Procedure for commissioning the SRTPV system
AEE S/D
Application

Submit the Application(F1)
Acknowledgement
Approval letter for
installation ( F5 or F6)
180 days

7 days

Work completion report(F7)
Report of Commissioning (F8)

7 days

Synchronizing Certificate (F8A)
Section office(F4)