Port Everglades 2009 Master / Vision Plan Update Broward County Board of County Commissioners Workshop January 11, 2011
Download ReportTranscript Port Everglades 2009 Master / Vision Plan Update Broward County Board of County Commissioners Workshop January 11, 2011
Port Everglades 2009 Master / Vision Plan Update Broward County Board of County Commissioners Workshop January 11, 2011 Port Everglades Agenda • Project Background • Update of Master/Vision Plan – Stakeholder Outreach Efforts – Key Factors Affecting the Updated 20-year Vision Plan – Status of 2006 Master Plan Projects – Strategic Changes from 2006 Plan • Review of Approach to Turning Notch Expansion – Southport Mangrove Creation-Enhancement Project – Turning Notch Expansion at Existing Depth – ACOE Channel Deepening and Widening • Costs and Affordability Analysis Results • Next Steps November 6, 2015 Page 3 Project Background • 2006 Master/Vision Plan was approved by the Board of County Commissioners in December 2007, with the exception of projects associated with the Turning Notch extension and Berth 29 expansion • BOCC directed that Port Master Plan be updated every two years • Notice to Proceed for the 2009 Master/Vision Plan Update issued in February 2009 November 6, 2015 Page 4 Master/Vision Plan Elements • Phase I – Completed in October 2009 – – – – Facilities Assessment Market Assessment Facilities Needs and Throughput Enhancement Strategy Development (Business Strategy, Asset Utilization & Master Plan Development) • Phase II – Scheduled to be completed in March 2011 – Strategy Development (Master Plan Development, Financial Strategy & Economic Impact Analysis) – Final Plan (Executive Summary) – Implementation Plan • Phase III – Scheduled to be completed by December 2011 – Update Deep Water Port Component of County’s Comprehensive Plan November 6, 2015 Page 5 More than 15 Stakeholder Outreach Meetings on the Port Master/Vision Plan Have Been Conducted Date 03/06/09 03/20/09 03/27/09 04/29/09 06/08/09 06/15/09 06/18/09 08/07/09 06/24/10 07/09/10 07/29/10 08/31/10 09/16/10 09/27/10 09/28/10 Meeting Description Port Everglades Association Meeting 1 Focus Group Meeting 1 Tenant / Stakeholder Meeting 1 Environmental Outreach Meeting Focus Group Meeting 2 Environmental Stakeholder Meeting Tenant/Stakeholder Meeting 2 Port Everglades Association Meeting 2 Focus Group meeting 3 Port Everglades Association Meeting 3 Tenant / Stakeholder Meeting 3 Public Meeting at Broward County Library Presentation to Metropolitan Planning Organization (MPO) Presentation to MPO Technical Coordinating Committees (TCC) Presentation to MPO Community Involvement Roundtable (CIR) November 6, 2015 Page 6 Port Everglades Southport November 6, 2015 Midport Page 7 Northport 20-Year Market Forecast Drives the Plan 25,000,000 (25%) 20,000,000 15,000,000 10,000,000 5,000,000 0 (5%) (26%) (12%) Containers (TEUs) Dry/Neo-Bulk (Tons) Petroleum (Tons) Cruise (Passengers) 2006 Plan 2,734,704 8,028,035 22,489,376 6,986,711 2009 Plan 2,401,230 7,625,627 16,699,008 5,161,118 2010`Actual 793,227 762,596 15,483,856 3,674,226 November 6, 2015 Page 8 Bigger Ships need Longer Berths and Deeper Water Calling PEV Today Lightly Loaded Calling PEV Today November 6, 2015 Page 9 Possible After Deepening Facility/Infrastructure Needs Over 20 year planning horizon • Ability to berth fully laden Post-Panamax vessels; 7,000 TEUs • More and longer cargo berths • Rail to Southport and ICTF • Longer cruise berths and larger cruise terminals • Reconfiguration of Northport slips • Upland improvements to terminals and intermodal access • New berth for crushed rock/aggregate ship November 6, 2015 Page 10 Status of 2006 Master Plan Projects Project Status Midport Roadway (Eller Drive) Improvements Completed and in operation Mobile Harbor Crane at Midport Completed Cruise Terminal 18 Expansion Completed and in operation Intermodal Bridge over FPL Canal Opened June 2010 Southport Container Yard Improvements Construction to be completed in early 2011 Eller Drive Overpass FDOT Construction begins in 2011 McIntosh Road Improvements Construction procurement begins in 2011 By-Pass Road Design in progress Phase 1 construction procurement begins in early 2011 Phase 2 programming underway Cruise Terminal Improvements at CT 2, CT 19, CT 21 and CT 26 In design Cruise Terminal 4 90% design Pending issue of permit from City of Fort Lauderdale November 6, 2015 Page 11 November 6, 2015 Page 12 November 6, 2015 Page 13 November 6, 2015 Page 14 Phase 1 November 6, 2015 Page 15 Phase 2 November 6, 2015 Page 16 Strategic Changes from 2006 Plan • New Upland Enhancement – Conservation Easement • Single phase approach to Turning Notch expansion • Refinement of ACOE Deepening and Widening program • Vessel and Crane Positioning due to FAA Object Height Restrictions pending • Revised phasing of bulkhead projects • Inclusion of potential ferry operations • ICTF advanced, Crushed Rock facility delayed November 6, 2015 Page 17 Aggregate project was in 5-year plan And ICTF was in 10-year plan 2006 5-Year Master Plan By-Pass road in single phase Turning Notch expansion was in 10-year plan New Bulkheads for Berth 9 and 10 were in 20-year plan Slip 2 lengthening was in 10-year plan Upland enhancement off-port Updated 5-Year Master Plan Aggregate project postponed to 10-year plan. ICTF moved forward in 5-year plan Turning Notch expansion moved forward in 5-year plan By-Pass road in two phases Relocated Bulkheads for Berth 9 and 10 moved in 5-year plan Slip 2 lengthening in 5-year plan On-port upland enhancement area of 16.5 acres November 6, 2015 Page 18 ICTF project was planned in the 10-year plan 2006 10-Year Vision Plan Lengthening and widening of Slip 2 Multimodal center built in one phase Slip 3 was widened Berth 29 was extended to increase berth capacity Tracor Basin was proposed to be filled Aggregate project comes in the 10-year plan Updated 10-Year Vision Plan No widening of Slip 2 and Slip 3 in 10-year Plan A small ferry Vessel berth Multimodal center built in two phases. Phase 1 starting in 10-year plan Berth 29 extension not considered per BOCC direction November 6, 2015 No filling in Tracor Basin. Page 19 with catwalk Replace finger pier in 5-Year Plan New bulkheads for Berths 1,2,3 and 16,17,18 2006 20-Year Vision Plan All bulkheads in Midport and Northport were scheduled to be replaced in 20-year plan Ro-Ro berths relocated in DCC Updated 20-Year Vision Plan Majority of bulkheads will be replaced in 20-year plan Ro-Ro berths relocated on the Western end of expanded Turning Notch Multimodal center built in two phases. Phase 2 starting in 20-year plan November 6, 2015 Page 20 Widening of Slips 1, 2 and 3 Southport Mangrove Creation-Enhancement Project • September 2010 BOCC and FDEP signed agreement on Southport Mangrove creationenhancement project 16.5 acres • 8.68 acres is replaced with approximately 16.5 acres 8.68 acres November 6, 2015 Page 21 Southport Mangrove Creation-Enhancement Project 16.5 acres Fee Simple Transfer Area 60 Acres 8.68 acres November 6, 2015 • Conservation Easement becomes approximately 60 acres of Fee Simple Area • Conservation Easement remains on Fee Simple Area and is assigned to the Broward County Audubon Society if they agree to serve as land manager for the State • RLI in process for design and permitting Page 22 Turning Notch Project The 2006 Plan called for lengthening in two phases Phase 1 1450’ long November 6, 2015 Phase 2 2450’ long Page 23 Turning Notch Project (at Existing Water Depth) • Project included in Port’s 5-year Capital Improvement Program • Projected Broward County Economic Impact – 3,843 Local Jobs – $9.4 Million per year in Local Taxes – $173.6 Million per year in Economic Activity November 6, 2015 Page 24 Increase Berth Capacity: Turning Notch Expansion (at Existing Water Depth) • Cost – – – – Project Cost $ 119.5 M Less Projected State Grants $ (30.2)M Less Federal Fund $ 0 M Cost to Port $ 89.3 M • Schedule – Start operations in 2017 – Full use operations in 2024 • Additional Gross Revenue at Full Use – $37.72 M per year – Revenue Supported by Market Assessment November 6, 2015 Page 25 2006 PORT EVERGLADES/U.S. ARMY CORPS OF ENGINEERS DEEPENING & WIDENING PROGRAM November 6, 2015 Page 26 UPDATED PORT EVERGLADES/U.S. ARMY CORPS OF ENGINEERS DEEPENING & WIDENING PROGRAM Draft National Economic Development (NED) Plan November 6, 2015 Page 27 ACOE Deepening and Widening • May 4, 2010 BOCC supports continuing with fully funded ACOE study • Benefit/Cost Ratio 2/1 • Projected Broward County Economic Impact – 1,037 Local Jobs – $2.6 Million per year in Local Taxes – $43.3 Million per year in Economic Activity • Cost – – – – – November 6, 2015 Project Cost $ 255 M Less Projected State Fund (uncertain) Less Projected Federal Fund $ 155 M Cost to Port $ 100 M Potential Add’l Cost to Port $ 23 M Page 28 ACOE Deepening and Widening Study Schedule • • • • • • • • • • Mar 2011 - Draft Report available for Cooperating Agency Review Dec 2011 – Released for Public Comment Nov 2012 - Final Report to include Broward County support letter Nov 2012 - Design Agreement to include Broward County financial commitment for design (estimated $1M of $4M total) Nov 2012 - Design Start Oct 2013 – Authorization Jun 2014 - Design Complete Jun 2014 - Project Partnership Agreement to include Broward County financial commitment for construction Jan 2015 - Construction Start Jan 2017 - Construction Complete November 6, 2015 Page 29 No-Build Impact of No Turning Notch & No Deepening • Unable to Meet Market Forecast – 1.9 M TEU (year 2020) – 2.4 M TEU (year 2029) • No Capacity to Handle Additional – 930,000 TEUs of containerized cargo – 4,000,000 Tons of bulk cargo • Potential Loss of Existing Customers • Loss of Potential Gross Revenue of $45.26 M per year • Lost Opportunity for Broward County Economic Benefits – 4,880 Local Jobs – $12 Million per year in Local Taxes – $217 Million per year in Economic Activity November 6, 2015 Page 30 Airport – Seaport Coordination on Object Heights To allow for higher air draft vessels and larger cranes at Midport and Southport November 6, 2015 Page 31 Bulkhead Replacement Schedule Summary • 5-year Plan – Berths 9,10 • 10-year Plan – Berths 1,2,3 – Berths 16, 17, 18 • 20-year Plan – – – – – – – Berths 19, 20 Berths 7, 8, 8A Berths 21, 22 Berths 14, 15 Berth 4, 5 Berths 23, 24, 25 Berths 11, 12, 12A, 13, 13A November 6, 2015 Page 32 The Project-Decision Matrix Considers these sensitivities: • Decision Matrix used to evaluate projects for potential placement into the 5-Year CIP • Project Cost • Return on Incremental Investment (ROI) • Net Present Value (NPV) • Economic Impact • Environmental Impact • Customer/Regulatory Need November 6, 2015 Page 33 Decision Matrix Used on These Projects: Intermodal Container Transfer Facility (ICTF) Development (Overall Project) Total Project Cost $42M ROI 12.3% Economic Impact Net Total Present Income Taxes Value (000's) Jobs (000's) $31.9M $1,485,574 43,825 $109,933 Environmental Impact High Mid Low X Permit Required Customer / Regulatory Needs High Mid X Low Cruise Terminals 2, 19, 21, 26 Expansion (Base Case at Minimum Guaranteed Volume) Total Project Cost $34M ROI 14.2% Net Present Value $25.7M Economic Impact Total Income Taxes (000's) Jobs (000's) $293,630 6,062 $21,729 Environmental Impact High Mid Low X Permit Required Customer / Regulatory Needs High X Mid Low Cruise Terminal 4 (CT-4) Redevelopment Total Project Cost $13M ROI 14.7% Net Present Value $8.1M Economic Impact Total Income Taxes (000's) Jobs (000's) $33,927 710 $2,511 Environmental Impact High Mid Low X Permit Required Customer / Regulatory Needs High X Mid Low Cruise Terminal 18 (CT-18) Parking Garage Construction (1600 Spaces Garage) Total Project Cost $32M ROI 5.6% Net Present Value $2.4M Economic Impact Total Income Taxes (000's) Jobs (000's) $172,127 3,844 $15,857 Environmental Impact High Mid Low X Permit Required Customer / Regulatory Needs High X Mid Low Southport Turning Notch Expansion Total Construction Cost $96M ROI 6.9% Net Present Value $14.3M Economic Impact Total Income Taxes (000's) Jobs (000's) $393,143 5,529 $29,092 November 6, 2015 Environmental Impact High Page 34 Mid X Low Permit Required X Customer / Regulatory Needs High X Mid Low 5-Year Master Plan Projects and Costs 5-Year Master Plan Years 2011 - 2015 Northport Midport Southport Port-wide Slip 1 New Bulkheads and Reconfiguration - Phase 1 By-Pass Road - Phase 1 By-Pass Road - Phase 2 Cruise Terminal #2 Improvements Cruise Terminal #4 Improvements New Petroleum Tank Farm Slip 2 Westward Lengthening Cruise Terminal #19 Improvements Cruise Terminal #21 Improvements Cruise Terminal #26 Improvements CT #18 Parking Garage Tracor Basin Finger Pier Replace with Catwalk+Dolphin McIntosh Road Improvements Upland Enhancement Westlake Mitigation Super Post Panamax Crane (1) Turning Notch Expansion - Contract 1 ICTF- Rail & Yard ACOE Deepening and Widening Design ACOE Deepening and Widening Construction (Depending on schedule) Total Estimated Cost (Millions) $ 55.00 $ 6.00 $ 30.00 $ 4.20 $ 13.00 $ 75.00 $ 23.00 $ 11.43 $ 5.05 $ 13.32 $ 32.00 $ 5.20 $ 11.20 $ 11.00 $ 12.60 $ 12.00 $ 67.08 $ 42.00 $ 4.00 $ $ FUNDED IN PRIOR CAPITAL BUDGETS November 6, 2015 Page 35 20.00 453.08 Projected Debt Service Coverage (2011-2015) 2011 2012 2013 2014 2015 Revenues $ 131,325,380 $ 147,380,705 $ 158,433,263 $ 159,927,413 $ 164,599,687 Expenses (80,788,110) (84,052,900) (90,771,940) (98,420,040) (102,770,870) Amount available for debt service $ 52,310,970 $ 63,783,705 $ 67,541,423 $ 61,232,773 $ 62,103,617 Existing debt service $ 32,043,144 $ 32,049,872 $ 32,043,681 $ 32,048,068 $ 32,050,655 New debt service - - - 2,980,516 10,924,806 Total debt service $ 32,043,144 $ 32,049,872 $ 32,043,681 $ 35,028,584 $ 42,975,461 Test (125%) 1.82 2.22 2.35 1.93 1.56 Test (110%) 1.63 1.99 2.11 1.75 1.45 - $ 27,095,599 $ 72,220,811 $ 50,071,844 Projected new debt required $ November 6, 2015 - $ Page 36 Projected Debt Service Coverage (2016-2020) 2016 2017 2018 2019 2020 Revenues $ 172,957,401 $ 179,599,260 $ 185,845,950 $ 195,986,420 $ 204,974,740 Expenses (107,952,560) (112,025,240) (118,941,410) (125,431,310) (131,183,830) Amount available for debt service $ 65,141,241 $ 67,895,220 $ 66,751,840 $ 70,473,510 $ 73,832,110 Existing debt service $ 32,051,244 $ 22,520,596 $ 22,523,588 $ 22,528,667 $ 22,527,702 New debt service 16,432,708 18,714,406 26,694,882 33,225,211 37,755,051 Total debt service $ 48,483,952 $ 41,235,002 $ 49,218,470 $ 55,753,878 $ 60,282,753 Test (125%) 1.44 1.79 1.45 1.34 1.30 Test (110%) 1.34 1.65 1.36 1.26 1.22 $ 20,742,711 $ 72,549,782 $ 59,366,630 $ 41,180,368 $ 43,350,643 Projected new debt required November 6, 2015 Page 37 Projected Debt Service Coverage Without Deepening (2011-2015) 2011 2012 2013 2014 2015 Revenues $ 131,325,380 $ 147,380,705 $ 158,433,263 $ 159,927,413 $ 164,599,687 Expenses (80,788,110) (84,052,900) (90,771,940) (98,420,040) (102,770,870) Amount available for debt service $ 52,310,970 $ 63,783,705 $ 67,541,423 $ 61,232,773 $ 62,103,617 Existing debt service New debt service $ 32,043,144 - $ 32,049,872 - $ 32,043,681 - $ 32,048,068 2,980,516 $ 32,050,655 10,924,806 Total debt service $ 32,043,144 $ 32,049,872 $ 32,043,681 $ 35,028,584 $ 42,975,461 Test (125%) 1.82 2.22 2.35 1.93 1.56 Test (110%) 1.63 1.99 2.11 1.75 1.45 - $ 27,095,599 $ 72,220,811 $ 30,071,844 Projected new debt required $ November 6, 2015 - $ Page 38 Projected Debt Service Coverage Without Deepening (2016-2020) 2016 2017 2018 2019 2020 Revenues $ 172,957,401 $ 179,599,260 $ 185,845,950 $ 195,986,420 $ 204,974,740 Expenses (107,952,560) (112,025,240) (118,941,410) (125,431,310) (131,183,830) Amount available for debt service $ 65,141,241 $ 67,895,220 $ 66,751,840 $ 70,473,510 $ 73,832,110 Existing debt service New debt service $ 32,051,244 14,232,708 $ 22,520,596 14,232,708 $ 22,523,588 16,939,895 $ 22,528,667 19,097,176 $ 22,527,702 22,072,933 Total debt service $ 46,283,952 $ 36,753,304 $ 39,463,483 $ 41,625,843 $ 44,600,635 Test (125%) 1.52 2.03 1.85 1.84 1.79 Test (110%) 1.41 1.85 1.69 1.69 1.66 - $ 24,610,795 $ 19,611,643 $ 27,052,333 $ 27,668,525 Projected new debt required $ November 6, 2015 Page 39 Estimated Cost Comparison of 2009 vs. 2006 Master/Vision Plans 2009 Cost ($M) 2006 Cost ($M) 5-Year Master Plan $ 453 $ 395 10-Year Vision Plan $547 $ 737 20-Year Vision Plan $461 $ 810 $1,461 $ 1,942 November 6, 2015 Page 40 Next Steps • Consideration of Adoption of Master/Vision Plan update by Board of County Commissioners • Upon adoption, the Deep Water Port Component of the County’s Comprehensive Plan will be modified www.portevergladesmasterplan.com November 6, 2015 Page 41