with, and access to, public transport
services
Clause 21, Code of Practice – Management of Infrastructure in Road Reserves
Working within the Road
Reserve
Hours of Work (2)
Works affecting Tram and Bus services:
road closure and/or tram track closure – consent
lane interruption between 6 - 9 am or 3 – 7 pm - consent
Note: “Lane interruption” means temporary interruption of
traffic flow in a lane (including lane closure) which may
impact on public transport services but excludes works
vehicles legally parked or works located within a legal parking
area which do not significantly encroach onto an adjacent
traffic lane.
“Lane interruption” works are not restricted to between 9 am and
3 pm – but these works do require consent
work arrangements may be negotiated with coordinating road
authority to minimise impacts on public transport and allow
works to proceed within peak times.
Clause 44 and Table 1, Code of Practice – Management of Infrastructure in Road Reserves
Working within the Road
Reserve
Compliance with Conditions of Consent
Works manager must comply with all conditions of a
written consent to conduct works within road reserve
Offence to fail to comply with conditions of consent
Section 65 RMA
Any required changes or variations to the plans or
specifications for the works should be negotiated with the
coordinating road authority
Clause 54, Code of Practice – Management of Infrastructure in Road Reserves
Working within the Road
Reserve
Dial Before You Dig
Road authorities recommended to contact Dial Before You Dig
where proposed roadworks (or maintenance activities) may
affect utility infrastructure
Clause 60, Code of Practice – Management of Infrastructure in Road Reserves
Utilities should also contact Dial Before You Dig when planning
for proposed utility works
Duty to Provide Information
Non-road infrastructure manager must comply with a request
from a road authority for information regarding:
the location of any non-road infrastructure
technical advice or assistance relating to the conduct of
works on non-road infrastructure in a safe manner
Schedule 7, clause 9 RMA
Working within the Road
Reserve
Redundant or Obsolete Utility Infrastructure
in Road Reserves
Utilities to advise coordinating road authority of details of
redundant or obsolete infrastructure:
where there is potential for deterioration that may
affect road infrastructure or become a road safety
hazard
where there are proposals to remove or treat such
infrastructure
when requested by a road authority
Clause 58, Code of Practice – Management of Infrastructure in Road Reserves
Reinstatement of Works
Duty to Reinstate – Utility Works
Works manager, after completing works, must reinstate the
roadway, pathway, shoulder or roadside:
to the standard before the works commenced;
as promptly as reasonably practicable;
as nearly as reasonably practicable to an equivalent standard
of quality and design; and
to restore features to assist persons with a disability.
Note: Road authority can not require ‘betterment’ of road
infrastructure
Schedule 7, clause 12 RMA
Utility infrastructure manager or works manager is responsible for
maintenance of reinstatement works for a period of 12 months
Reinstatement works conducted by road authority – road authority
accepts ongoing responsibility for works
Clause 56, Code of Practice – Management of Infrastructure in Road Reserves
Resolution of Disputes
Dispute between Road Authority and Utility
or Provider of Public Transport
determined by the relevant Ministers or their nominees
have regard to RMA ‘works and infrastructure
management principles’ – section 20(2) RMA
Section 125 RMA
from practical perspective, seek resolution as quickly as
possible by parties at the workface – with escalation as
necessary (without involving Ministers)
Clause 72, Code of Practice – Management of Infrastructure in Road Reserves
Working within the Road
Reserve
Further Information
Working within the Road
Reserve
‘A Guide to Working in the Road Reserve’
brochure (on VicRoads website)
Working within the Road
Reserve
Close