Transcript Slide 1

Legacy Waste Retrieval And Treatment Processing
Methods At RSRL Harwell Site
Author : Marc Rigby
Presented by : Malcolm Adam
28th May 2009
History Of The Harwell Site
• Harwell was the birthplace of the UK`s Civil
Nuclear Programme
• Activities encompassed all aspects of the
nuclear cycle over 50 years of R&D
• Since the early 1990`s the site has been
decommissioning redundant nuclear facilities
and processing legacy waste into a passively
safe state
• Overall aim is to return the site to brown field
status by 2040
Site Facilities
• Five research fission reactors including
two material test reactors
• One fusion reactor
• Accelerators and radioactive handling
facilities and laboratories
Legacy Waste
• Experimental rigs – mechanically size
reduced
• Bench sweepings and swarf
• Manipulator parts
• Fuel cladding
• Grossly contaminated materials from
active cells or from research reactors
Solid Waste Storage Tube Facility
• Facility constructed between 1952 and 1974
• Long-term storage of RH-ILW waste from on-site
facilities
• Facility filled to capacity by 1990
• Studies carried out in late 1980`s showed that waste
cans within the storage tubes had degraded and
required treatment
• Construction of a series of Head End Cells and Vault
Store for processing recovered waste
• Programme started in 1990`s to refurbish the facility and
recover the waste cans for processing into NDA-RWMD
approved containers
Legacy Waste Retrieval Processes At
RSRL Harwell Site
• Remote Handling Machine (RM1) recovers waste cans
from storage tubes into transfer drums
• RM1 equipped with active handling cell and remote grab
– modular design
• Drums exported in shielded lead flask to Head End Cells
for processing into 500 litre stainless steel drums
• Packaging process involves assay, sorting and loading
of waste into drums
• Full drums placed into interim storage pending
encapsulation
• 10,000 waste cans are to be recovered, processed and
encapsulated into a passively safe form by 2020
Retrieval Machine 1 &
Head End Cell
Current Status Of Facility
• 30% of RH-ILW has been recovered using
remote handling retrieval machines
• 20% of waste recovered has been debris
• All waste is expected to have been recovered by
2014
• Overall aim is to decommission and demolish
the facility
• Waste retrieval facility will be decommissioned
leaving only the vault store
Waste Immobilisation
• 500 litre drums recovered from
interim storage for addition of
grout mix
• Staged processing involving
–
–
–
–
Outer and inner lid removal
Grout addition
24 hour curing
Grout capping and further
curing
– Lidding and return to interim
storage
• Cement encapsulation widely
used within UK at all
decommissioning sites
Immobilisation Of Radium
Contaminated Waste
• Radon gas emanations occur as part of the radium
decay process and must be controlled
• Studies carried out investigate different encapsulation
techniques using grout
• Acceptable results for small particulate but unacceptable
for larger items due to voidage
• New polymer-based encapsulation method developed
which proved greatly superior to cementation for radium
containing wastes
• Produces a robust block which greatly improves
attenuation to radon emanations due to minimal voidage
Sectioned Grout & Polymer
Encapsulated Cans Trials Comparison
Future Waste Arisings &
Treatment Methods
• Cementation remains the proposed encapsulation
method for Harwell solid waste
• Occassionally not acceptable for certain wastes requiring
additional treatments (WRAT)
• An example is GLEEP fuel which has been highlighted
as WRAT due to corrosion concerns within the 500 litre
drums
• Polymer proposed for immobilising GLEEP fuel rods
within their current 23 litre storage cans prior to grouting
in 500 litre drums
• Results indicate this method to be acceptable for
meeting NDA RWMD requirements