ALICE TOF DCS Answers to DCS Commissioning and Installation related questions ALICE week at CERN O.
Download ReportTranscript ALICE TOF DCS Answers to DCS Commissioning and Installation related questions ALICE week at CERN O.
ALICE TOF DCS Answers to DCS Commissioning and Installation related questions ALICE week at CERN O. Pinazza and the TOF team CERN, 2007-03-06 O.Pinazza: ALICE TOF DCS 1 Subsystems HV LV FEE Cooling Gas VME CERN, 2007-03-06 O.Pinazza: ALICE TOF DCS 2 Sub systems status • HV – – – • PVSS: ok for both 3.1 and 3.6 (with FW and OPC, custom and standard panels) FSM: ok on 3.1, not ported yet on 3.6 HW: 2 SY1527 delivered, ready to be installed in CR4-Z02 and CR4-Z03, needs of 1-ph power and ethernet connection, besides HV cables (tested, few connectors missing) LV – – – PVSS: fwCAEN is working correctly with 3.6, worse with 3.1, standard panels FSM: (see FSM for HV) HW: • • • FEE – – – • • • 4 SY1527 and branch controllers delivered, 2 ready to be installed (racks O03-O32, I03-I32, needs of 1ph power, eth, EASY bus patch) 12 Maciste: 1 to 2 ready to be installed in racks O04-O31 (1ph power –svc-, 3-ph power, EASY bus, LV bars) PVSS: ok, dpt and dp ready, simple panels, DIM -services and commands- prepared, tested, strictly FED compliant FSM: not ready HW: 2 SM installed with FEE devices, lab setup at Cern and in Italy (see Integration); needs for optical fibers to PCs in CR3, cooling on SM08 Cooling: PVSS, FSM, HW unknown GAS: PVSS, FSM, HW unknown VME: PVSS, FSM, HW unknown CERN, 2007-03-06 O.Pinazza: ALICE TOF DCS 3 TOF DCS SW issues • PVSS 3.1 SP2 – HV, FEE and FSM projects ok – LV (with new fwCAEN) not yet correct (OPC addresses) • PVSS 3.6 – HV, LV, FEE projects ok – Unable to convert any of the previous projects – Unable to convert FSM project HV LV FEE FSM PVSS 3.1 ok no ok ok PVSS 3.6 ok ok ok wip CERN, 2007-03-06 O.Pinazza: ALICE TOF DCS (frozen) ECS interfaced development 4 ECS © F.Cindolo FSM TOF TOF_SM00 TOF_SM08 work in progress HV LV FEE … … … CAEN Ch CAEN Ch ©P.Antonioli OPC CAEN DIM devices OPC DIM CTRL PC CAEN FERO CERN, 2007-03-06 O.Pinazza: ALICE TOF DCS 5 TOF_DCS_NODE Applies to: TOF_DCS, TOF_NN_DCS, TOF_INFRA TOF_DCS RECOVER OFF GO_STANDBY CONFIGURE (RUNMODE) MOVING_STBY_CONF GO_OFF STANDBY GO_STANDBY STBY_CONFIGURED ERROR CALIBRATE CALIBRATING GO_READY MOVING_READY READY All states can fall to the ERROR state GO_STBY_CONF CERN, 2007-03-06 O.Pinazza: ALICE TOF DCS 6 Installation at P2 CERN, 2007-03-06 O.Pinazza: ALICE TOF DCS 7 Installation news Supermodule 08 • Starting probably this week, the supermodule will finally be pushed in its final position • At present, our effort is to set all the connections and services needed for the SM to be switched on, operated and tested as soon as possible Cables, connections and services in the pit are not fully available 1-ph power 3-ph power LV bars Ethernet Easy bus HV connections (CR4) Optical fibers After last survey at Point 2, we‘re still missing many connectors (rack side). This/next week we’ll hopefully begin to install devices in the racks in UX and CR CERN, 2007-03-06 O.Pinazza: ALICE TOF DCS 8 Final Installation at P2 • Complete SW with PVSS 3.6 – A running (but not final) version is going to be installed in the next days, to test and operate the first SMs – Complete system: not before mid May • Network, cables and connectors – To be checked early this week • Devices – Hopefully this week: • HV PS in CR4 • LV PS (SY and Maciste) side O – PCs: 4/21 linux “farm” pc ready in CR3 (remaining 17 not before May) CERN, 2007-03-06 O.Pinazza: ALICE TOF DCS 9 Integration CERN, 2007-03-06 O.Pinazza: ALICE TOF DCS 10 DCS+ECS F. Cindolo CERN, 2007-03-06 O.Pinazza: ALICE TOF DCS 11 Integration • DAQ, DA, ECS validated (Dec ’06-Feb ‘07) • Further integration tests to be performed in the TOF lab at Cern: – February 28: Test of ECS+DCS (CERN, TOF) – March 19-22: Integration test for all DCS components of TOF in ECS (TOF) with real HW – April 10-13: Combined test with TRG, DAQ, DCS, ECS, DA on real HW CERN, 2007-03-06 O.Pinazza: ALICE TOF DCS 12 Conclusions • SW: Main PVSS subprojects are beings used in the TOF lab; not in their final version, but almost fully functional – Still missing: alarms, interlocks, Oracle archiving, complex FEE procedures (ex. Calibration, error recovery actions), FSM-FEE tree • HW: Most of the hardware has been delivered and the first devices are being installed probably this week to test SM08 • Integration tests have started CERN, 2007-03-06 O.Pinazza: ALICE TOF DCS 13