OVERVIEW – SUNDANCE WIND PROJECT
PROPOSED $600 MILLION INVESTMENT NEAR TUMBLER & CHETWYND
Ron Percival
Avro Wind Energy Inc.
October, 2014
PRESENTATION OVERVIEW
i.
Proposed $600 Million near-term
investment in Tumbler Ridge /
Chetwynd region
ii. Who Is EDF EN Canada?
iii. Overview Sundance Wind Project
iv. Environmental Assessment
Activities
v. Visual Simulation for Sundance
Project
EDF EN: A LEADER IN RENEWABLE ENERGY
An expertise in multiple segments
An international footprint
18 countries
~ 3,050 employees
+ Biomass
Biogas
+ Sea Energy
+ Concentrated
Solar Power
WIND ENERGY
SOLAR ENERGY
onshore & offshore
pv
Other
North America
Europe
Africa / Middle-East /
India
A leading position in its business
Integrated skills
Present on all the renewable value chain
Generation activity
 6,611 MW gross installed
Among the top 10
global players
 1,986 MW gross under construction*
 11,1 TWh of green electricity generated in 2013
Development
Construction
Generation
Operations &
Maintenance
Complementary activities
 2,310 MW developed, built and sold
 9,039 MW in operation and maintenance*
Key figures at 31 December 2013
MW gross : capacity of power plants in which EDF EN is shareholder
* For own account and for third party
|
|
EDF EN CANADA
MORE THAN $3 BILLION INVESTED – WITH ANOTHER POSSIBLE
$1.8 BILLION FOR BC PEACE
1,304 MW – Wind PPA
• 774 MW Under Construction
• 530 MW Complete & Operating
Operations and Maintenance in
Canada:
864MW – Wind
300MW – Solar MW
720 MW of Wind in BC South
Peace Region in permitting or
shovel ready
More than $3 Billion
Investment in Canada
400 MW
70 MW
27 MW
250 MW
300 MW
1003 MW
88 MW
189.5 MW
Wind, Under
Development
72 MW
EDF EN Canada contracted Avro Wind Energy to help
develop wind projects in BC Peace River Region. Avro has
carried interest in the projects.
Wind, Under
PPA/Construction
23 MW
Solar, In
Operation
O&M, Under
Contract
OVERVIEW – SUNDANCE WIND PROJECT
 Generation capacity up to 250 MW
 Potential investment of more than $600 Million
 Jobs:

Approximately 250 during construction

Approximately 10 – 15 during operations
 Build and Permitting Schedule:
 Build early as 2016 subject to Power Purchase
Agreement with BC Hydro.

EA Certificate expected in 2015

First open house – June 2013

Supportive engagement with Treaty 8 First Nations
 Project located on Crown land, approximately 20km
north of Tumbler Ridge.
 Near D-CAT transmission, proposed Site C dam, and
ramping gas electrical load
ON-GOING & UPCOMING ENVIRONMENTAL
ASSESSMENT ACTIVITIES
EDF EN Canada and Avro are working closely with First Nations, stakeholders, and local government to
ensure EA studies are comprehensive, transparent and sensitive to local and regional concerns
On-going Activities
• First Nations, Public & Stakeholder Consultation
• BC Environmental Assessment process – submission for
Application review expected in early 2015
• Analysis of local features
Some Upcoming Activities
• Fall Bat surveys
• Reporting on results of field studies, including Archaeological
Resources, Furbearers, Ungulates (including Caribou), Bears,
Fish and Fish Habitat, Vegetation and Ecosystems, Amphibians
and Reptiles, Bats, Birds, Terrestrial Invertebrates, Community
Infrastructure, Visual Resources, Land and Land Use,
Communication Systems, Human Health, Terrain Stability, and
Hydrology
VISUAL SIMULATIONS – SUNDANCE MOOSE LAKE
I October 1 2013
VISUAL SIMULATIONS – SUNDANCE HWY 52
I October 1 2013
VISUAL SIMULATIONS – SUNDANCE GWILLIM LAKE
I October 1 2013
HOW CAN YOU HELP – AND BENEFIT?
 Help us deliver message to BC Government and BC Hydro:
 Tumbler Ridge and Chetwynd are endowed with “world class” wind energy
resource.
 Let BC Government and BC Hydro know the world’s leading renewable power
developers, owners and operators (like EDF EN Canada) are here already:
 Making regional investments near Tumbler Ridge and Chetwynd; and
 Developing low cost power with social license for the benefit of all British
Columbians
 Three Peace Region EDF EN Canada wind projects can build as early as 2016.
 Potential for near term $1.8 Billion regional investment.
 Opportunities for local construction contracts and long term careers in operations
and maintenance.
QUESTIONS?
David Warner
EDF EN Canada Inc.
416.216.5883
[email protected]
www.edf-en.ca
www.sundancewindproject.ca
Ron Percival
Avro Wind Energy
250.285.2304
[email protected]