Big Trout Lake Stormwater Management Design Project By Hannah Rollin Problem  Valuable Trout Lake for the state of Minnesota  Excess sediment and stormwater flows directly into.

Download Report

Transcript Big Trout Lake Stormwater Management Design Project By Hannah Rollin Problem  Valuable Trout Lake for the state of Minnesota  Excess sediment and stormwater flows directly into.

Slide 1

Big Trout Lake
Stormwater
Management Design
Project
By Hannah Rollin

Problem

 Valuable Trout Lake for the state of Minnesota
 Excess sediment and stormwater flows directly
into the lake due to the current curb and
gutter system and the culvert
 Increasing temperature of the lake and
decreasing the clarity

Constraints

Limited land area available
Snowmobile route

Steep slopes (instability)

Field Assessment

 Surface and groundwater measurements
 Temperature
 Salinity

 Soil type assessment
 General land type observations

Proposed Solution
 Use a vortex separator to remove sediment from the
stormwater
 Downstream Defender®
 The vortex system forces particles to settle into the sump
 Efficient and easy to maintain
 Small footprint

 System of Perforated Pipes
 Infiltration of stormwater will aid in temperature reduction

Watershed and Drainage
Assessment
 Delineate the watershed in GIS
 Calculate drainage area:
 Grass/Vegetated area: 167,277ft2
 Paved area: 156,722 ft2

 Calculate runoff from precipitation data
 37,040 ft3

Final Design

Two 4ft Downstream Defenders (each
can handle 8cfs)
12 perforated pipes, 2ft in diameter

Next Steps
 Research possibility of installing larger pipes for
larger storage volume
 Survey elevations to calculate gradients of
pipes
 Cost analysis
 Questions?


Slide 2

Big Trout Lake
Stormwater
Management Design
Project
By Hannah Rollin

Problem

 Valuable Trout Lake for the state of Minnesota
 Excess sediment and stormwater flows directly
into the lake due to the current curb and
gutter system and the culvert
 Increasing temperature of the lake and
decreasing the clarity

Constraints

Limited land area available
Snowmobile route

Steep slopes (instability)

Field Assessment

 Surface and groundwater measurements
 Temperature
 Salinity

 Soil type assessment
 General land type observations

Proposed Solution
 Use a vortex separator to remove sediment from the
stormwater
 Downstream Defender®
 The vortex system forces particles to settle into the sump
 Efficient and easy to maintain
 Small footprint

 System of Perforated Pipes
 Infiltration of stormwater will aid in temperature reduction

Watershed and Drainage
Assessment
 Delineate the watershed in GIS
 Calculate drainage area:
 Grass/Vegetated area: 167,277ft2
 Paved area: 156,722 ft2

 Calculate runoff from precipitation data
 37,040 ft3

Final Design

Two 4ft Downstream Defenders (each
can handle 8cfs)
12 perforated pipes, 2ft in diameter

Next Steps
 Research possibility of installing larger pipes for
larger storage volume
 Survey elevations to calculate gradients of
pipes
 Cost analysis
 Questions?


Slide 3

Big Trout Lake
Stormwater
Management Design
Project
By Hannah Rollin

Problem

 Valuable Trout Lake for the state of Minnesota
 Excess sediment and stormwater flows directly
into the lake due to the current curb and
gutter system and the culvert
 Increasing temperature of the lake and
decreasing the clarity

Constraints

Limited land area available
Snowmobile route

Steep slopes (instability)

Field Assessment

 Surface and groundwater measurements
 Temperature
 Salinity

 Soil type assessment
 General land type observations

Proposed Solution
 Use a vortex separator to remove sediment from the
stormwater
 Downstream Defender®
 The vortex system forces particles to settle into the sump
 Efficient and easy to maintain
 Small footprint

 System of Perforated Pipes
 Infiltration of stormwater will aid in temperature reduction

Watershed and Drainage
Assessment
 Delineate the watershed in GIS
 Calculate drainage area:
 Grass/Vegetated area: 167,277ft2
 Paved area: 156,722 ft2

 Calculate runoff from precipitation data
 37,040 ft3

Final Design

Two 4ft Downstream Defenders (each
can handle 8cfs)
12 perforated pipes, 2ft in diameter

Next Steps
 Research possibility of installing larger pipes for
larger storage volume
 Survey elevations to calculate gradients of
pipes
 Cost analysis
 Questions?


Slide 4

Big Trout Lake
Stormwater
Management Design
Project
By Hannah Rollin

Problem

 Valuable Trout Lake for the state of Minnesota
 Excess sediment and stormwater flows directly
into the lake due to the current curb and
gutter system and the culvert
 Increasing temperature of the lake and
decreasing the clarity

Constraints

Limited land area available
Snowmobile route

Steep slopes (instability)

Field Assessment

 Surface and groundwater measurements
 Temperature
 Salinity

 Soil type assessment
 General land type observations

Proposed Solution
 Use a vortex separator to remove sediment from the
stormwater
 Downstream Defender®
 The vortex system forces particles to settle into the sump
 Efficient and easy to maintain
 Small footprint

 System of Perforated Pipes
 Infiltration of stormwater will aid in temperature reduction

Watershed and Drainage
Assessment
 Delineate the watershed in GIS
 Calculate drainage area:
 Grass/Vegetated area: 167,277ft2
 Paved area: 156,722 ft2

 Calculate runoff from precipitation data
 37,040 ft3

Final Design

Two 4ft Downstream Defenders (each
can handle 8cfs)
12 perforated pipes, 2ft in diameter

Next Steps
 Research possibility of installing larger pipes for
larger storage volume
 Survey elevations to calculate gradients of
pipes
 Cost analysis
 Questions?


Slide 5

Big Trout Lake
Stormwater
Management Design
Project
By Hannah Rollin

Problem

 Valuable Trout Lake for the state of Minnesota
 Excess sediment and stormwater flows directly
into the lake due to the current curb and
gutter system and the culvert
 Increasing temperature of the lake and
decreasing the clarity

Constraints

Limited land area available
Snowmobile route

Steep slopes (instability)

Field Assessment

 Surface and groundwater measurements
 Temperature
 Salinity

 Soil type assessment
 General land type observations

Proposed Solution
 Use a vortex separator to remove sediment from the
stormwater
 Downstream Defender®
 The vortex system forces particles to settle into the sump
 Efficient and easy to maintain
 Small footprint

 System of Perforated Pipes
 Infiltration of stormwater will aid in temperature reduction

Watershed and Drainage
Assessment
 Delineate the watershed in GIS
 Calculate drainage area:
 Grass/Vegetated area: 167,277ft2
 Paved area: 156,722 ft2

 Calculate runoff from precipitation data
 37,040 ft3

Final Design

Two 4ft Downstream Defenders (each
can handle 8cfs)
12 perforated pipes, 2ft in diameter

Next Steps
 Research possibility of installing larger pipes for
larger storage volume
 Survey elevations to calculate gradients of
pipes
 Cost analysis
 Questions?


Slide 6

Big Trout Lake
Stormwater
Management Design
Project
By Hannah Rollin

Problem

 Valuable Trout Lake for the state of Minnesota
 Excess sediment and stormwater flows directly
into the lake due to the current curb and
gutter system and the culvert
 Increasing temperature of the lake and
decreasing the clarity

Constraints

Limited land area available
Snowmobile route

Steep slopes (instability)

Field Assessment

 Surface and groundwater measurements
 Temperature
 Salinity

 Soil type assessment
 General land type observations

Proposed Solution
 Use a vortex separator to remove sediment from the
stormwater
 Downstream Defender®
 The vortex system forces particles to settle into the sump
 Efficient and easy to maintain
 Small footprint

 System of Perforated Pipes
 Infiltration of stormwater will aid in temperature reduction

Watershed and Drainage
Assessment
 Delineate the watershed in GIS
 Calculate drainage area:
 Grass/Vegetated area: 167,277ft2
 Paved area: 156,722 ft2

 Calculate runoff from precipitation data
 37,040 ft3

Final Design

Two 4ft Downstream Defenders (each
can handle 8cfs)
12 perforated pipes, 2ft in diameter

Next Steps
 Research possibility of installing larger pipes for
larger storage volume
 Survey elevations to calculate gradients of
pipes
 Cost analysis
 Questions?


Slide 7

Big Trout Lake
Stormwater
Management Design
Project
By Hannah Rollin

Problem

 Valuable Trout Lake for the state of Minnesota
 Excess sediment and stormwater flows directly
into the lake due to the current curb and
gutter system and the culvert
 Increasing temperature of the lake and
decreasing the clarity

Constraints

Limited land area available
Snowmobile route

Steep slopes (instability)

Field Assessment

 Surface and groundwater measurements
 Temperature
 Salinity

 Soil type assessment
 General land type observations

Proposed Solution
 Use a vortex separator to remove sediment from the
stormwater
 Downstream Defender®
 The vortex system forces particles to settle into the sump
 Efficient and easy to maintain
 Small footprint

 System of Perforated Pipes
 Infiltration of stormwater will aid in temperature reduction

Watershed and Drainage
Assessment
 Delineate the watershed in GIS
 Calculate drainage area:
 Grass/Vegetated area: 167,277ft2
 Paved area: 156,722 ft2

 Calculate runoff from precipitation data
 37,040 ft3

Final Design

Two 4ft Downstream Defenders (each
can handle 8cfs)
12 perforated pipes, 2ft in diameter

Next Steps
 Research possibility of installing larger pipes for
larger storage volume
 Survey elevations to calculate gradients of
pipes
 Cost analysis
 Questions?


Slide 8

Big Trout Lake
Stormwater
Management Design
Project
By Hannah Rollin

Problem

 Valuable Trout Lake for the state of Minnesota
 Excess sediment and stormwater flows directly
into the lake due to the current curb and
gutter system and the culvert
 Increasing temperature of the lake and
decreasing the clarity

Constraints

Limited land area available
Snowmobile route

Steep slopes (instability)

Field Assessment

 Surface and groundwater measurements
 Temperature
 Salinity

 Soil type assessment
 General land type observations

Proposed Solution
 Use a vortex separator to remove sediment from the
stormwater
 Downstream Defender®
 The vortex system forces particles to settle into the sump
 Efficient and easy to maintain
 Small footprint

 System of Perforated Pipes
 Infiltration of stormwater will aid in temperature reduction

Watershed and Drainage
Assessment
 Delineate the watershed in GIS
 Calculate drainage area:
 Grass/Vegetated area: 167,277ft2
 Paved area: 156,722 ft2

 Calculate runoff from precipitation data
 37,040 ft3

Final Design

Two 4ft Downstream Defenders (each
can handle 8cfs)
12 perforated pipes, 2ft in diameter

Next Steps
 Research possibility of installing larger pipes for
larger storage volume
 Survey elevations to calculate gradients of
pipes
 Cost analysis
 Questions?


Slide 9

Big Trout Lake
Stormwater
Management Design
Project
By Hannah Rollin

Problem

 Valuable Trout Lake for the state of Minnesota
 Excess sediment and stormwater flows directly
into the lake due to the current curb and
gutter system and the culvert
 Increasing temperature of the lake and
decreasing the clarity

Constraints

Limited land area available
Snowmobile route

Steep slopes (instability)

Field Assessment

 Surface and groundwater measurements
 Temperature
 Salinity

 Soil type assessment
 General land type observations

Proposed Solution
 Use a vortex separator to remove sediment from the
stormwater
 Downstream Defender®
 The vortex system forces particles to settle into the sump
 Efficient and easy to maintain
 Small footprint

 System of Perforated Pipes
 Infiltration of stormwater will aid in temperature reduction

Watershed and Drainage
Assessment
 Delineate the watershed in GIS
 Calculate drainage area:
 Grass/Vegetated area: 167,277ft2
 Paved area: 156,722 ft2

 Calculate runoff from precipitation data
 37,040 ft3

Final Design

Two 4ft Downstream Defenders (each
can handle 8cfs)
12 perforated pipes, 2ft in diameter

Next Steps
 Research possibility of installing larger pipes for
larger storage volume
 Survey elevations to calculate gradients of
pipes
 Cost analysis
 Questions?


Slide 10

Big Trout Lake
Stormwater
Management Design
Project
By Hannah Rollin

Problem

 Valuable Trout Lake for the state of Minnesota
 Excess sediment and stormwater flows directly
into the lake due to the current curb and
gutter system and the culvert
 Increasing temperature of the lake and
decreasing the clarity

Constraints

Limited land area available
Snowmobile route

Steep slopes (instability)

Field Assessment

 Surface and groundwater measurements
 Temperature
 Salinity

 Soil type assessment
 General land type observations

Proposed Solution
 Use a vortex separator to remove sediment from the
stormwater
 Downstream Defender®
 The vortex system forces particles to settle into the sump
 Efficient and easy to maintain
 Small footprint

 System of Perforated Pipes
 Infiltration of stormwater will aid in temperature reduction

Watershed and Drainage
Assessment
 Delineate the watershed in GIS
 Calculate drainage area:
 Grass/Vegetated area: 167,277ft2
 Paved area: 156,722 ft2

 Calculate runoff from precipitation data
 37,040 ft3

Final Design

Two 4ft Downstream Defenders (each
can handle 8cfs)
12 perforated pipes, 2ft in diameter

Next Steps
 Research possibility of installing larger pipes for
larger storage volume
 Survey elevations to calculate gradients of
pipes
 Cost analysis
 Questions?


Slide 11

Big Trout Lake
Stormwater
Management Design
Project
By Hannah Rollin

Problem

 Valuable Trout Lake for the state of Minnesota
 Excess sediment and stormwater flows directly
into the lake due to the current curb and
gutter system and the culvert
 Increasing temperature of the lake and
decreasing the clarity

Constraints

Limited land area available
Snowmobile route

Steep slopes (instability)

Field Assessment

 Surface and groundwater measurements
 Temperature
 Salinity

 Soil type assessment
 General land type observations

Proposed Solution
 Use a vortex separator to remove sediment from the
stormwater
 Downstream Defender®
 The vortex system forces particles to settle into the sump
 Efficient and easy to maintain
 Small footprint

 System of Perforated Pipes
 Infiltration of stormwater will aid in temperature reduction

Watershed and Drainage
Assessment
 Delineate the watershed in GIS
 Calculate drainage area:
 Grass/Vegetated area: 167,277ft2
 Paved area: 156,722 ft2

 Calculate runoff from precipitation data
 37,040 ft3

Final Design

Two 4ft Downstream Defenders (each
can handle 8cfs)
12 perforated pipes, 2ft in diameter

Next Steps
 Research possibility of installing larger pipes for
larger storage volume
 Survey elevations to calculate gradients of
pipes
 Cost analysis
 Questions?


Slide 12

Big Trout Lake
Stormwater
Management Design
Project
By Hannah Rollin

Problem

 Valuable Trout Lake for the state of Minnesota
 Excess sediment and stormwater flows directly
into the lake due to the current curb and
gutter system and the culvert
 Increasing temperature of the lake and
decreasing the clarity

Constraints

Limited land area available
Snowmobile route

Steep slopes (instability)

Field Assessment

 Surface and groundwater measurements
 Temperature
 Salinity

 Soil type assessment
 General land type observations

Proposed Solution
 Use a vortex separator to remove sediment from the
stormwater
 Downstream Defender®
 The vortex system forces particles to settle into the sump
 Efficient and easy to maintain
 Small footprint

 System of Perforated Pipes
 Infiltration of stormwater will aid in temperature reduction

Watershed and Drainage
Assessment
 Delineate the watershed in GIS
 Calculate drainage area:
 Grass/Vegetated area: 167,277ft2
 Paved area: 156,722 ft2

 Calculate runoff from precipitation data
 37,040 ft3

Final Design

Two 4ft Downstream Defenders (each
can handle 8cfs)
12 perforated pipes, 2ft in diameter

Next Steps
 Research possibility of installing larger pipes for
larger storage volume
 Survey elevations to calculate gradients of
pipes
 Cost analysis
 Questions?


Slide 13

Big Trout Lake
Stormwater
Management Design
Project
By Hannah Rollin

Problem

 Valuable Trout Lake for the state of Minnesota
 Excess sediment and stormwater flows directly
into the lake due to the current curb and
gutter system and the culvert
 Increasing temperature of the lake and
decreasing the clarity

Constraints

Limited land area available
Snowmobile route

Steep slopes (instability)

Field Assessment

 Surface and groundwater measurements
 Temperature
 Salinity

 Soil type assessment
 General land type observations

Proposed Solution
 Use a vortex separator to remove sediment from the
stormwater
 Downstream Defender®
 The vortex system forces particles to settle into the sump
 Efficient and easy to maintain
 Small footprint

 System of Perforated Pipes
 Infiltration of stormwater will aid in temperature reduction

Watershed and Drainage
Assessment
 Delineate the watershed in GIS
 Calculate drainage area:
 Grass/Vegetated area: 167,277ft2
 Paved area: 156,722 ft2

 Calculate runoff from precipitation data
 37,040 ft3

Final Design

Two 4ft Downstream Defenders (each
can handle 8cfs)
12 perforated pipes, 2ft in diameter

Next Steps
 Research possibility of installing larger pipes for
larger storage volume
 Survey elevations to calculate gradients of
pipes
 Cost analysis
 Questions?


Slide 14

Big Trout Lake
Stormwater
Management Design
Project
By Hannah Rollin

Problem

 Valuable Trout Lake for the state of Minnesota
 Excess sediment and stormwater flows directly
into the lake due to the current curb and
gutter system and the culvert
 Increasing temperature of the lake and
decreasing the clarity

Constraints

Limited land area available
Snowmobile route

Steep slopes (instability)

Field Assessment

 Surface and groundwater measurements
 Temperature
 Salinity

 Soil type assessment
 General land type observations

Proposed Solution
 Use a vortex separator to remove sediment from the
stormwater
 Downstream Defender®
 The vortex system forces particles to settle into the sump
 Efficient and easy to maintain
 Small footprint

 System of Perforated Pipes
 Infiltration of stormwater will aid in temperature reduction

Watershed and Drainage
Assessment
 Delineate the watershed in GIS
 Calculate drainage area:
 Grass/Vegetated area: 167,277ft2
 Paved area: 156,722 ft2

 Calculate runoff from precipitation data
 37,040 ft3

Final Design

Two 4ft Downstream Defenders (each
can handle 8cfs)
12 perforated pipes, 2ft in diameter

Next Steps
 Research possibility of installing larger pipes for
larger storage volume
 Survey elevations to calculate gradients of
pipes
 Cost analysis
 Questions?


Slide 15

Big Trout Lake
Stormwater
Management Design
Project
By Hannah Rollin

Problem

 Valuable Trout Lake for the state of Minnesota
 Excess sediment and stormwater flows directly
into the lake due to the current curb and
gutter system and the culvert
 Increasing temperature of the lake and
decreasing the clarity

Constraints

Limited land area available
Snowmobile route

Steep slopes (instability)

Field Assessment

 Surface and groundwater measurements
 Temperature
 Salinity

 Soil type assessment
 General land type observations

Proposed Solution
 Use a vortex separator to remove sediment from the
stormwater
 Downstream Defender®
 The vortex system forces particles to settle into the sump
 Efficient and easy to maintain
 Small footprint

 System of Perforated Pipes
 Infiltration of stormwater will aid in temperature reduction

Watershed and Drainage
Assessment
 Delineate the watershed in GIS
 Calculate drainage area:
 Grass/Vegetated area: 167,277ft2
 Paved area: 156,722 ft2

 Calculate runoff from precipitation data
 37,040 ft3

Final Design

Two 4ft Downstream Defenders (each
can handle 8cfs)
12 perforated pipes, 2ft in diameter

Next Steps
 Research possibility of installing larger pipes for
larger storage volume
 Survey elevations to calculate gradients of
pipes
 Cost analysis
 Questions?


Slide 16

Big Trout Lake
Stormwater
Management Design
Project
By Hannah Rollin

Problem

 Valuable Trout Lake for the state of Minnesota
 Excess sediment and stormwater flows directly
into the lake due to the current curb and
gutter system and the culvert
 Increasing temperature of the lake and
decreasing the clarity

Constraints

Limited land area available
Snowmobile route

Steep slopes (instability)

Field Assessment

 Surface and groundwater measurements
 Temperature
 Salinity

 Soil type assessment
 General land type observations

Proposed Solution
 Use a vortex separator to remove sediment from the
stormwater
 Downstream Defender®
 The vortex system forces particles to settle into the sump
 Efficient and easy to maintain
 Small footprint

 System of Perforated Pipes
 Infiltration of stormwater will aid in temperature reduction

Watershed and Drainage
Assessment
 Delineate the watershed in GIS
 Calculate drainage area:
 Grass/Vegetated area: 167,277ft2
 Paved area: 156,722 ft2

 Calculate runoff from precipitation data
 37,040 ft3

Final Design

Two 4ft Downstream Defenders (each
can handle 8cfs)
12 perforated pipes, 2ft in diameter

Next Steps
 Research possibility of installing larger pipes for
larger storage volume
 Survey elevations to calculate gradients of
pipes
 Cost analysis
 Questions?