Transcript BSUP–PPP

DPR Wise Physical Progress on Site
Statement showing Physical progress of all the sanctioned Schemes under BSUP , at Nagpur As of 22nd November 2013
Sr.
No.
Name of Project
Sanction
Du's
Du's In
Balance Du's Du's to Total Du's to Du's to
ed DU's Complete progress not yet started :
be
be completed
be
d
will be
dropped
against
Relocate
completed by
sanctioned
d
March 2015
Du's
A
Remarks
B
C
D
E
F
G=B-F
H
I
1 Construction of 456 DUs and
development of infrastructure in
Sanjay Nagar & Zingabai Takli
456
53
113
90
200
256
0
In Situ Re development in existing
structure : Work progress is slow because
the slum is highly congested & due to
rasistance from beneficiries 200 Du's are
proposed to be dropped
2 Construction of 279 DU's and
development of infrastructure in
Jattatrodi, slum.
279
45
234
0
0
279
3 Construction of 1017 DU's and
development of infrastructure for
Borkar Nagar, Indira Nagar, Wanjara,
slum
234 Du's are constructed at Nara Nari ,
work Started proposal submitted for
SLSC Approval
1017
155
402
460
0
1017
120 In Situ Re development in existing structure
: 120 Du's to be relocated and constructed
at Dhammadeep Nagar :Work Started:
Praposal submitted for SLSC Approval
4 Construction of 365 DU's and
development of infrastructure for
Gopal Nagar &Bh Anand Kau
365
5 Construction of 219 DU's and
development of infrastructure for
Panch Zopda .
219
54
56
109
0
219
0
6 Construction of 630 DU's and
development of infrastructure for
Savitribai Fule Nagar, Adivasi Toli
630
25
100
0
505
125
0
959
931
705
2261
305
39
54
272
0
365
185 In Situ Cluster : 185 Du's to be relocated
and constructed at Dhammadeep Nagar :
Work Started : Proposal submitted for
SLSC Approval
A
Total 2966 371
In Situ Cluster : 54 Beneficiries have been
handed over completed house . Another 56
beneficiries have been shifted to transit .
Now 3rd and 4th Cycle of shifting is still
pending but would be completed by mission
period .
At Sawatribai phule nagar , the ULC land
was awarded to orignal owner by high court
Order. 505 Du's to be dropped
DPR Wise Physical Progress on Site
Statement showing Physical progress of all the sanctioned Schemes under BSUP , at Nagpur As of 22nd November 2013
Sr.
Name of Project
Sanction
No.
Du's
Du's In
Balance Du's
Du's to
Total Du's to
Du's to
be
be completed
be
dropped
against
Relocate
completed by
sanctioned
d
March 2015
Du's
ed DU's Complete progress not yet started :
d
will be
Remarks
New Projects
7 850 new DUS in Sravasti Nagar,
850
0
100
570
180
670
0
work orders issued and work has
Sanjay Nagar & Sewadal Nagar
8 376 New Dus in Bezanbaug II
started . The bidder for 180 Du's at
376
0
75
301
0
376
0
Srawasthi Nagar has refused to work .
(Gautam Nagar) and Lumbini Nagar
9 360 New Dus in New Pandharabodi
Within short time it will be difficult to
360
39
30
291
0
360
0
call tenders hence proposed to be
dropped .
B
Total 1586
39
205
1162 180
1406
0
BSUP-PPP Projects
10 Construction of 1694 Du's on
1694
0
0
0
1694
0
0
Initially work of 544 Du's started but
Relocation site
now the work is stopped and decision
to be taken to drop the project
C
D
Total 1694
Total (A+B+C)
0
0
6246 410 1164
0 1694
2093 2579 3667
0
0
305
Physical -Old Projects Sanctioned in 2008-09
Sr. No
1
2
Name of Project
Work In
Progress
Balance
Dwelling
Unit
1525.00
8
45
53
10
103
113
290
0
290
1242.23
45
234
0
New Strategy
45
150
171
New Strategy
Old Strategy
Old Strategy
Total
317
174
160
1017
5688.00
62
0
48
155
86
0
166
402
169
120
0
460
New Strategy
Old Strategy
Total
530
100
630
3744.00
25
0
25
0
100
100
505
0
505
185
180
365
New Strategy
Old Strategy
2685.00
0
39
39
0
54
54
185
87
272
219
Old Strategy
1061.06
54
56
109
15945.29
371
959
1636
Old Projects
Project 01
Sanjay Nagar
Zingabai Takli
Total
3
4
5
6
7
8
9
Project 02
Jat Tarodi - 2
Project 03
Indira nagar (Nr martin nagar)
Indiramata nagar
Borkar Nagar,Basod Mahalla
Wanjra ( North Along Road)
Project 04
Savitribai Phuley Nagar
Adivasi Gondtoli
Project 05
10 Bh Anand Kaushalayan nagar
11 Gopal Nagar(East of Dipty Signal)
Total
Project 06
12 Panch Zopada
A: Total
Sanctioned
Units
Scheme/
Strategy
308
148
456
New Strategy
Old Strategy
279
Old Strategy
366
2966
Approved
DU's
project Cost Completed
Physical–PPP –BSUP Scheme /New Projects (130th CSMC)
Sr. No
Name of Project
Sanctioned
Units
Scheme/
360
New Strategy
Strategy
Approved
DU's
Work In Balance
project Complete Progress Dwelling
Cost
d
Unit
New projects
Project 07
13
New Pandhrabodi
1978.64
39
30
291
Project 08
14
Sewadal Nagar
430
New Strategy
0
75
355
15
Sanjay Gandhi Nagar
240
New Strategy
0
25
215
16
Srawasthi Nagar
180
New Strategy
0
0
180
0
100
750
Total
850
5078.97
Project 09
17
Lumbini Nagar
226
New Strategy
0
50
176
18
Bezonbagh
150
New Strategy
0
25
125
Total
B:Total
19
PPP - BSUP Projects
376
2806.47
0
75
301
1586
9864.08
39
205
1342
11672.00
0
0
1694
11672.00
0
0
1694
410
1164
4672
1694
C:Total
1694
TOTAL (A+B+C)
6246
Old Strategy