Construction of Facilities Dan Cloak Environmental Consulting Construction Workshop, May 2, 2012     Low Impact Development: What it is, what it does Runoff dispersal (“self-retaining.

Download Report

Transcript Construction of Facilities Dan Cloak Environmental Consulting Construction Workshop, May 2, 2012     Low Impact Development: What it is, what it does Runoff dispersal (“self-retaining.

Construction of Facilities
Dan Cloak
Environmental Consulting
Construction Workshop, May 2, 2012




Low Impact Development: What it is, what it does
Runoff dispersal (“self-retaining areas”)
Pervious pavements
Bioretention
 How facilities work and how they are sized
 What to watch for during construction
 Features
 Impervious surfaces:
roofs and pavement
 Catch basins and
piped drainage
 “Collect and
convey” design
objective
Site Scale
Watershed and Stream Scale
Higher peak flows
Flooding and scouring of stream beds
Lower time of concentration
Flash flows
Runoff from small storms
Discharge when runoff did not previously occur
Increased runoff durations
Stream erosion at moderate stream flow rates
Greater runoff volumes
Higher pollutant loading
Greater runoff energy
Conveys trash and gross pollutants to streams
Decreased infiltration
Lower and less frequent stream base flow
Dry weather discharges
High pollutant concentrations during low flows
Watershed and Stream Scale
Site scale
Reduce peak flows
Detain runoff on site
Increase time of concentration
Slow runoff from leaving site
No runoff from small storms
Infiltrate, evapotranspirate and reuse
Reduce duration of moderate flows
Let runoff seep away very slowly
Reduce runoff volume
Infiltrate and reuse where possible
Reduce runoff energy
Detain and slow flows
Increase groundwater storage and
stream base flows
Facilitate infiltration
Reduce pollutants in runoff
Detain and filter runoff
Protect against spills and dumping
Disconnect drainage and filter runoff
 Instead of “collect and convey,”
“slow it, spread it, sink it.”
 Avoid concentrating flows
 Keep drainage areas small
 Promote infiltration
 Detain
 Treat

Optimize the site
layout


Optimize the site
layout
Use pervious
surfaces and green
roofs where possible



Optimize the site
layout
Use pervious
surfaces and green
roofs where possible
Disperse runoff to
landscaping




Optimize the site
layout
Use pervious
surfaces and green
roofs where possible
Disperse runoff to
landscaping
Direct drainage from
impervious surfaces
to bioretention
facilities
 Rationale
 Produce no runoff from
“small” storms
 Also called “zero discharge”
areas
 Criteria
 Bermed or graded concave
 Slopes do not exceed 4%
 Amended soils and
vegetation to maintain soil
stability and permeability
 Inlets of area drains, if any,
3" minimum above
surrounding grade
 Rationale
 Self-retaining areas are
capable of ponding and
infiltrating some additional
runoff
 Criteria
 Ratio is not greater than 2:1
if treatment-only
requirements apply
 Ratio is not greater than 1:1
if flow-control requirements
apply
 Provide sufficient
ponding/storage depth
 Facilitate infiltration
 Variations







Pervious concrete
Porous asphalt
Porous pavers
Gravel
Open pavers
Solid unit pavers set on sand/gravel
Artificial turf
 Common Characteristics




Require a base course
Base course depth varies with soil type
More costly than conventional concrete or asphalt
Installation on slopes requires careful design
 Minimal compaction of underlying soil
 Check base course depth
 4 to 12 inches or more, depending on competence of
underlying soils
 Base course underdrains
 Consider omitting the underdrain and relying on
infiltration and lateral flow
 Perforated SDR 35 or equivalent
 Outlet elevation minimum 3" above bottom of base course
 Underdrain may be routed to storm drain
 Pavers
 Rigid edge required
 Solid pavers require 3/8" minimum gap
 Joints filled with open-graded aggregate free of fines
 Permeable concrete and pervious asphalt
 Installed by industry-certified professionals according to
vendor’s recommendations.
Overflow
Underdrain
i = 0.2 inches/hour
BMP Area/Impervious Area =
0.2/5 = 0.04
Surface Loading Rate
i = 5 inches/hour
1.00
Impervious
Mitigated Post-Project Site
Pre-Project Site
Q10
0.1Q2
0.90
0.80
Flow (cfs)
0.70
0.60
0.50
IMP Reduces Impervious Runoff
to Less Than Pre-Project Levels
0.40
0.30
0.20
0.10
0.00
0.00
0.05
0.10
0.15
0.20
0.25
% Time Exceeded
0.30
0.35
0.40
A
V1
V2
0.04
Overflow
2"
4"
Soil Mix
18"
Gravel
12"
Φ = 0.4
Facility
Design
Soil Group
A
Bioretention
B
Facility
C
D
A
FlowB
through
C
Planter
D
A
B
Dry Well
C
D
A
Cistern +
B
Bioretention
C
D
A
Bioretention
B
+ Vault
C
D
Area
Volume
A
V1
(ft2/ft2)
(ft3/ft2)
0.07
0.11
0.06
0.05
0.058
0.092
0.050
0.042
0.06
0.05
0.05
0.06
0.050
0.042
0.130
0.204
0.020
0.009
0.013
0.017
0.04
0.04
0.04
0.04
0.193
0.210
0.105
0.063
N/A
N/A
N/A
N/A
Volume
Rainfall
Adjustment
2
for Surface
3
(ft /ft2)
Area
No min.
Eq. 4-6
No min.
Eq. 4-7
0.066
Eq. 4-8
0.055
Eq. 4-9*
Not permitted in “A” soils
Not permitted in “B” soils
0.066
Eq. 4-8
0.055
Eq. 4-9*
N/A
Eq. 4-6
N/A
Eq. 4-7
Not permitted in “C” soils
Not permitted in “D” soils
N/A
Eq. 4-13
N/A
Eq. 4-14
N/A
Eq. 4-15
N/A
Eq. 4-16
0.096
N/A
0.220
N/A
0.152
N/A
0.064
N/A
V
Rainfall
Adjustment
for Storage
Volume
Eq. 4-6
Eq. 4-7
Eq. 4-8
Eq. 4-9
Maximum
Release
Rate
No orifice
No orifice
Eq. 4-10
Eq. 4-11
Eq. 4-8
Eq. 4-9
Eq. 4-6
Eq. 4-7
Eq. 4-10
Eq. 4-11
No release
No release
Eq. 4-6
Eq. 4-7
Eq. 4-8
Eq. 4-9
Eq. 4-6
Eq. 4-7
Eq. 4-8
Eq. 4-9
Eq. 4-17
Eq. 4-12
Eq. 4-10
Eq. 4-11
No release
Eq. 4-12
Eq. 4-10
Eq. 4-11

Drainage
area
includes
portions of
roof and of
parking lot
 Runoff may
enter by sheet
flow or be
piped.
 Roof leaders
can be piped
directly or spill
across
pavement
 Ensure is
consistent with
DMA
delineation
 Outlet structure
 Top of overflow grate
 Underdrain connection
 Inlet
 Flow line at inlet
 Top of curb
 Top of adjacent paving
 Soil layers
 Top of soil layer
 Bottom of gravel layer
 Bottom of soil layer
15"
Overflow
elevation
 Class 2 permeable
 Caltrans spec 68-1.025
 Typical to be slightly off
gradation spec on delivery
 No filter fabric
 Underdrain
 Near top of gravel layer
 PVC SDR 35 or equivalent; holes facing down
 Solid pipe for 2' closest to outlet structure
 Cleanout
 Now included in NPDES Permit
 60-70% Sand
 ASTM C33 for fine aggregate
 30-40% Compost
 Certified through US Composting
Council Seal of Testing Assurance
Program
 Submittal per Guidebook
 Option to accept test results for a
“brand-name” mix if volume is
less than 100 cubic yards
 Install in 8"-12" lifts
 Do not compact
 Do not overfill
 Leave room for mulch
 Maintain design
top of soil
elevation
 Trees
 Incorporate into
bioretention
facility
 Account for
surface roots
 Inspect each new facility within 45 days of
installation
 Inspect 20% of all facilities each year
 Inspect every facility at least once every
five years
 Stormwater C.3 Guidebook, 6th Edition
 www.cccleanwater.org/c3.html
 Or search “Contra Costa Stormwater”
 See in particular:
 Chapter 5, Construction Checklist
 Design sheets at end of Chapter 4
 Appendix B, Soils/Plantings/Irrigation
for Bioretention Facilities