Transcript BSUP–PPP
DPR Wise Physical Progress on Site Statement showing Physical progress of all the sanctioned Schemes under BSUP , at Nagpur As of 22nd November 2013 Sr. No. Name of Project Sanction Du's Du's In Balance Du's Du's to Total Du's to Du's to ed DU's Complete progress not yet started : be be completed be d will be dropped against Relocate completed by sanctioned d March 2015 Du's A Remarks B C D E F G=B-F H I 1 Construction of 456 DUs and development of infrastructure in Sanjay Nagar & Zingabai Takli 456 53 113 90 200 256 0 In Situ Re development in existing structure : Work progress is slow because the slum is highly congested & due to rasistance from beneficiries 200 Du's are proposed to be dropped 2 Construction of 279 DU's and development of infrastructure in Jattatrodi, slum. 279 45 234 0 0 279 3 Construction of 1017 DU's and development of infrastructure for Borkar Nagar, Indira Nagar, Wanjara, slum 234 Du's are constructed at Nara Nari , work Started proposal submitted for SLSC Approval 1017 155 402 460 0 1017 120 In Situ Re development in existing structure : 120 Du's to be relocated and constructed at Dhammadeep Nagar :Work Started: Praposal submitted for SLSC Approval 4 Construction of 365 DU's and development of infrastructure for Gopal Nagar &Bh Anand Kau 365 5 Construction of 219 DU's and development of infrastructure for Panch Zopda . 219 54 56 109 0 219 0 6 Construction of 630 DU's and development of infrastructure for Savitribai Fule Nagar, Adivasi Toli 630 25 100 0 505 125 0 959 931 705 2261 305 39 54 272 0 365 185 In Situ Cluster : 185 Du's to be relocated and constructed at Dhammadeep Nagar : Work Started : Proposal submitted for SLSC Approval A Total 2966 371 In Situ Cluster : 54 Beneficiries have been handed over completed house . Another 56 beneficiries have been shifted to transit . Now 3rd and 4th Cycle of shifting is still pending but would be completed by mission period . At Sawatribai phule nagar , the ULC land was awarded to orignal owner by high court Order. 505 Du's to be dropped DPR Wise Physical Progress on Site Statement showing Physical progress of all the sanctioned Schemes under BSUP , at Nagpur As of 22nd November 2013 Sr. Name of Project Sanction No. Du's Du's In Balance Du's Du's to Total Du's to Du's to be be completed be dropped against Relocate completed by sanctioned d March 2015 Du's ed DU's Complete progress not yet started : d will be Remarks New Projects 7 850 new DUS in Sravasti Nagar, 850 0 100 570 180 670 0 work orders issued and work has Sanjay Nagar & Sewadal Nagar 8 376 New Dus in Bezanbaug II started . The bidder for 180 Du's at 376 0 75 301 0 376 0 Srawasthi Nagar has refused to work . (Gautam Nagar) and Lumbini Nagar 9 360 New Dus in New Pandharabodi Within short time it will be difficult to 360 39 30 291 0 360 0 call tenders hence proposed to be dropped . B Total 1586 39 205 1162 180 1406 0 BSUP-PPP Projects 10 Construction of 1694 Du's on 1694 0 0 0 1694 0 0 Initially work of 544 Du's started but Relocation site now the work is stopped and decision to be taken to drop the project C D Total 1694 Total (A+B+C) 0 0 6246 410 1164 0 1694 2093 2579 3667 0 0 305 Physical -Old Projects Sanctioned in 2008-09 Sr. No 1 2 Name of Project Work In Progress Balance Dwelling Unit 1525.00 8 45 53 10 103 113 290 0 290 1242.23 45 234 0 New Strategy 45 150 171 New Strategy Old Strategy Old Strategy Total 317 174 160 1017 5688.00 62 0 48 155 86 0 166 402 169 120 0 460 New Strategy Old Strategy Total 530 100 630 3744.00 25 0 25 0 100 100 505 0 505 185 180 365 New Strategy Old Strategy 2685.00 0 39 39 0 54 54 185 87 272 219 Old Strategy 1061.06 54 56 109 15945.29 371 959 1636 Old Projects Project 01 Sanjay Nagar Zingabai Takli Total 3 4 5 6 7 8 9 Project 02 Jat Tarodi - 2 Project 03 Indira nagar (Nr martin nagar) Indiramata nagar Borkar Nagar,Basod Mahalla Wanjra ( North Along Road) Project 04 Savitribai Phuley Nagar Adivasi Gondtoli Project 05 10 Bh Anand Kaushalayan nagar 11 Gopal Nagar(East of Dipty Signal) Total Project 06 12 Panch Zopada A: Total Sanctioned Units Scheme/ Strategy 308 148 456 New Strategy Old Strategy 279 Old Strategy 366 2966 Approved DU's project Cost Completed Physical–PPP –BSUP Scheme /New Projects (130th CSMC) Sr. No Name of Project Sanctioned Units Scheme/ 360 New Strategy Strategy Approved DU's Work In Balance project Complete Progress Dwelling Cost d Unit New projects Project 07 13 New Pandhrabodi 1978.64 39 30 291 Project 08 14 Sewadal Nagar 430 New Strategy 0 75 355 15 Sanjay Gandhi Nagar 240 New Strategy 0 25 215 16 Srawasthi Nagar 180 New Strategy 0 0 180 0 100 750 Total 850 5078.97 Project 09 17 Lumbini Nagar 226 New Strategy 0 50 176 18 Bezonbagh 150 New Strategy 0 25 125 Total B:Total 19 PPP - BSUP Projects 376 2806.47 0 75 301 1586 9864.08 39 205 1342 11672.00 0 0 1694 11672.00 0 0 1694 410 1164 4672 1694 C:Total 1694 TOTAL (A+B+C) 6246 Old Strategy