Kakatiya 1x600 MW Generator Stator Lifting on 11.06.2014

Shri Shiva Kumar Chief Engineer / KTPP TGGENCO breaking coconut on the occasion of Stator Lifting.

Shri M V Keshavraj AGM BHEL Site breaking coconut on the occasion of Stator Lifting.

Lifting of Generator Stator commenced at 0940 Hrs.

Stator Lifting under progress.

Stator entering TG floor.

Stator Placed on Pedestals at 1100 Hrs

TGGENCO officials along with BHEL staff after Stator Lifting