Transcript Slide 1

INDIANA POWER OF WIND
COALITION
Regulatory Flexibility Committee
Strategies for Procuring New Generation
September 18, 2013
INDIANA POWER OF WIND
COALITION
The Challenge
• There is no “free market” for procurement of energy and resources.
• Utilities in regulated states are vertically integrated monopolies with a
franchise agreement that entitles them to serve customers within the
franchise area.
• Currently, utilities develop integrated resource plans (IRP) which identify
supply needs for customers.
• Generally, utilities fulfill energy/capacity shortfall through request for
proposals (RFP) and the utility typically chooses themselves.
INDIANA POWER OF WIND
COALITION
Other Challenges
• Self build options don’t always take into account all transmission and
interconnection costs.
• Risk of construction delay and cost overruns are often not accounted for in
self build options.
• Utilities have the ability to recover additional costs from ratepayers.
• Independent power producers (IPP) provide an all-in, binding cost when
responding to request for proposals.
• This includes all costs – including transmission and interconnection costs.
• If the project is completed over budget, the risk is borne by the IPP as
opposed to the ratepayer.
INDIANA POWER OF WIND
COALITION
Example of Utility Share of Supply Resources
• Approx. 95% of all electricity comes from generation owned by the IOUs
Utility
Total
Resources
(MW)
AEP
Duke
IPL
NIPSCO
Vectren
5,279
6,830
3,353
3,422
1,498
Owned
PPA
% Owned
Resources Resources
Resources
(MW)
(MW)
5,012
6,722
3,053
3,322
1,288
267
108
300
100
210
94.9%
98.4%
91.1%
97.1%
86.0%
SOURCE: 2011 Utilities IRPs
INDIANA POWER OF WIND
COALITION
Comparison of Self-Build to Third Party Supply
• Utilities receive no rate of return on power purchase agreement (PPA) and
as a result forfeit potential returns for shareholders.
• Lower cost to ratepayer for power purchase agreement, however this may
not be the successful proposal.
Utility Self-Build – 100 MW
Thermal Plant1 (excludes
operating costs)
$427,488,000
Resource
Investment
8%
Rate of Return
$ 34,199,040
Total Return
Power Purchase Agreement – 100
MW Plant2
Current
structure
leads to
inefficient
outcomes
$336,384,000
Purchase
Agreement Cost
0%
Rate of Return
$0
Total Return
1 Lazard Levelized Cost of Energy Analysis Version 6.0, June 2012. Assumes Gas Combined Cycle at 40%
capacity factor for 20 years at $61/MWh.
2 Lazard Levelized Cost of Energy Analysis Version 6.0, June 2012. Assumes Wind at 40% capacity factor
for 20 years at $48/MWh.
INDIANA POWER OF WIND
COALITION
Example of Competitive Procurement Proposal
• Allowing an earned rate of return still provides a lower cost to ratepayer.
Alternative Procurement – Utilized Wind
PPA
$336,384,000
Resource Investment
8%
Rate of Return
$ 26,910,720
Total Return
Utility Self-Build – 100 MW
Thermal Plant1 (excludes
operating costs)
$427,488,000
Resource
Investment
8%
Rate of Return
$ 34,199,040
Total Return
Ratepayer Savings:
$98,392,320
Power Purchase Agreement – 100
MW Plant2
Current
structure
leads to
inefficient
outcomes
$336,384,000
Purchase
Agreement Cost
0%
Rate of Return
$0
Total Return
INDIANA POWER OF WIND
COALITION
Benefits
• Ensure ratepayer is served at lowest, efficient cost. Allow utility sector to balance
the utility shareholder interests with the ratepayer’s desire for low cost energy.
• Reduce ratepayer exposure to cost overrun risk.
• Does not change the regulatory process that currently exists in each state.
• Cooperative working relationships between utilities and independent power
producers.
• Alternative for utilities if capital constrained due to generation fleet
retirement/retrofit costs, transmission expansion costs, and other system
improvement costs. Leverage third parties to provide capital needed to maintain
supply adequacy.
• Provide appropriate human resources to support utilities in building new resources.
Some utilities no longer have in-house capability for design, project management,
and commissioning of new generation resources. The projected utility attrition rate
is also a potential concern.
INDIANA POWER OF WIND
COALITION
Questions/Follow Up
Speakers:
Jason Minalga
Consultants:
Tony Samuel
Manager, Regulatory Affairs
Invenergy
312-582-1500
[email protected]
President
Samuel Solutions
317-403-2339
[email protected]