Day 1, 9h45. 1st presentation, Objectives and description of the

Download Report

Transcript Day 1, 9h45. 1st presentation, Objectives and description of the

CARBON PARTNERSHIP FACILITY
APRIL 2014 SELLER PARTICIPANT TRAINING
OVERVIEW OF VIETNAM RENEWABLE ENERGY
DEVELOPMENT PROGRAM (REDP)
OPERATIONS PLAN
CARBON PARTNERSHIP FACILITY
1
Training on CDM Operations Plans and Sub-ERPA Contracting
presented by
Dr. Balasankari
01 April 2014
CARBON PARTNERSHIP FACILITY
2
Training on CDM Operations Plans and Sub-ERPA Contracting
General sections in operations manual
 Overview of CDM PoA
 Institutional structure and implementation arrangement
 Main program activities
 CPA preparation and inclusion process
 Responsibilities of CME and CPA implementer
 Data monitoring & database management
 Quality Assurance (QA) and Quality Control (QC)
 Forms and format to be used
CARBON PARTNERSHIP FACILITY
3
Training on CDM Operations Plans and Sub-ERPA Contracting
General PoA process
CARBON PARTNERSHIP FACILITY
4
Training on CDM Operations Plans and Sub-ERPA Contracting
Vietnam REDP Programme
• Around 15 - 25 Small Hydro power (SHP) plants with
maximum capacity up to 30 MW to be installed
• Coordinating/Managing Entity - Ministry of Industry and
Trade (MOIT)
• Other stakeholders




Ministry of Finance (MOF)
Participating Banks (PBs)
Dam Safety Review Panel (DSRP)
CPA Implementers ( Project Owners)
CARBON PARTNERSHIP FACILITY
5
Training on CDM Operations Plans and Sub-ERPA Contracting
REDP - Implementation Structure
Re-financing by
Ministry of Finance
(MOF)
Ministry of Industry and
Trade (MOIT) - CME
Dam Safety Review Panel
(DSRP)
Project Management Board
(PMB)
CPA Implementers
(Project developers)
Participating Banks
PB 1
SHP 1
CARBON PARTNERSHIP FACILITY
SHP 2
PB 2
PB 3
SHP 3
6
Training on CDM Operations Plans and Sub-ERPA Contracting
REDP - Implementation Structure
Proper functioning of implementation structure is CME’s
responsibility
How CME can ensure effective functioning of implementation
structure ?

Make all stakeholders aware of programme structure
 Establish clear communication channels between stakeholders
 Organize meeting of all stakeholders at fixed periods
 Provide training on CDM aspects
CARBON PARTNERSHIP FACILITY
7
Training on CDM Operations Plans and Sub-ERPA Contracting
Key aspects of operations plan
Commissioning of SHP plants
Installation of metering equipments
Data recording and reporting
Quality control and quality assurance
CARBON PARTNERSHIP FACILITY
8
Training on CDM Operations Plans and Sub-ERPA Contracting
CPA preparation & inclusions
Selection of SHP project under REDP
Confirmation of CPA eligibility criteria under REDP PoA
Preparation of CPA DD as per the latest template
Hiring of DOE for validation
DOE validation site visit
Validation and inclusion of CPA into PoA by DOE
CARBON PARTNERSHIP FACILITY
9
Training on CDM Operations Plans and Sub-ERPA Contracting
CME level responsibilities in operations plan
Commissioning of SHP
plants
Site visit to construction site and
conformation with technical design
Installation of metering Guidance in selection of meters and
equipments
calibration process
Data recording
reporting
Design formats for data recording,
and
create PoA database, and provide
training in monitoring
Quality control
quality assurance
and Cross check CPA data with additional
evidences / PDD values
CARBON PARTNERSHIP FACILITY
10
Training on CDM Operations Plans and Sub-ERPA Contracting
CME level responsibilities in operations plan
Commissioning of SHP
plants
Construction and commissioning of
plant as per technical design
Procurement and installation at specific
Installation of metering
metering locations as per monitoring
equipments
plan
Data recording
reporting
and Data
collection
for
monitored
parameters at required frequency
Quality control
quality assurance
and Internal data check and submission to
CME
CARBON PARTNERSHIP FACILITY
11
Training on CDM Operations Plans and Sub-ERPA Contracting
Establishing CME - CDM Team
CARBON PARTNERSHIP FACILITY
12
Training on CDM Operations Plans and Sub-ERPA Contracting
Responsibilities of CDM team
CDM Manager
• Manage implementation of CDM PoA monitoring at CME level
• Ensure adequate training to staff from MOIT PMB and CPA implementers
• Resolve any issues arising in the implementation of CDM monitoring
plan
• Review the quality check and quality assurance plans of PoA periodically
• Review reports submitted by CDM advisor and database administrator
• Approve all the monitoring data for CER calculation
CARBON PARTNERSHIP FACILITY
13
Training on CDM Operations Plans and Sub-ERPA Contracting
Responsibilities of CDM team
CDM Advisor
• Carry out regular inspection to the power plants
• Assist project developers in implementing the CDM
monitoring plan at their plants
• Provide proper training on CDM monitoring to plant
operators
• Cross check the monthly data reported by the project
developer with the hard copy records at the plant during site
visit
CARBON PARTNERSHIP FACILITY
14
Training on CDM Operations Plans and Sub-ERPA Contracting
Responsibilities of CDM team
Database administrator
• Create central PoA level database with all CPA level data
• Ensure that the database is free of duplicate records
• Check if data given by CPA implementers are complete
• Update the monthly monitoring data submitted by CPA implementers
into the database
• Generate reports on SHP status, energy generation, etc, based on latest
data
CARBON PARTNERSHIP FACILITY
15
Training on CDM Operations Plans and Sub-ERPA Contracting
Understanding PoA database management
Central REDP
PoA Database
CPA 1
CPA 2
CPA 3
Hydro power
plant data
Hydro power
plant data
Hydro power
plant data
CDM monitoring
data
CDM monitoring
data
CDM monitoring
data
CARBON PARTNERSHIP FACILITY
16
Training on CDM Operations Plans and Sub-ERPA Contracting
Understanding CPA level monitoring
Measurement of
electricity produced
Electricity meter
Plant operation staff
Verification &
calculation of CER
Monitoring officer
CARBON PARTNERSHIP FACILITY
CPA database
17
Training on CDM Operations Plans and Sub-ERPA Contracting
Understanding Electricity Metering at site
Grid
Main meter
Secondary meter
Internal plant loads
Transformer
Generator
CARBON PARTNERSHIP FACILITY
18
Training on CDM Operations Plans and Sub-ERPA Contracting
Metering standards, accuracy & calibration requirements
The picture of typical two-way energy meter:
All the meters installed must be in compliance with IEC 62053-22
standards.
CARBON PARTNERSHIP FACILITY
19
Training on CDM Operations Plans and Sub-ERPA Contracting
Metering standards, accuracy & calibration requirements
No.
Meter
Type
Accuracy level
1
Main meter
Electronic, two way
± 0.2
2
Secondary meter
Electronic, two way
± 0.5
• Calibration must be carried out annually by EVN or by an authorized
company appointed by EVN for both meters.
• Re-calibration should be carried out within 10 days of either of the
following events:
 Measurement error between main meter and secondary meter is high
 Energy meter has been repaired due to component malfunction
CARBON PARTNERSHIP FACILITY
20
Training on CDM Operations Plans and Sub-ERPA Contracting
Quality control & quality assurance
What may go wrong during implementations ?
o Change in technical specification of power plant
o Different type / accuracy of electricity meter installed
o Data mismatch between electronic data submitted and hard copy
data
o Meters not calibrated on time
o Hard copy documents not maintained at power plant office
Make regular visit to power plant site and ensure all the above aspects
CARBON PARTNERSHIP FACILITY
21
Training on CDM Operations Plans and Sub-ERPA Contracting
Things to do…
At starting of project activity
 Design of data recording templates
 Design of CPA level and PoA level database formats
 Training to staff of CPA implementers
Checking for technical specifications of commissioned power plant
 Checking for proper installation of meters
 Collection of EPC contract and commissioning reports/ documents etc.
CARBON PARTNERSHIP FACILITY
22
Training on CDM Operations Plans and Sub-ERPA Contracting
Things to do …
During operation of SHPs
Regular site visit to power plants
 Collect monthly data from CPA implementers
 Check for calibration of meters
Creation and update of PoA level database
 Cross-check data provided by CPA
implementers
CARBON PARTNERSHIP FACILITY
23
Training on CDM Operations Plans and Sub-ERPA Contracting
Forms and Formats
A single format must be used across all CPAs
Example form
CARBON PARTNERSHIP FACILITY
24
Training on CDM Operations Plans and Sub-ERPA Contracting
Forms and Formats
Prepare and use
Example excel sheet
CARBON PARTNERSHIP FACILITY
25
Training on CDM Operations Plans and Sub-ERPA Contracting
Order of priority of reference documents
 Registered REDP PoA DD
Registered specific CPA DD
CDM Operations manual
REDP Operations manual, Jan 2009
Other training materials
CARBON PARTNERSHIP FACILITY
26
Training on CDM Operations Plans and Sub-ERPA Contracting
Questions & Discussions
CARBON PARTNERSHIP FACILITY
27