POLITECNICO DI TORINO

Post Graduated Master Course
TUNNELLING AND TUNNEL BORING MACHINES
Subject of the lesson : RME270 series 24000
“Perllongament dels FGC a Terrassa”
Lecturer : René Raúl Ramírez Vázquez
Golden Sponsors

Sponsors

Academic Year: 2009-10


Slide 2

POLITECNICO DI TORINO

Presentation Overview
Tunnel Alignment
Geology
General Specifications
Site Assembly Challenge

Production
Operation Challenges
Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 3

POLITECNICO DI TORINO

Presentation Overview
Tunnel Alignment
Geology
General Specifications
Site Assembly Challenge

Production
Operation Challenges
Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 4

POLITECNICO DI TORINO

Tunnel Alignment
Main Pit
Rambla

Renfe

Can Roca

Vallparadis
Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 5

POLITECNICO DI TORINO

Tunnel Alignment Challenge
Hazardous Surface Structures

Can Roca

Renfe

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 6

POLITECNICO DI TORINO

Tunnel Alignment Challenge
Hazardous Surface Structures

Can Roca

Renfe

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 7

POLITECNICO DI TORINO

Tunnel Alignment Challenge
Hazardous Surface Structures

Can Roca

Renfe

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 8

POLITECNICO DI TORINO

Tunnel Alignment Challenge
Hazardous Surface Structures

Can Roca

Renfe

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 9

POLITECNICO DI TORINO

Tunnel Alignment Challenge
Consecutive Curves with Minimum Radius

Vallparadis

Rambla

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 10

POLITECNICO DI TORINO

Tunnel Alignment Challenge
Consecutive Curves with Minimum Radius

Vallparadis

Rambla

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 11

POLITECNICO DI TORINO

Tunnel Alignment Challenge
Consecutive Curves with Minimum Radius

Vallparadis

Rambla

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 12

POLITECNICO DI TORINO

Tunnel Alignment Challenge
Consecutive Curves with Minimum Radius

Vallparadis

Rambla

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 13

POLITECNICO DI TORINO

Presentation Overview
Tunnel Alignment
Geology
General Specifications
Site Assembly Challenge

Production
Operation Challenges
Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 14

POLITECNICO DI TORINO

Geology
Can Roca

Pleistocene: Mud, Sand and Gravel

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES

Main Pit


Slide 15

POLITECNICO DI TORINO

Geology
Rambla

Clay of Tertiary Origin

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES

Can Roca


Slide 16

POLITECNICO DI TORINO

Presentation Overview
Tunnel Alignment
Geology
General Specifications
Site Assembly Challenge

Production
Operation Challenges
Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 17

POLITECNICO DI TORINO

RME270 Series 24000 Terrassa

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 18

POLITECNICO DI TORINO

General Specifications
•
•
•
•
•
•
•
•
•
•
•
•

Mixed Face EPB
Cut Diameter:
TBM Length:
Overall Length:
Installed Power:
Design Operating Pressure:
Min. Radius of Curvature:
Electric Drive
Maximum Continuous Torque
Drive Maximum Speed
Propulsion Cylinders
Total Maximum Thrust

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES

6.884 m
9.975 m
122 m
2812 kW
4 bar
160 m
1035 Tm
3.01 RPM
26
6592 Tonne


Slide 19

POLITECNICO DI TORINO

Presentation Overview
Tunnel Alignment
Geology
General Specifications
Site Assembly Challenge
Production

Operation Challenges
Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 20

POLITECNICO DI TORINO

Full TBM Assemble Before Launch

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 21

POLITECNICO DI TORINO

Presentation Overview
Tunnel Alignment
Geology
General Specifications
Site Assembly Challenge

Production
Operation Challenges
Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 22

POLITECNICO DI TORINO

Production Rates
•
•
•
•
•
•
•
•

Average Advance Rate:
Average Penetration:
Best Production (24 Hours):
Best Shift (12 Hours):
Best month:
Average Torque:
Average Thrust:
GCS Injection Rate:

65 mm/min
36.2 mm/RPM
33 Rings (49.5M)
19 Rings (28.5M)
389 Rings (583M)
298 Tm (28.7%)
938 Tonne (14.2%)
1800 LPM (51.4%)

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 23

POLITECNICO DI TORINO

Performance
2500

@RAMBLA
389 DAYS
AFTER

@NEW YEAR BREAK
2009-2010
2000

@VALLPARADIS
1364 Rings, 282 Days

1500

@RENFE
824 Rings, 163 Days

1000

@CAN ROCA
126 Rings, 48 Days
500

0
0

50

100

150

200

250

300

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES

350

400

450


Slide 24

POLITECNICO DI TORINO

Accumulated Rings x 12 Hours Shift
50% Total Production

300

275

250
250

198

200

168 152
150

Great!

100

50

19
0
1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

Rings
Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES

16

17

18

19

20


Slide 25

POLITECNICO DI TORINO

Presentation Overview
Tunnel Alignment
Geology
General Specifications
Site Assembly Challenge

Production
Operation Challenges
Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 26

POLITECNICO DI TORINO

Operation Challenges
• EPB Cells
• Material Weigh Control
• Stations Crossing

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 27

POLITECNICO DI TORINO

EPB Bulkhead Cells
P0
P6

P1

P5

P2

P4

P3

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 28

POLITECNICO DI TORINO

EPB Collapse Cells
Forward Shield

Stationary Shield

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 29

POLITECNICO DI TORINO

EPB Cells Display

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 30

POLITECNICO DI TORINO

Material Weigh Control
• Independent Weigh Scales
• Independent Instrumented Volume
o Low Pressure Water
o High Pressure Water
o Bentonite System
o Ground Conditioning

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 31

POLITECNICO DI TORINO

Material Weigh Control

Original Setup, Two Scales and One Integrator
Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 32

POLITECNICO DI TORINO

Material Weigh Control

Modified Setup, Two Scales and Two Integrators
Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 33

POLITECNICO DI TORINO

Material Weigh Control
GCS

Material

28%

60%

4%

Bentonite

6%
2%

LP Water
HP Water

Volume: 69,25 m3
Bulking Factor: 1,25
Average: 122 Tonnes
Deviation: +/- 15,7 T

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 34

POLITECNICO DI TORINO

Station Crossing “Can Roca”

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 35

POLITECNICO DI TORINO

Station Crossing “Can Roca”

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 36

POLITECNICO DI TORINO

Station Crossing “Vallparadis”

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 37

POLITECNICO DI TORINO

Station Crossing “Vallparadis”

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 38

POLITECNICO DI TORINO

Station Crossing “Vallparadis”

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 39

POLITECNICO DI TORINO

Station Crossing “Vallparadis”

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 40

POLITECNICO DI TORINO

Station Crossing “Vallparadis”

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES


Slide 41

POLITECNICO DI TORINO

www.

.com

Academic Year: 2009-10
Post Graduate Master Course
TUNNELLING AND TUNNEL BORING MACHINES