Alpha Taxiway Rehabilitation Improvement Project
Download
Report
Transcript Alpha Taxiway Rehabilitation Improvement Project
Yakima Air Terminal
ALPHA TAXIWAY REHABILITATION
IMPROVEMENT PROJECT
PRESENTATION OVERVIEW
Project Overview
Project Schedule
Impacts
Project Status
Questions
PROJECT OVERVIEW
The Yakima Air Terminal has received an $11,000,000 grant. The
grant is to:
Resurface and widen Alpha Taxiway, Taxiway Connectors A1-A5, and
portions of Bravo and Charlie Taxiways;
Resurface airfield pavement between the north taxiway edge line to the
non-movement line;
Replace the existing MITL system with LED MITL, including new conduit,
fixtures, and regulator;
Replace all existing directional and hold short signs; and
Correct several markings not meeting FAA standards.
PROJECT OVERVIEW
PROJECT OVERVIEW
PROJECT SCHEDULE
Expected construction START DATE
June 22, 2015:
Phase 1: June 22, 2015 – July 17, 2015
Phase 2: July 20, 2015 – July 31, 2015
Phase 3: August 1, 2015 – August 14, 2015
Phase 4: August 15, 2015 – September 4, 2015
Phase 5: September 8, 2015 – September 29, 2015
Phase 6/7: September 30, 2015 – October 30, 2015
PROJECT OVERVIEW – PHASE 1
IMPACTS
Phase 1: June 22, 2015 – July 17, 2015
Ramp Closures.
McCormick
West, and Plath Hangar.
Partial Ramp Closures.
Fuel
Tank/House and McCormick Air Center.
Temporary Runway 9/27 Closure for work within the
Runway Safety Area.
On-going construction activities and vehicle traffic on
service roads and ramps.
PROJECT OVERVIEW – PHASE 2
IMPACTS
Phase 2: July 20, 2015 – July 31, 2015
Ramp Closures.
Airlift Northwest, FedEx Air Cargo and Airport Maintenance Building.
Partial Ramp Closures.
McCormick Air Center and Private Hangars (formerly Noland-Decoto).
Temporary Runway 9/27 Closure for work within the Runway
Safety Area.
On-going construction activities and vehicle traffic on
service roads and ramps.
PROJECT OVERVIEW – PHASE 3
IMPACTS
Phase 3: August 1, 2015 – August 14, 2015
Ramp Closures.
GE Aviation, West Itinerant Ramp, Med Assets, and West Terminal Apron
Ramp.
Partial Ramp Closures.
Private Hangars (formerly Noland-Decoto).
Temporary Runway 9/27 Closure for work within the Runway
Safety Area.
On-going construction activities and vehicle traffic on service
roads and ramps.
PROJECT OVERVIEW – PHASE 4
IMPACTS
Phase 4: August 15, 2015 – September 4, 2015
Ramp Closures.
East Terminal Apron Ramp.
Partial Ramp Closures.
East Itinerant Ramp.
Runway 4/22 and Bravo Taxiway Closed.
Temporary Runway 9/27 Closure for work within the Runway
Safety Area.
On-going construction activities and vehicle traffic on service
roads and ramps.
PROJECT OVERVIEW – PHASE 5
IMPACTS
Phase 5: September 8, 2015 – September 29, 2015
Ramp Closures.
No Ramps Closed.
Alternate routes required for: Cub Crafters, McAllister Museum,
Advanced Medical Systems, and South Air Park.
Temporary Runway 9/27 Closure for work within the Runway
Safety Area.
On-going construction activities and vehicle traffic on
service roads and ramps.
PROJECT OVERVIEW – PHASE 6
IMPACTS
Phase 6: September 30, 2015 – October 30,
2015
Partial Ramp closures denoted by barricades.
Runway 4/22 closed intermittently.
On-going construction activity and vehicle traffic on service
roads and taxiways.
PROJECT OVERVIEW – PHASE 7
IMPACTS
Phase 7: September 30, 2015 – October 30,
2015
Not expecting any closures, however a schedule will be
provided of the impacted areas to minimize air traffic and
vehicle operations within the work areas.
On-going construction activities and vehicle traffic on
service roads and ramps.
OPERATIONS DURING CONSTRUCTION
If at all possible, avoid construction areas.
Please plan all operations around construction to the maximum
extent possible.
If there are known operations that will be impacted by the proposed
schedule, please let us know.
The Airport Management will provide NOTAMs.
Do not travel (plane or car) across barricades delineating closed
pavement.
Do not provide direction to the contractor unless there is an
emergency.
QUESTIONS
Robert Peterson
[email protected]
Office: (509) 575-6149 (#7)
Cell: (509) 833-0898
Kris Yalovich
[email protected]
Office: (509) 575-6149 (#7)
Stephanie Ray, PE
[email protected]
(509) 966-7000
Michael Battle, PE
[email protected]
(509) 966-7000